| 1 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils |
| 2 | Providingand laying inposition cement concrete including curing, compactionetc .completeins pecifiedgradeexcluding the costofcentering and shuttering All work upto plinth level. 1:4:8 (1cement :4coarsesand: 8graded stone aggregate 40 mm nominal size). |
| 3 | Providing and laying in position specified grade of cement concrete for all RCC structural elements upto plinth level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers( if required) excluding the cost of centering, shuttering and reinforcement. M20 grade Nominal Mix / Design Mix |
| 4 | Providing and laying in position specified grade of cement concrete for RCC structural elements upto floor five level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers (if required ) excluding the cost of centering, shuttering and reinforcement for Walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc.M20 grade Nominal Mix / Design Mix |
| 5 | Centering and Shuttering with plywood or steel sheets including strutting, propping bracing both ways and removal of formwork for foundation , footings, strap beam, raft , bases of columns etc. |
| 6 | Centering & shuttering with plywood or steel sheets including strutting, propping bracing both ways with steel props and removal of formwork for upto floor five level for : Columns, pillars, posts and struts etc. |
| 7 | Providing and fabricating reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding (including cost of binding wire) all complete up to floor five level. ('Original producers' who manufacture billet directly from iron ores and roll the bilets to produce steel conforming to IS:1786) Thermo-mechanically Treated bars (Conforming of relevent IS code) |
| 8 | Steel work in built up tubular trusses including cutting, hoisting ( height upto 10 m)fixing in position and applying a priming coat of approved steel primer, welded and bolted including special shaped washers etc. complete. Hot finished welded type tubes. |
| 9 | Providing corrugated G.S. sheet roofing including vertical / curved surface fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washers filled with white lead and including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (upto any pitch in horizontal/ vertical or curved surfaces) excluding the cost of purlins, rafters and trusses and including cutting to size and shape whenever required. 0.63 mm thick with zinc coating not less than 275 gm/m2 |
| 10 | Filling available excavated earth (excluding rock) in trenches, plinth side of foundation etc. in layers not exceeding 20 cm. in depth, consolidating each deposited layer by ramming and watering including lead up to 50 meter and with all lift. |
| 11 | Random rubble dry stone Kharanja under floor. |
| 12 | Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry, making of lines or groove etc complete but excluding the cost of nosing of steps etc. complete. 75mm thick with 20mm thick nominal size aggregate. |
| 13 | Plaster onnewsurfaceonwalls incement sandmortar 1:6 including racking of joint etc. complete fine finish 12mm thick. |
| 14 | Wall painting with plastic emulsion paint of approved brand and manufacture to give an even shade including all scaffolding: 12.40.1 Two or more coats on new work including prepartion of base with primer, putty, lippy etc complete in all respect. |
| 15 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade : Two or more coats on new work Please Enable Macros to View BoQ information |