| 1 | Earthwork exavation in all kind of Soil including dressing and levelling the bed and depositing the excavated materials away from the work site with all leads, lifts, sundries, T&P required for the work etc complete as directed by the engineer in Charge |
| 2 | Filling foundation and plinth with sand including cost, conveyance & royalty of all materials to the work site including watering & ramming with all leads, lifts, sundries & T&P etc. complete, as per direction of Engineer-in-Charge. |
| 3 | C.C. work of M-15 with 40 mm down graded hard granite crusher broken metal including cost, conveyance, royalty and other taxes of all materials to the work site, mixing and laying of concrete in position & compacted properly with all leads, lifts, sundries with all hire & running charges of machineries such as concrete mixer, vibrator etc. required for the work site with proper compaction and curing etc. complete as per the direction of Engineer-in-charge |
| 4 | Rigid smooth centering & shuttering for C.C. work including false work and dismentaling them after casting including cost & conveyance of materials complete as per drawing & specification with all leads, lifts, sundries and T&P etc. complete as per the direction of Engineer-in-charge. |
| 5 | Foundation |
| 6 | R.C.C. work of M-25 with 20 mm down graded hard granite crusher broken chips including cost, conveyance, royalty and other taxes of all materials to the work site, mixing and laying of concrete in position & compacted properly with all leads, lifts, sundries with all hire & running charges of machineries such as concrete mixer, vibrator etc. required for the work site with proper compaction and curing etc. complete as per the direction of Engineer-in-charge. |
| 7 | C.C. work of M-20 with 12 mm down graded hard granite crusher broken metal including cost, conveyance, royalty and other taxes of all materials to the work site, mixing and laying of concrete in position & compacted properly with all leads, lifts, sundries with all hire & running charges of machineries such as concrete mixer, vibrator etc. required for the work site with proper compaction and curing etc. complete as per the direction of Engineer-in-charge. |
| 8 | Supplying, Fitting & Placing uncoated HYSD bar Reinforcement complet as per drwaing & specification including cost of binding wire, cutting, bending & binding etc Complete as per the direction of Engineer in Charge |
| 9 | Filling bitumen expansation joint board 12 mm thick etc.complete and as per the direction of Engineer-in-charge. |
| 10 | Filling in foundation and Plinth with excavated materials incluiding watering,ramming etc complete as per direction of Engineer in Charge |
| 11 | Excavation of any approved type of soil in approved borrow area by mechanical means loading into and transportation by mechanical means and unloading the soil with all lead on properly prepared and scientifically approved surface including breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 22.5 cm with all leads, lifts, sundreis & T&P required for the work etc. complete as directed by the Engineer-in-charge. |
| 12 | Providing weep holes in Brick masonry / Plain / Reinforced concrete abutment, wing wall / return wall with 70 mm dia PVC pipe of approved specification, extending through the full width of the structure with slope of 1V: 20H towards drawing face and as per drawing and Technical specification including cost, conveyance, royalty, taxes of all materials with all labour, T&P includinng finishing the surface smooth with all leads, lifts and delift including dewatering with required etc. complete & as per direction of the engineer-in-charge. |
| 13 | Supplying and fixing 15cm dia and 1m long guard posts of R.C.C. (1:2:4) using 7.5Kg. Of steel for each guard post with 12mm size H.G.C.B. chips including cost of all reinforcement and materials centering shuttering and watering carrying etc. complete as per direction of the Engineer -in charge. |
| 14 | Wall painting 2 coats with weather coat of approved shade on new work to give an even shade inculding cost of paint .etc as per direction of the Engineer In Charge Please Enable Macros to View BoQ information |