| 1 | Re-joining one snapped LT conductor after removing damaged portion including Reshackling and conveyance of all materials complete. |
| 2 | Additional rate for refitting/redoing one Shackle Set, including reshacling one span, while renewing any type of LT pole. |
| 3 | Fiting One no MVT on existing cross arm including 2 nos end termination (for One phase) of any rating for 11 kV AB Cable |
| 4 | Fitting one Additional 75x40mm, 1.8m Channel cross arm in existing single pole including conveyance of materials. |
| 5 | Fitting one set (3No.) 11kV LA and giving connections excluding earthing. |
| 6 | Erection of Anchor clamp / dead end clamp for 11kV ABC of any size |
| 7 | Erection of suspension clamp for 11KV ABC of any size |
| 8 | Stringing of 11 kV Aerial bunched cable of size 3 x 120 + 1 x 95 sqmm with bare/insulated Messenger through existing poles |
| 9 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at standard distance (1.5m) away from the pole/structure in ordinary soil & backfilling the pit with 15cm alternate layer of charcoal, salt and sand up to 90cm from the bottom. including the cost of 20kg salt, 25kg charcoal, excluding supply of earth pipe. |
| 10 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 11 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 12 | Dismantling (without damage) LT stay including digging pit in all classes of soil and backfilling. |
| 13 | Fitting and providing one Strut using HT PSC pole including digging and back filling pit in ordinary soil. |
| 14 | Labour charges for loading HT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 15 | Fitting one set AB switch on existing DP, giving connection and drawing sufficient length of GI earthing leads to the ground for earthing, excluding provision of earthing. |
| 16 | Fitting one Additional2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP including conveyance of materials. |
| 17 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 18 | Fitting and erecting one HT PSC Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 19 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 20 | Transferring LT single phase 2/3 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 21 | Transferring LT three phase 4/5 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 22 | Transporting LT ABC by hired vehicle to a distance up to 5 km and carring up to 2 drum including loading and un loading using crane |
| 23 | Transporting Transformers by hired vehicle to a distance upto 5km and carrying upto 2 numbers of 63/100/160/250kVATransformers / Ring Main Units excluding loading& unloading charges. |
| 24 | Providing one Coil Earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 25 | Fitting and erecting one HT Double Pole Structure using PSC pole in position including fitting 2 channel cross arms, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 26 | Fitting 5 channel cross arms, AB switch, DO fuse, LA(Ord), HT & LT connections upto OH lines, etc. on existing DP structure, Fixing distribution box/provision for one set (3No.) of LT fuses, , drawing sufficient length of GI earthing leads to the ground for earthing, excluding provision of earthing & mounting of Transformer on poles. |
| 27 | Erecting one 100kVA Transformer to existing DP and giving connections, including loading from TMR/SRS/other stacking place & unloading at site but excluding cost for transporting transformer. |
| 28 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling. |
| 29 | Providing Transformer fencing to a height of 1.8 m above ground level using MS Angle frames of size ISA 50x50x6mm for outer frame, 2 runs of 40 x 6 MS flat for horizondal brasing and grills with MS rods 8 mm Dia @ 10cm c/c for verticals, providing gate with locking arrangements, providing danger board & name board, embeding the legs in cement concrete 1:2:4, footing of size 30cmx30cmx50cm, painting with synthetic enamel paint two coats over one coat of iron primer etc complete, incl cost of transportation |
| 30 | Cleaning and levelling of transformer yard/RMU, spreading 40 mm broken stone in yard for a thickness of 10 cm above bed of 10 cm thick 6 mm broken stone, after constructing a curb wall of height 20cm above ground and 10cm below level including cost of all materials and charges for conveying, spreading, consolidating etc. |
| 31 | Fitting one additional Fuse unit and giving connection from Transformer to fuse and Distribution box to LT OH line. |
| 32 | Fitting and providing one HT Fly stay for 11kV pole using HT PSC pole including digging and back filling pits in ordinary soil, drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing). Please Enable Macros to View BoQ information |