| 1 | Site clearing and clearance including removing tree all complete. |
| 2 | Dewatering of water in pond by disel pump including disel, fuel, pump operator. all complete. |
| 3 | Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap): 450mm dia piles. DSR.20.3.3 |
| 4 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge.DSR-2023, 2.6. |
| 5 | Provinding and laying cement concrete 1:4:8 (1 Cement: 4 coarse sand derived from natural sources: 8 graded stone aggregate 40 mm nominal size derived from natural sources).DSR-2023, 4.1.8. |
| 6 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement: 1.5 coarse sand(zone-III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources).DSR-2023, 5.3 |
| 7 | Mild steel or iron in plan work such as reinforced concrete or reinforced brick work wrought to required shape as necessary including bending for proper completion of the work. All complete S.I.No. 504 |
| 8 | Excavating, supplying, stacking and filling of local earth (including royalty) b mechanical transport upto a lead of 5km allso including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift. DSR 2023 2.25(a) |
| 9 | M150 brick work Designation 7.5 in foundation and plinth in: Brick work with common burnt clay F.P.S. (non modular) bricks of class.DSR-2023,6.1.1. |
| 10 | 12mm thick plaster in 1:3 cement and coarse sand mortar. All complete. DSR-2023, 13.4.1. Please Enable Macros to View BoQ information |