| 1 | Supply & fix Cable jointing kit for 11 KV (Earthed) grade cable for indoor termination heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable of size 50-95 Sqmm, 3 core including taking down old u/s jointing kit complete all as specified and directed. |
| 2 | Supply and fixing in replacement pin type insulator porcelain with GI Spindle nut for 33 KVolts grade complete all as specified and directed. |
| 3 | M&L for earthing complete with steel earth plate eletrode 60cm x 60cm x6mm thick buried dirctly in ground vertically (earth pit not less than 2.25 mtr below ground level) with top edge of plat not less than 1.5 mtr below ground level connected to GI strip 32x6mm by means of bolts. nuts,check nuts and washers etc including protection pipe 15mm dia up to 7.5m length , provision the earth lead to earth connection in ther main distribution box with lugs and GI nuts,bolts, earthing shall be done all as per shown electrical plate No 3 of SSR part 1 Including neccessary excavation in disintergratedand hard soil and 20mm dia GI pipe with funel for watering PCC earth chamber 100mm thick precast RCC cover with suitable precast RCC frame and earth test point and testing in presence of Engr -in -Charge complete all as specified and directed. |
| 4 | M &L for Chemical earthing with copper earth plate 90x60cmx5mm & copper earth strip 32X6m all as per IS-3043 1987 all as specified or indicated including testing on completion and payment will be done only after complete testing and getting result of earthing less than 1 ohm. and gbfc (graphite-70% and alumina-30% ) material should be not less than 50 kg in weight also the PH Value of chemical compound must be in between 7 to 9 and weight of electrode must not be less than 12 kg complete all as specified and directed. |
| 5 | Supply and fixing in replacement lighting arrestor non linear resistance type line discharge current 10 KA height current 100 KA assembly suitable for 33 KV including all necessary clamps, nut, bolts and washers and connecting to earth with 32 x 6 mm GI Strip complete all as specified and directed. |
| 6 | Taking down the defective unserviceable transformer from existing site from pole and Sub Stn with the help of man power & chain pully block or by crane etc including dieconnecting all electrical and mechanical connections from the site and carrying to workshop for repair and replacement of old burnt u/s item including transporting of capacity 3150 KVA including transporting back after repair to the site where recieved complete all as specified and directed. |
| 7 | Repair/Maintinance of existing power transformer of capacity 3150 KVA (33/11 KV) by lifting the top cover taking out the HT/LT core and draining out the transformer oil in barral including cleaning the transformer chamber (body) inside and out side throughly with emery paper and cloth than checked the winding and other worn-out parts such as HV/LV coils silicor stamping and other connected items as Tap-changer, breather assembly etc and replacement of HT and LT coil and connected to existing serviceable strip by jointing with soldring and re insulated of cotton tape over strip including using insulating material like varnish to limb coil fire proof type and sleeves etc including lifting of core assembaly and by drying and baking of Insulating material in heating chamber in adequate temprature Reassembling the transformer LT/HT connection with help of soldering. Testing of transformer after repair complete testing of transformer after repair incl painting to the transformer with super enameled paint complete all as specified and directed.Note :- HV/LV coils and other connected items shall be measured & paid seperately. |
| 8 | Supply only for winding HT coil with DPC or enamelled copper wire/ of existing size & guage winding wire for winding the transformer coil incl insulating material complete all as specified and directed. |
| 9 | Supply only for LT coil winding with DPC or enamelled copper wire strip of existing size & guage winding for winding the transformer coil LT coil complete all as specified and directed. |
| 10 | Supply filling of transformer oil EHV as per IS 335 of 1993 Part II.Note :- (i) Oil shall be brought in the manufacture sealed contrainer (drum) and shall be kept in safe custody of Engineer-in-Charge.(ii) Contractor shall hand over the purchase voucher and manufacturer's test certificate to the engineer in charge.(iii) Di-electric strength shall not be less than 50 KV. |
| 11 | Old core removal and fixing the same |
| 12 | Supply only of insulating materials |
| 13 | Supply only gasket |
| 14 | Supply only of Silica gel breather assembly with silica gel cristal(2Kg) suitable for 3150 KVA transformer to air column of conservator tank complete all as specified and directed by Engineer-in-Charge. |
| 15 | Supply and fix in replacement of relay MiCOM P122 complete all as specified and directed. |
| 16 | M & L in replacement of Factory Made precast cable duct cover with two no perforations with bar of size 1150x450x100 mm , made of PCC 1:2:4, type B0, (using 12.5mm graded crushed stone aggregate), cover reinforced with 8mm dia TMT bars @ 100mm centre to centre both ways complete all as specified and directed. |
| 17 | Labour charges for servicing/overhauling/repairing & testing of all protection relays , CTs,PTs and 33KV VCB breaker 1250 A out door type, including all circuit control wiring complete all as specified and directed, follows:- (a) CTs primary current injection test . (CT Testing) (b) Ratio test of PTs (c) Protection relays testing through secondary current injection kit (Relay testing) (d) Voltmeter,ammeter functional tesing (e) Breaker tesing for tripping time, closing time , contact resistance , IR values and physically healthyness of Vaccum interuptor. |
| 18 | Taking out defective/wornout parts from 33 KV VCB at the time of overhauling and S&F in replacement, for the following complete all as specified and directed. (a) Closing coil |
| 19 | (b) Tripping Coil. |
| 20 | (c) Auxillary switch |
| 21 | (d) Spring charging motor assy |
| 22 | (e) PT Fuse |
| 23 | (f) Motor cutoff switch |
| 24 | (g) Breaker control switch |
| 25 | (h) Space heater |
| 26 | (J) Ammeter as per existng site |
| 27 | (K) Voltmeter as per existng site Please Enable Macros to View BoQ information |