| 1 | ProvidingoneCoilEarthusingNo.8GI-earthwire(50mmdia,115turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 2 | Additional rate for excavation of one Pit for Coil Earthing in Laterite |
| 3 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 4 | FittinganderectingoneHTPSCSinglePoleinposition,includingfitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 5 | Additionalrateforprovidingonediscset,PGclampetc.complete,onany type of HT pole for making cut point. |
| 6 | LabourchargesforloadingHTPSCpolefromthestackingplaceand unloading the same at work site (transportation by any vehicle). |
| 7 | AdditionalrateforexcavationofonePitforHTPole/HTStayinHard Laterite. |
| 8 | Conveyance of one km 11kV line materials from section store/stackingplace to the work site (excluding poles). |
| 9 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Laterite. |
| 10 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 11 | FittingandprovidingoneStrutusingHTPSCpoleincludingdiggingand back filling pit in ordinary soil. |
| 12 | Fitting and providing one HT Fly stay for 11kV pole using HT PSC pole includingdiggingandbackfillingpitsinordinarysoil,drawingsufficient lengthofGIearthleadstothegroundforearthing(excludingprovisionof earthing). |
| 13 | FittingoneAdditional2.4m/3mChannelcrossarm(100x50x6mm),in existing 11kV DP including conveyance of materials. |
| 14 | Fitting one set AB switch on existing DP, giving connection and drawing sufficientlengthofGIearthingleadstothegroundforearthing,excluding provision of earthing. |
| 15 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 16 | Stringing of one km 3 PH 11kV line with XLPE Insulated ACSR Raccoon or equivalant (3 conductors) after fitting insulators, binding conductors to pin insulators using suitable tie and anchoring with wedge type anchoring clamps including cutting and removing tree branches wherever necessary excluding cut point works. |
| 17 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling. |
| 18 | Fitting and erecting one HT Double Pole Structure using A type pole in position including fitting 2 No. channel cross arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 19 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 20 | Additional rate for excavation of Pit for A type pole in Hard Laterite. |
| 21 | Providingconcretemuffingofsize0.45x0.45x1.5m(0.5maboveGLand 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm) 0.45x0.45x1.5m, Plastering (1:3) 12mm 0.45x0.45mx5sides. |
| 22 | Fitting and erecting one HT Double Pole Structure using PSC pole in position including fitting 2 channel cross arms, digging and back filling all cross arms to the ground for earthing (excluding provision of earthing) |
| 23 | Quoted Amount of BOQ1 in figures |
| 24 | GST Rate in percentage Please Enable Macros to View BoQ information |