| 1 | Supply, Erection, testing & commissioning of S.T Pole 11mtr. Long SP-56 with base plate & cap for HT. Strictly as per REC standards |
| 2 | Erection, testing & commissioning of S.T Pole 11mtr. Long SP-56 including its carriage from Divisisonal Store to Site |
| 3 | Supply, Erection, testing & commissioning of S.T Pole 9mtr Long SP-33 with base plate & cap for HT. Strictly as per REC standards |
| 4 | Erection, testing & commissioning of S.T Pole 9mtr Long SP-33 including its carriage from Divisisonal Store to Site |
| 5 | Supply, Erection, testing & commissioning of S.T Pole 8mtr Long SP-15 with base plate & cap for LT. Strictly as per REC standards |
| 6 | Erection, testing & commissioning of S.T Pole 8mtr Long SP-15 including its carriage from Divisisonal Store to Site |
| 7 | Supply, Erection, testing & commissioning of PCC Pole 8mtr Long |
| 8 | Erection, testing & commissioning of PCC Pole 8mtr Long including its carriage from Divisisonal Store to Site |
| 9 | Supply, Laying, stringing, tensioning & binding of ACSR 100mmsq (Dog) Conductor |
| 10 | Laying, stringing, tensioning & binding of ACSR 100mmsq (Dog) Conductor including its carriage from Divisisonal Store to Site |
| 11 | Supply, Laying, stringing, tensioning & binding of ACSR 50mmsq (Rabbit) Conductor |
| 12 | Laying, stringing, tensioning & binding of ACSR 50mmsq (Rabbit) Conductor including its carriage from Divisisonal Store to Site |
| 13 | Supply, Laying, stringing, tensioning & binding of ACSR 30mmsq (Weasal) Conductor |
| 14 | Laying, stringing, tensioning & binding of ACSR 30mmsq (Weasal) Conductor including its carriage from Divisisonal Store to Site |
| 15 | Providing & fixing of ISMC 100x50x6mm Channel iron cross arms for x-mer frame 8'long @ 22.4 Kg each -1 NO including Nuts & Bolts |
| 16 | Fixing of ISMC 100x50x6mm Channel iron cross arms for x-mer frame 8'long |
| 17 | Providing & fixing of ISMC 75x40x6mm Channel iron cross arms for x-mer frame- 1 Nos @16.5 kg each 8' long including Nuts & Bolts |
| 18 | Fixing of ISMC 75x40x6mm Channel iron cross arms for x-mer frame- |
| 19 | Providing ,fixing, of ISMC 75X40x6mm X-arm 5' long |
| 20 | Fixing, of ISMC 75X40x6mm X-arm 5' long- |
| 21 | Providing ,fixing, of MS Angle iron Braces 50x50x6mm-4.5 ft long, |
| 22 | Fixing, of MS Angle iron Braces 50x50x6mm-4.5 ft long |
| 23 | Providing and Fixing of sprial earthing made of 115 turns of GI wire SWG No.8 placed 1.5m below ground level including excavation of pit, refilling the same withsoft soil |
| 24 | Fixing of sprial earthing made of 115 turns of GI wire SWG No.8 placed 1.5m below ground level including excavation of pit, refilling the same withsoft soil |
| 25 | Supply,fixing, testing & commissioning of 11KV Link Set (polymer) Station type as per IS Standards |
| 26 | Fixing, testing & commissioning of 11KV Link Set Station type (polymer/porcelain )as per IS Standards |
| 27 | Supply,fixing, testing & commissioning of 11KV Link Set Heavy Duty as per IS Standards |
| 28 | Fixing, testing & commissioning of 11KV Link Set Heavy Duty (polymer/porcelain ) as per IS Standards |
| 29 | Supply,fixing, testing & commissioning of 11KV DO Fuse Set (polymer )as per IS Standards |
| 30 | Fixing, testing & commissioning of 11KV DO Fuse Set (polymer/porcelain ) as per IS Standards |
| 31 | Supply,fixing, testing & commissioning of 11KV LA Set (polymer )as per IS Standards |
| 32 | Fixing, testing & commissioning of 11KV LA Set (polymer/porcelain ) as per IS Standards |
| 33 | Providing and fixing of LT fuse set as approved by KPDCL. |
| 34 | Supply,fixing, testing & commissioning of 11KV Disc Set (polymer) 45 KN complete Set |
| 35 | Supply,fixing, testing & commissioning of 11KV Disc Set (porcelain) 45 KN complete Set |
| 36 | Fixing, testing & commissioning of 11KV Disc Set (polymer/porcelain ) 45 KN complete Set |
| 37 | Supply,fixing, testing & commissioning of 11KV Pin (polymer ) Insulators 45 KN with GI pins complete. |
| 38 | Supply,fixing, testing & commissioning of 11KV Pin Insulators (porcelain ) 45 KN with GI pins complete. |
| 39 | Fixing, testing & commissioning of 11KV Pin Insulators (polymer/porcelain ) 45 KN with GI pins complete. |
| 40 | Carriage, Installation, testing & commisioing of 16/25 kVA 11/0.433 KV 3-Phase dully Oil Filled Distribution Transformer from Divisional stores upto site within the jurisdiction of SD-Bijbehara of ED Bijbehara |
| 41 | Carriage, Installation, testing & commisioing of 16/25 kVA 11/0.433 KV 3-Phase dully Oil Filled Distribution Transformer from Divisional stores upto site within the jurisdiction of SD-Aishnuqam of ED Bijbehara |
| 42 | Carriage, Installation, testing & commisioing of 63/100 kVA 11/0.433 KV 3-Phase dully Oil Filled Distribution Transformer from Divisional stores upto site within the jurisdiction of SD-Bijbehara of ED Bijbehara |
| 43 | Carriage, Installation, testing & commisioing of 63/100 kVA 11/0.433 KV 3-Phase dully Oil Filled Distribution Transformer from Divisional stores upto site within the jurisdiction of SD-Aishnuqam of ED Bijbehara |
| 44 | Carriage, Installation, testing & commisioing of 200/250/300 kVA 11/0.433 KV 3-Phase dully Oil Filled Distribution Transformer from Divisional stores upto site within the jurisdiction of SD-Bijbehara of ED Bijbehara |
| 45 | Carriage, Installation, testing & commisioing of 200/250/300 kVA 11/0.433 KV 3-Phase dully Oil Filled Distribution Transformer from Divisional stores upto site within the jurisdiction of SD-Aishnuqam of ED Bijbehara |
| 46 | Carriage, Installation, testing & commisioing of 400/500/630 kVA 11/0.433 KV 3-Phase dully Oil Filled Distribution Transformer from Divisional stores upto site within the jurisdiction of SD-Bijbehara of ED Bijbehara |
| 47 | Carriage, Installation, testing & commisioing of 400/500/630kVA 11/0.433 KV 3-Phase dully Oil Filled Distribution Transformer from Divisional stores upto site within the jurisdiction of SD-Aishnuqam of ED Bijbehara |
| 48 | Providing & fixing of Thimbles 95 mm Sq. of standard make |
| 49 | Fixing of Thimbles 95 mm Sq. of standard make |
| 50 | Providing & fixing of Thimbles 120 mm Sq. of standard make |
| 51 | Fixing of Thimbles 120 mm Sq. of standard make |
| 52 | Providing & fixing of Thimbles 185 mm Sq. of standard make |
| 53 | Fixing of Thimbles 185 mm Sq. of standard make |
| 54 | Providing & fixing of Thimbles 240 mm Sq. of standard make |
| 55 | Fixing of Thimbles 240 mm Sq. of standard make |
| 56 | Providing & fixing of Thimbles 300 mm Sq. of standard make |
| 57 | Fixing of Thimbles 300 mm Sq. of standard make |
| 58 | Providing & fixing of Thimbles 400 mm Sq. of standard make |
| 59 | Fixing of Thimbles 400 mm Sq. of standard make |
| 60 | Providing & fixing of Soldress Clamp 95 mm Sq. of standard make |
| 61 | Fixing of Soldress Clamp 95 mm Sq. of standard make |
| 62 | Providing & fixing of Soldress Clamp 120 mm Sq. of standard make |
| 63 | Fixing of Soldress Clamp 120 mm Sq. of standard make |
| 64 | Providing & fixing of Soldress Clamp 185 mm Sq. of standard make |
| 65 | Fixing of Soldress Clamp 185 mm Sq. of standard make |
| 66 | Providing & fixing of Soldress Clamp 240 mm Sq. of standard make |
| 67 | Fixing of Soldress Clamp 240 mm Sq. of standard make |
| 68 | Providing & fixing of Soldress Clamp 300 mm Sq. of standard make |
| 69 | Fixing of Soldress Clamp 300 mm Sq. of standard make |
| 70 | Providing & fixing of Soldress Clamp 400 mm Sq. of standard make |
| 71 | Fixing of Soldress Clamp 400 mm Sq. of standard make |
| 72 | Providing, Fixing of GI nuts and bolts for fixing of x-arms and other accessories. |
| 73 | Fixing of nuts and bolts for fixing of x-arms and other accessories. |
| 74 | Painting of poles with one coat of red oxide and two coats of Alm paint. Complete job icluding the cost of paint and red oxide |
| 75 | Supply, Fixing, of LT Shackle insuators with d-clamps and nuts bolts. |
| 76 | Fixing, of LT Shackle insuators with d-clamps and nuts and bolts. |
| 77 | Supply, Fixing, of LT Shackle insuators with GI Mukhi-clamps nuts and bolts. |
| 78 | Fixing, of LT Shackle insuators with Mukhi-clamps nuts and bolts. |
| 79 | Dismentalling of ST 8Mtr Long Poles including its carriage to Divisional Stores Bijbehara (complete job) |
| 80 | Dismentalling of ST 9Mtr Long Poles including its carriage to Divisional Stores Bijbehara (complete job) |
| 81 | Dismentalling of ST 11Mtr Long Poles including its carriage to Divisional Stores Bijbehara (complete job) |
| 82 | Dismentalling of PCC Poles including its carriage to Divisional Stores Bijbehara (complete job) |
| 83 | Dismentalling & Re-erection of PCC Poles |
| 84 | Dismentalling & Re-erection of ST 8Mtr. Long Poles |
| 85 | Dismentalling & Re-erection of ST 9Mtr. Long Poles |
| 86 | Dismentalling & Re-erection of ST 11Mtr. Long Poles |
| 87 | Dismentalling of ACSR 30mmsq including its carriage to Divisional Stores Bijbehara (complete job) |
| 88 | Dismentalling of ACSR 50mmsq including its carriage to Divisional Stores Bijbehara (complete job) |
| 89 | Dismentalling of ACSR 100mmsq including its carriage to Divisional Stores Bijbehara (complete job) |
| 90 | Dismentalling & Re-laying of ACSR 30mmsq at site |
| 91 | Dismentalling & Re-laying of ACSR 50mmsq at site |
| 92 | Dismentalling & Re-laying of ACSR 100mmsq at site |
| 93 | Re-Stringing of loose Conductor (50mmsq) |
| 94 | Re-Stringing of loose Conductor (30mmsq) |
| 95 | Re-Stringing of loose Conductor (100mmsq) |
| 96 | Branch cutting of trees for route clearance for minimising frquency of faults. |
| 97 | Unloading of 16kVA/25KVA distribution transformer |
| 98 | Loading of 16kVA/25KVA distribution transformer |
| 99 | Unloading of 63kVA/100KVA distribution transformer |
| 100 | Loading of 63kVA/100KVA distribution transformer |
| 101 | Unloading of 200kVA/250kVA/300KVA distribution transformer |
| 102 | Loading of 200kVA/250kVA/300KVA distribution transformer |
| 103 | Unloading of 400kVA/500kVA/630KVA distribution transformer |
| 104 | Loading of 400kVA/500kVA/630KVA distribution transformer |
| 105 | Straightening of tilted ST poles (11Mtr/9Mtr/ 8Mtr.) |
| 106 | Unloading of ST 11Mtr/9Mtr/8Mtr. Long Poles in Divisional Stores |
| 107 | Loading of ST 11Mtr/9Mtr/8Mtr. Long Poles in Divisional Stores |
| 108 | Stacking of Poles in Divisional stores Bijbehara(11Mtr/9Mtr/ 8Mtr.) |
| 109 | Loading of Octagonal Poles and Pipes in Divisional Stores Bijbehara |
| 110 | Unloading of Octagonal Poles and Pipes in Divisional Stores Bijbehara |
| 111 | Stacking of Octagonal Poles and Pipes in Divisional Stores Bijbehara |
| 112 | Loading of LED Lights(12/40/70/100/200 W) in Divisional Stores Bijbehara |
| 113 | Unloading of LED Lights(12/40/70/100/200 W) in Divisional Stores Bijbehara |
| 114 | Stacking of LED Lights(12/40/70/100/200 W) in Divisional Stores Bijbehara |
| 115 | Supply and fixing of Earthing of sub station-Excavation of earth pit of dia 650 mm & depth 3000mm,installation of earthing pipe of 40mm Nominal bore and 4mm wall thickness and length 2.5 mtr long as per IS 1239 GI strip for neutral earthing of size25x3mm for connection of transformer body,GO set and lighting arrestor as per IS 2629/85,GI nuts and Bolts,refilled with earth enhancement material and earth chamber made of brick masonary with RCC slab cover. |
| 116 | Supply and fixing of Galvanised stay set with 50 x 8 mm stay clamp, guy insulator ( 02 no. ), anchor plate (200x200x6 mm ) , nuts and bolts , 2 no. turn buckles , 1.8 mm long , 16mm dia solid GS stay rod and 7/3.15 mm dia GI stranded wire complete |
| 117 | Fixing of Galvanised stay set with 50 x 8 mm stay clamp, guy insulator ( 02 no. ), anchor plate (200x200x6 mm ) , nuts and bolts , 2 no. turn buckles , 1.8 mm long , 16mm dia solid GS stay rod and 7/3.15 mm dia GI stranded wire complete |
| 118 | Supply,installation , testing & commissioning of Gapless Surge Arrestor,9 kV,10 kA, LA with (polymer) housing, Station Type |
| 119 | installation , testing & commissioning of Gapless Surge Arrestor,9 kV,10 kA, LA with (polymer) housing, Station Type |
| 120 | Supply,installation , testing & commissioningof 11 kV, G.O AB Switch , 3-phase, 200A |
| 121 | installation , testing & commissioning of 11 kV, G.O AB Switch , 3-phase, 200A |
| 122 | Supply, installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 50 Sq mm |
| 123 | installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 50 Sq mm |
| 124 | Supply, installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 70 Sq mm |
| 125 | installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 70 Sq mm |
| 126 | Supply, installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 120 Sq mm |
| 127 | installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 120 Sq mm |
| 128 | Supply, installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 185 Sq mm |
| 129 | installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 185 Sq mm |
| 130 | Supply, installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 240 Sq mm |
| 131 | installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 240 Sq mm |
| 132 | Supply, installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 300 Sq mm |
| 133 | installation , testing & commissioning of Un Armoured Single Core XPLE, FRLS Cable 300 Sq mm |
| 134 | Supply and laying of Cement bottoming 1:2:4 mix as per REC standards 0.5 cum/pole, muffing 20 cm above ground level ,including plaster and curing of concrete. |
| 135 | Supply and laying of Cement bottoming 1:2:4 mix as per REC standards 0.45 cum/pole, muffing 20 cm above ground level ,including plaster and curing of concrete. |
| 136 | Providing, Installation, testing & commisioning of 3-Phase 4-wire Prodigy Meter (40 -200A), including suitable stand/clamps using channels and Canopy to protect the same from Adverse Weather Conditions (Complete) |
| 137 | Installation, testing & commisioning of 3-Phase 4-wire Prodigy Meter (40 -200A), including suitable stand/clamps using channels and Canopy to protect the same from Adverse Weather Conditions (Complete) |
| 138 | Providing, Installation, testing & commisioning of single phase energy meter including suitable clamps nuts and bolts(Complete) |
| 139 | Installation, testing & commisioning of single phase energy meter including suitable clamps nuts and bolts(Complete) |
| 140 | Providing, Installation, testing & commisioning of three phase energy meter including suitable clamps nuts and bolts(Complete) |
| 141 | Installation, testing & commisioning of three phase energy meter including suitable clamps nuts and bolts(Complete) |
| 142 | Supply, laying, testing & commissiong of 35mmsq AB (HT Cable) (3x35+1x35mmsq) XLPE (11kV , 3 x 1Core + Earth) of standard make conforming to IS; 8130-1894, IS; 398(Part-IV) - 1994, IS:7098 (Part II) - 2011 & IS; 5831-1984 with upto date amendments if any. |
| 143 | Laying, testing & commissiong of 35mmsq AB (HT Cable) (3x35+1x35mmsq) XLPE (11kV , 3 x 1Core + Earth) of standard make conforming to IS; 8130-1894, IS; 398(Part-IV) - 1994, IS:7098 (Part II) - 2011 & IS; 5831-1984 with upto date amendments if any. |
| 144 | Supply, laying, testing & commissiong of 50mmsq AB (HT Cable) (3x50+1x70mmsq) XLPE (11kV , 3 x 1Core + Earth) of standard make conforming to IS; 8130-1894, IS; 398(Part-IV) - 1994, IS:7098 (Part II) - 2011 & IS; 5831-1984 with upto date amendments if any. |
| 145 | laying, testing & commissiong of 50mmsq AB (HT Cable) (3x50+1x70mmsq) XLPE (11kV , 3 x 1Core + Earth) of standard make conforming to IS; 8130-1894, IS; 398(Part-IV) - 1994, IS:7098 (Part II) - 2011 & IS; 5831-1984 with upto date amendments if any. |
| 146 | Supply, laying, testing & commissiong of 70mmsq AB (HT Cable) (3x70+1x95mmsq) XLPE (11kV , 3 x 1Core + Earth) of standard make conforming to IS; 8130-1894, IS; 398(Part-IV) - 1994, IS:7098 (Part II) - 2011 & IS; 5831-1984 with upto date amendments if any. |
| 147 | Laying, testing & commissiong of 70mmsq AB (HT Cable) (3x70+1x95mmsq) XLPE (11kV , 3 x 1Core + Earth) of standard make conforming to IS; 8130-1894, IS; 398(Part-IV) - 1994, IS:7098 (Part II) - 2011 & IS; 5831-1984 with upto date amendments if any. |
| 148 | Supply, laying, testing & commissiong of 120mmsq AB (HT Cable) (3x120+1x95mmsq) XLPE (11kV , 3 x 1Core + Earth) of standard make conforming to IS; 8130-1894, IS; 398(Part-IV) - 1994, IS:7098 (Part II) - 2011 & IS; 5831-1984 with upto date amendments if any. |
| 149 | Laying, testing & commissiong of 120mmsq AB (HT Cable) (3x120+1x95mmsq) XLPE (11kV , 3 x 1Core + Earth) of standard make conforming to IS; 8130-1894, IS; 398(Part-IV) - 1994, IS:7098 (Part II) - 2011 & IS; 5831-1984 with upto date amendments if any. |
| 150 | Supply, laying, testing & commissiong of 120mmsq AB (LT Cable) (3x120+1x16+1x70mmsq) of standard make . |
| 151 | Laying, testing & commissiong of 120mmsq AB (LT Cable) (3x120+1x16+1x70mmsq) of standard make . |
| 152 | Supply, laying, testing & commissiong of 50mmsq AB (LT Cable) (3x50+1x16+1x35mmsq) of standard make . |
| 153 | Laying, testing & commissiong of 50mmsq AB (LT Cable) (3x50+1x16+1x35mmsq) of standard make . |
| 154 | Supply, fixing, testing & commissiong of 11 KV Single core Straight Through Jointing KIT 400/300/185mm2 |
| 155 | Supply, fixing, testing & commissiong of 11 KV Single core Cable Termination KIT 400/300/185mm2 |
| 156 | Supply, fixing, testing & commissiong of Mid Span Straight through Jointing kit for 11kV AB Cable suitable for AB Cable of standard make and size conforming to the latest IS Standards |
| 157 | Fixing, testing & commissiong of Mid Span Straight through Jointing kit for 11kV AB Cable suitable for AB Cable of standard make and size conforming to the latest IS Standards |
| 158 | Supply, fixing, testing & commissiong of 11kV Heat Shrinkable Out Door Cable termination Kit for 11kV AB Cable of standard make and size conforming to the latest IS Standards |
| 159 | Fixing, testing & commissiong of 11kV Heat Shrinkable Out Door Cable termination Kit for 11kV AB Cable of standard make and size conforming to the latest IS Standards |
| 160 | Supply, Fixing of ' Suspension Clamps with eye Hook (Complete)' of standard make for AB Cable including strips for fixing on polesof required sizes |
| 161 | Fixing of ' Suspension Clamps with eye Hook (Complete)' of standard make for AB Cable including strips for fixing on polesof required sizes |
| 162 | Supply, Fixing of Dead End Clamps (Complete) of standard make for AB Cable including strips for fixing on poles of required sizes |
| 163 | Fixing of Dead End Clamps (Complete) of standard make for AB Cable including strips for fixing on poles of required sizes |
| 164 | Supply, Installation ,Testing and Commissioning at sites within the jurisdiction of SD Bijbehara of ED Bijbehara (by utilizing skilled mechanics) of 2.8KVA Portable Gensets on hire basis |
| 165 | Supply, Installation ,Testing and Commissioning at sites within the jurisdiction of SD Aishmuqam of ED Bijbehara (by utilizing skilled mechanics) of 2.8KVA Portable Gensets on hire basis |
| 166 | Loading,Carriage to and fro ,Installation ,Testing and Commissioning (by utilizing skilled mechanics) of 2.8KVA Portable Gensets (to be provided by the department) from Divisional Stores upto sites within the jurisdiction of SD-Bijbehara of ED Bijbehara |
| 167 | Loading,Carriage to and fro ,Installation ,Testing and Commissioning (by utilizing skilled mechanics) of 2.8KVA Portable Gensets (to be provided by the department) from Divisional Stores upto sites within the jurisdiction of SD-Aishmuqam of ED Bijbehara |
| 168 | Operation and Maintainence (by utilizing skilled mechanics) of 2.8KVA Portable Gensets |
| 169 | Loading,Carriage to and fro ,Installation ,Testing and Commissioning (by utilizing skilled mechanics) of 25 KVA Portable Gensets (to be provided by the department) from Divisional Stores upto sites within the jurisdiction of SD-Bijbehara of ED Bijbehara |
| 170 | Loading,Carriage to and fro ,Installation ,Testing and Commissioning (by utilizing skilled mechanics) of 25 KVA Portable Gensets (to be provided by the department) from Divisional Stores upto sites within the jurisdiction of SD-Aishmuqam of ED Bijbehara |
| 171 | Operation and Maintainence (by utilizing skilled mechanics) of 25 KVA Portable Gensets |
| 172 | Installation, Testing & commisioing of 70watt LED lights including their back carriage to the divisional stores from the site (to be provided by department) |
| 173 | Supply, Installation, Testing & commisioing of 40watt LED lights including providing bracket , clamps , nuts & bolts of standard make |
| 174 | Installation, Testing & commisioing of 40watt LED lights including bracket , clamps , nuts & bolts of standard make |
| 175 | Supply, Installation, Testing & commisioing of 5watt LED bulb of standard make |
| 176 | Supply, Installation, Testing & commisioing of 7watt LED bulb of standard make |
| 177 | Supply, Installation, Testing & commisioing of 9watt LED bulb of standard make |
| 178 | Supply, Installation, Testing & commisioing of 10watt LED bulb of standard make |
| 179 | Supply, Installation, Testing & commisioing of 15watt LED bulb of standard make |
| 180 | Supply, Installation, Testing & commisioing of 20watt LED bulb of standard make |
| 181 | Providing, laying of 16mmsq twin core aluminuim conductor FRLS |
| 182 | Providing, laying of 10mmsq twin core aluminuim conductor FRLS |
| 183 | Providing, laying of 6mmsq twin core aluminuim conductor FRLS |
| 184 | Providing, laying of 1mmsq multicore Cu flexible wire of standard make |
| 185 | Providing, laying of 1.5mmsq multicore Cu flexible wire of standard make |
| 186 | Providing, laying of 2.5mmsq multicore Cu flexible wire of standard make |
| 187 | Providing, laying of 4mmsq multicore Cu flexible wire of standard make |
| 188 | Providing, laying of 6mmsq multicore Cu flexible wire of standard make |
| 189 | Supply, Installation, Testing & commisioing of 5Amp Switch Socket Combine |
| 190 | Supply, Installation, Testing & commisioing of 16Amp Switch Socket Combine |
| 191 | Supply,Installation, Testing & commisioing of 32 Amp with DP Switch Socket Combine |
| 192 | Supply, Installation, Testing & commisioing of pendent holders |
| 193 | Supply, installation, testing & commissioing of LT Distribution Box for25KVA DTR with MCCB for incommer and MCB's for outgoing ckt. With terminal extensions (complete) |
| 194 | installation, testing & commissioing of LT Distribution Box for25KVA DTR with MCCB for incommer and MCB's for outgoing ckt. With terminal extensions (complete) |
| 195 | Supply, installation, testing & commissioing of LT Distribution Box for 63KVA DTR with MCCB for incommer and MCB's for outgoing ckts.With terminal extensions (complete) |
| 196 | installation, testing & commissioing of LT Distribution Box for 63KVA DTR with MCCB for incommer and MCB's for outgoing ckts.With terminal extensions (complete) |
| 197 | Supply, installation, testing & commissioing of LT Distribution Box for 100KVA DTR with MCCB for incommer and MCB's for outgoing ckts. With terminal extensions(complete) |
| 198 | installation, testing & commissioing of LT Distribution Box for 100KVA DTR with MCCB for incommer and MCB's for outgoing ckts. With terminal extensions(complete) |
| 199 | Supply, installation, testing & commissioing of LT Distribution Box for 250KVA DTR with MCCB for incommer and MCB's for outgoing ckts.With terminal extensions (complete) |
| 200 | installation, testing & commissioing of LT Distribution Box for 250KVA DTR with MCCB for incommer and MCB's for outgoing ckts.With terminal extensions (complete) |
| 201 | Supply, installation, testing & commissioing of LT Distribution Box for 400KVA DTR with MCCB for incommer and MCB's for outgoing ckts.With terminal extensions (complete) |
| 202 | installation, testing & commissioing of LT Distribution Box for 400KVA DTR with MCCB for incommer and MCB's for outgoing ckts.With terminal extensions (complete) |
| 203 | Supply of 4Pole 200Amp, 415v, 50Hz, Off load Change over switch conforming to latest IS standards of reputed brands like havells, L&T etc. |
| 204 | Supply of 4Pole 100Amp, 415v, 50Hz, Off load Change over switch conforming to latest IS standards of reputed brands like havells, L&T etc. |
| 205 | Supply of 4Pole 63Amp, 415v, 50Hz, Off load Change over switch conforming to latest IS standards of reputed brands like havells, L&T etc. |
| 206 | Supply and Installation of MS Kiosk for Housing of Changeover Switches |
| 207 | Unloading of line material & workshop material like ACSR (30mmsq, 50mmsq, 100mmsq, DPC, T.Oil (barrels) , GI Wire, link sets, DO sets, Nuts & bolts, channel iron of sizes, Disc Sets, braces of sizes, bush rods, Alm. Strips, insulators, Etc. from Divisional stores |
| 208 | Loading of line material & workshop material like ACSR (30mmsq, 50mmsq, 100mmsq, DPC, T.Oil (barrels) , GI Wire, link sets, DO sets, Nuts & bolts, channel iron of sizes, Disc Sets, braces of sizes, bush rods, Alm. Strips, insulators, Etc. from Divisional stores |
| 209 | Supply of Tent of size 20x15 feet of Standard make for arrangement of functions |
| 210 | Providing of Hydra/crane on hire basis for lifting of damaged Distribution transformers and re-installation at site ( Rate to be quoted per DT) |
| 211 | Design/Supply/Fixing of Hoardings of Sizes |
| 212 | Design/Supply/Fixing of Flex Banner of Sizes |
| 213 | Design/Supply/Fixing of Fleyers of Sizes Please Enable Macros to View BoQ information |