| 1 | Filling foundation and plinth with sand well watered and rammed as per direction of engineer in charge |
| 2 | Providing Cement Concrete (1:3:6) using 40mm size hard black granite Crosser broken metal approved quality from approved quarry including hoisting laying using concrete mixture and vibrators including cost, carriage, royalty, cost of all labour T.&P. etc complete and as directed by E.I.C.. |
| 3 | Providing R.C.C. M-20 grade with 20mm and down grade C.B. chips of approved quality from approved quarry including hoisting, laying hire charges of concrete mixture, vibrator, watering, curing and cost of all materials and labour, T&P centering shuttering etc complete but excluding cost of reinforcement . |
| 4 | column |
| 5 | roof slab |
| 6 | providing M.S reinforcement for Rcc work Cutting, bending, binding M.S. or tor rod R.C.C. work including tying the grills and placing in position including cost of steel and binding wire.. |
| 7 | Brick work with Fly ash bricks of 25 Cm. x 12 Cm. x 8 Cm. size having crushing sfength not less than 75 Kg./Crn2 with dimensional tolerance + 2 % in cement mortar ( 1 : 6 ) in super structure |
| 8 | 20mm thick cement plaster (1:4) as grading plaster on roof slab including all cost conveyance royalty & taxes etc. complete at work site per 1sqm |
| 9 | 12mm thick cement plaster (1:6) on brick work including all cost conveyance royalty & taxes etc. comp. to work site per 1sqm |
| 10 | 16mm thick cement plaster (1:6) on brick work including all cost conveyance royalty & taxes etc. comp. to work site per 1sqm |
| 11 | Supplying all materials, labour, T&P and providing 6mm thick cement plaster (1:4) to RCC surfaces finished smooth including closed deep chipping and slurry tratment including watering, curing, conveyance of all materials to worksite, payment of royalty, taxes etc all complete as per specification and direction of the E.I.C |
| 12 | Supplying all materials, labour, T&P and providing cement concrete (1:2:4) with 12mm size hard brokengranite chips including watering, curing, conveyance of all materials to worksite, payment of royalty, taxes etc all complete as per specification and direction of the E.I.C |
| 13 | Supplying all materials, labour, T&P and providing priming 1 coat with any approved primer all complete as per specification and direction of the E.I.C |
| 14 | Supplying all materials, labour, T&P and distempering two coats to walls with distemper of approved shade on new work to give an even shade etc all complete as per specification and direction of the E.I.C |
| 15 | Supplying all materials, labour, T&P and Weather Coat two coats to walls with approved shade on new work to give an even shade etc all complete as per specification and direction of the E.I.C |
| 16 | Fitting & fixing of iron door, window labour all cost including t & p etc. |
| 17 | Supplying all materials, labour, T&P and providing priming 1 coat (Red Oxide Primer)with any approved primer all complete as per specification and direction of the E.I.C |
| 18 | Supplying all materials, labour, T&P and providing painting 2 coat with any approved paint (Enamel Paint)on new Iron work all complete as per specification and direction of the E.I.C |
| 19 | Providing Photographs , Placing & Fixing of transparency board at Work Site etc. complete . Please Enable Macros to View BoQ information |