| 1 | Dismantling Brickwork built in C. Mortar all as specified in MES SSR 2020. |
| 2 | Dismantling RCC work in roof, floors (other than ground floors), beams, Staircases, landing including reinforcement cut as required to facilitate demolition complete all as sp. in MES SSR 2020. |
| 3 | Earth work in excavation in trenches n.exc. 1.5 M wide and 1.5M deep and getting out, returning filling in, including spreading & leveling in layers all as specified in MES SSR 2020. |
| 4 | M/L PCC bed 1:5:10 in fillings & Mass concrete all as specified in MES SSR 2020. |
| 5 | M/L RCC work 1:1½:3 for slabs supported on walls, columns , roofs, landing, balconies, canopies deck slabs and in shelves and the like all as specified in MES SSR, 2020 |
| 6 | M/L RCC work 1:1½ :3 for foundation including raft footing foundation beams plinths beams bases for columns basement slabs under reamed piles and mass concrete and the like all as specified in MES SSR, 2020. |
| 7 | M/L brick work except brick in cement mortar 1: 4 straight or curved on plan exe. 6m mean radius with sub class ‘A’ bricks all as specified in MES SSR 2020. (including removing mortar from and cleaing bricks). |
| 8 | M/L of brickwork with fly ash bricks class designation 75 (Kgf/cm2) straight or curved on plan exc 6m mean radius built in cement mortor 1:4 all as specified in MES SSR 2020. |
| 9 | M/L sand filling under floors including watering & well ramming all as specified in MES SSR,2020 |
| 10 | Removing of Malba/dismantle material to a distance upto 05 Km. |
| 11 | M/L screed 15-20 mm thick in C. mortar 1:4 for laying of marble/tiles all as sp. in MES SSR 2020. |
| 12 | S/f of Marble tiles upto 0.60 Sqm x20mm thick machine cut, bedded jointed and pointed with grey cement slurry including cutting and polishing type (excluding screed)White Marble. |
| 13 | S/F machine cut kota stone slab flooring 20-25mm thick over cement screed base laid and jointed with grey cement slurry mixed with pigment to match the shade of the slab including rubbing and polishing complete all as specified in MES SSR, 2020. (Excluding screed). |
| 14 | Use & waste of formwork to sides of concrete foundations, footings, bases of columns, raft and raft beams, sides and soffits (if any) of Foundation and Plinth Beams and similar work; vertical or to batter fair finished surface all as sp. in MES SSR 2020. |
| 15 | Use & waste of formwork to soffits of suspended slabs such as roof slabs, floor slabs, Columns, beams, landings and similar work, not exceeding 200mm thick (Horizontal or sloping)fair finished surface all as sp. in MES SSR 2020. |
| 16 | S/F Mild steel bars 10 mm dia and over, cut to length, bent to shape required, including cranking, bending spirally for hoping for columns, hooking ends and binding with and including mild steel wire (annealed) not less than 0.9 mm dia or securing with clips all specified in MES SSR, 2020. |
| 17 | M/L PCC floor in cement concrete 1:2:4 fair finished even and smooth without using extra cement (flooring 40mm thick) all as specified in MES SSR 2020. |
| 18 | M/L PC plaster 12 mm thick in cement mortar 1:4, fair finishes over and without using extra cement all as specified in MES SSR, 2020. |
| 19 | M/L glazed ceramic tiles 300 mm x 200mm or 300 mm x 300 mm x 7 mm thick etc. on walls set and jointed in neat cement slurry and pointed in white or colored cement to match all as specified in MES SSR,2020 ( colored tiles). |
| 20 | S/F Aluminium Frame (color coated) Made of Aluminium rectangular section of 1.3 mm Thickness of size 2 ½” x 1 ½” Complete including fixing of 5 mm thick Glass Black/Brown for widows, doors & partly fixed partly openable frame, including hinges door closer, handle etc. complete all as specified in MES SSR 2020. |
| 21 | S/F framed work such as grills, grating, cattle traps etc., with ends of bars shouldered and/ or riveted, or forged into spikes; framed guard bars; barred iron doors; ladders; framed balusters, trusses, MS bar fencing, walk wais; railings; frame work of water tanks and similar work confirming to Fe 410-0 or Fe 310-0 all as specified in MES SSR, 2020. |
| 22 | Providing & fixing 10-12mm thick plaster of paris ceiling (Gypsum anhydrous) to flat surface (RCC ceiling surface) with design as per requirement and approved by the Engineer-in-charge all as specified in MES SSR, 2020 |
| 23 | Putty filling two coats application of one coat of Primer followed by two coats of premium Acrylic emulsion such as Asian/Nerolac/Berger or equivalent followed by preparing existing surface to smooth Interior finish all as sp. |
| 24 | Putty filling two coats application of one coat of primer followed by super fine roller coat finish of spectrum or equivalent to be applied with foam Roller, Finally coated with two coat premium exterior emulsion/Apex or equivalent all as sp. |
| 25 | M/L point wiring for one light point or one fan point conrolled by one switch with cables 1.5 Sqmm in size copper conductor PVC sheathed single core in PVC conduit all as sp. in MES SSR 2020. |
| 26 | M/l for modular switch 1 way 6A 1 module complete all as sp. in MES SSR 2020. |
| 27 | Supply and fixing of PVC rotational water tank triple layer 5000 litre capacity each including float valve brass for 1\\" dia inlet complete all as sp. |
| 28 | Supply and fixing of Monoblock pump 3 HP Single Phase (Make : crompton/Kirlosker or Equivalent) Complete all as sp. |
| 29 | The other works to be carried out shall be payable as per MES Schedule of rate all as specified in MES SSR 2020. |
| 30 | Recovery item : Old Door servicable after nessecary repair by contractor. |
| 31 | Recovery item : Old windows with Grills unservicable. |
| 32 | Recovery item : Old Reinforcement unserviceable. Please Enable Macros to View BoQ information |