| 1 | Agency for supply&install of stack duct |
| 2 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for UB 1&2 of CPP . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for UB 1&2 of CPP is 12.6 Meter approximatelty . |
| 3 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for FGD of CPP . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for FGD of CPP is 12.8 Meter approximatelty . |
| 4 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 42-AS-001 of CCR . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 42-AS-001 of CCR is 3.2 Meter approximatelty |
| 5 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 805-AS-001 of Incinerator . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 805-AS-001 of Incinerator is 3.2 Meter approximatelty |
| 6 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 56-AH-001 of HCDS . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 56-AH-001 of HCDS is 13.6 Meter approximatelty |
| 7 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 70-MSH-001 of PRU MMS . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 70-MSH-001 of PRU MMS is 3.2 Meter approximatelty |
| 8 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 10-AS-001 of AVU/CDU . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 10-AS-001 of AVU/CDU is 3.2 Meter approximatelty |
| 9 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 10-AS-002 of AVU/VDU . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 10-AS-002 of AVU/VDU is 3.2 Meter approximatelty |
| 10 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 10-AH-001 of AVU/TOC . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 10-AH-001 of AVU/TOC is 3.2 Meter approximatelty |
| 11 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 89-AH-001 of SRU . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 89-AH-001 of SRU is 6.2 Meter approximatelty |
| 12 | Supply ,fabrication and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack for 28-AH-001 of SARU . Spiral duct shall be epoxy painted from inside and outside . Spiral duct shall be installed and fixed using angle channel, clamp ,moore rope . Job to be completed in all respect including man and materilas for proper fixing and installation of spiral duct ,18 guage ,dia 300 mm for fresh air stack.The length of spiral duct ,18 guage ,dia 300 mm for fresh air stack for28-AH-001 of SARU is 3.2 Meter approximatelty |
| 13 | Remove old segment,supply & install new:Bend size, round spiral shape, 18-gauge, GI with 300 mm diameter, length - 2 meter |
| 14 | Remove old segment,supply & install new: Straight piece, round spiral shape,18 gauge, GI with 300 mm diameter, length – 2 meter |
| 15 | Supply and charging of chemical media stage-1 for Fresh Air Unit |
| 16 | Supply and charging of chemical media stage-2 for Fresh Air Unit |
| 17 | Supply Fabrication and installation of GI duct -18 guage (1.25 mm) GSS for fresh air unit as per site Requirement like canopy/duct hood etc |
| 18 | Supply Fabrication and installation of GI duct 1.0 mm (20 gauge) GSS for fresh air unit as per site Requirement like canopy/duct hood etc |
| 19 | Supply and installation of Pre filter :size : 305 x 610 x 50 mm |
| 20 | Supply and installation of Fine Filter: 305 x 610 x 150 mm |
| 21 | Remove old ,supply & install new Mooring metal rope for supporting fresh air stack unit Please Enable Macros to View BoQ information |