| 1 | Jungle clearance in borrow area , building premises,flanks and slopes of the roads,canals and embankments by removing the grass and the jungle bushes from top including weeding out shrubs,roots and levelling etc. complete as per direction of E/I.(Part - B-5.1.3.1,Patr - A-2.02) |
| 2 | E/w in stripping by hydraulic M/C in grade A & B type of soil including morroum soil, soil mixed with kankar, pebbles,boulders upto 300 mm size and disposal of the same along with all organic materials in the country side beyond 150 M upto 500 M in all by tipper including construction & maintenance of haul road etc. complete as per specification and direction of E/I.(5.1.6.1) |
| 3 | Earthwork in excavation and filling of canal by the hydraulic excavator as per designed section in all kinds of soil, soil mixed with kankar, pebbles and boulders upto 300 mm size and disposal of spoil upto 10 m with all lifts all complete as per s[ecification and direction of E/I. ( 7.1.43.1) |
| 4 | E/W in excavation in canal by the hydraulic excavator as per designed section in all kinds of soil, soil mixed with kankar, pebbles and boulders upto 300 mm size and disposal of spoil upto 500 m with all lifts by tipper including construction and maintenance of haul road all complete as per specification and direction of E/I. ( 7.1.43.2) |
| 5 | Extra for earth work in marshy, slushy and daldal soil (vide classification of soil item - F) all complete as per specification and direction of E/I. ( 7.1.11) |
| 6 | Use rate of 10 H.P. Diesel Pumpset including diesel, mobil, Operator etc all complete.(PM-29) |
| 7 | Supplying and laying sand filter on slope of the dam as per design, drawing, with watering and compaction including the cost of materials, royalty and all taxes etc. but excluding the cost of carriage all complete as per specification and direction of E/I. (5.6.5) |
| 8 | Supplying and laying Stone metal (20mm to 63mm) on the slope of dam -do- as per specification and direction of E/I. (WRD 5.6.7 ) |
| 9 | Supplying and laying (properly as per design and drawing) rip -rap with good quality of boulder duly packed including the cost of materials, royalty all taxes etc. but excluding the cost of carriage as per specification and direction of E/I. (5.6.8) |
| 10 | Supplying and laying boulders in rock toe, heel trenches of the dam as per design, drawing including the cost of materials, royalty and all taxes etc. but excluding the cost of carriage all complete as per specificatins and direction of E/I.(Item No.5.6.4) |
| 11 | Providing and laying P.C.C. or R.C.C. M 150 with nominal mix of (1:2:4) in various components on slope with approved quality of 20 mm graded coarse aggregate of required grade as per design and approved quality of sand of requisite F.M. (2.5 to 3.0) washed and screened excluding cost of shuttering or formwork as well of reinforcement, its cutting, bending, binding and placing but including necessary tools and plants and vibrating, curing, royalty all taxes etc. complete job as per specification and direction of E/I .(5.3.1.2) |
| 12 | Providing shuttering including strutting proping etc. and its removal after use in foundation as per specification and direction of E/I.(7.3.18) |
| 13 | Providing rough dressed random rubble stone masonry in cement mortar (1:4) in foundation with approved quality of coarse sand of requisite F.M (2.5 to 3) washed and screened with raking out joints curing, scaffolding and its removal wherever required including royalty and all taxes etc. complete job as per specifications and direction of E/I.(5.2.28 ) |
| 14 | Providing rough dressed random rubble stone masonry in cement mortar (1:4) in super-structure with approved quality of coarse sand of requisite F.M (2.5 to 3) washed and screened with raking out joints curing, scaffolding and its removal wherever required including royalty and all taxes etc. complete job as per specifications and direction of E/I.(Item No.5.2.31) |
| 15 | Providing 25mm thick cement plaster (1:4) with approved quality of sand of requisite F.M (2.5 to 3.0) washed and screened including curing, scaffolding wherever required and its removal , royalty and all taxes etc. complete job as per specifications and direction of E/I.(5.7.12) |
| 16 | Earth work in excavation of foundation trenches in ordinary soil (Vide classification of soil item-A) and disposal of excavated earth so obtained (50M. away from the edge of the trenches) with initial lead of 150M and initial lift of 1.5M as per specification and dir- ection of E/I.(5.1.14.1) |
| 17 | Dismantling of structures (Dismantling of existing structures like culverts, bridges, retaining walls and others structures comprising of masonry, cement concret, wood work, steel work including T&P and scaffolding wherever necessary, sorting the Dismantled material,disposal of unserviceable materil and stacking the serviceable materil with all lifts and lead of 1000 metres) Scarping Plaster in Lime or Cement Mortar from Brick/ Stone Masonry (Part - A-2.04(viii)) |
| 18 | Dismantling of structures (Dismantling of existing structures like culverts, bridges, retaining walls and others structures comprising of masonry, cement concret, wood work, steel work including T&P and scaffolding wherever necessary, sorting the Dismantled material,disposal of unserviceable materil and stacking the serviceable materil with all lifts and lead of 1000 metres) Scarping Plaster in Lime or Cement Mortar from Brick/ Stone Masonry (Part - A-2.04(iii)(I)(B)) |
| 19 | Labour charge for taking out disturbed boulder from boulder pitching or rip rap or rock toe etc. and cleaning the surface and stacking the same within a lead of 100M as per specification and direction of E/I (WRD-7.7.41 ) |
| 20 | Carriage of materials |
| 21 | (i) Cement – Lead 9 km(s) + 1 km(k) |
| 22 | (ii) Sand – Lead 11 km(s) + 1 km(k) |
| 23 | (iii) Stone Chips – Lead 34 km(s) + 1 km(k) |
| 24 | (iv) Stone Metal – Lead 34 km(s) + 1 km(k) |
| 25 | (v) Boulder – Lead 34 km(s) + 1 km(k) |
| 26 | After adding GST @18% on total estimated value the total estimated amount is |
| 27 | Labour Cess @1% on above total estimated amount Please Enable Macros to View BoQ information |