| 1 | Earth work in excavation in hard soil within initial lead & lift includingrough dressing and breaking clods |
| 2 | Filling foundation & plinth with sand watered & rammed etc complete including cost, conveyance, royalty of sand etc complete. |
| 3 | Cement concrete of proportion (1:3:6) in foundation and floors using 4cm (1 ½”) size clean hard black crusher broken granite stone metal of approved quality and from approved quarry including hoisting, lowering and laying concrete in layers not exceeding 15 cm. (6”) thick to the required level ramming, watering, curing etc. complete including cost, conveyance, royalties and taxes of all materials with all labour, cess and T&P required for the work etc. complete in all respect. |
| 4 | Plain cment concrete (1:2:4) using 12mm size black hard crusher broken granite chips of approved quality from approved quarry including hoisting, lowering and laying concrete in layers, watering, curing etc. complete including cost, conveyance, royalties and taxes of all materials with labour, cess and T&P etc. required for the work complete. |
| 5 | Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor.R.C.C. for foundation and plinth band, footings, base of columns, mass concrete, pre-cast slabs etc. |
| 6 | Fly Ash brick masonry in cement mortar (1:6) in F & P using fly ash bricks of 25cm x 12cm x 8cm size having a crushing strength of not less than 75 kg/cm2 with dimensional tolerance ± 2% including splays cutting circular moulding chamfering and corbelling and similar such type of works with all necessary projections watering and curing including cost, conveyance, royalties and taxes of all materials with all labour, cess and T&P required for the work complete in all respect in all floors. [Vide AR(P) 71 item No.3]Brick Work in Foundation |
| 7 | Brick Work In Superstructure |
| 8 | Supplying, fitting and fixing G.C.I. Sheet in roof drilling holes in wind ties including fixing of ridges valleys wind ties etc. including cost of sheet & fittings etc. complete |
| 9 | Supplying all material, labour, T&P for providing Mild steel tubular posts and trusses and base plates made out of erw tubes grde yst 210 conforming to iss no 1161/79 with Painting two coats over a coat of primer to iron work including all charges. |
| 10 | 12mm (1/2\\") thick cement plaster (1:4) over brick work after raking out the joint including watering and curing with cost, conveyance, royalties and taxes of all materials with all labour and T&P required for the work etc. complete in all respect. |
| 11 | Painting one coat with weather seal paintincluding cost, conveyance, taxes of all materials, labour and T&P etc. complete |
| 12 | Site Clearance |
| 13 | Display Board Please Enable Macros to View BoQ information |