| 1 | ऑगनबाड़ी केन्द्र |
| 2 | Earth work in excavation by mechanicalmeans (Hydraulic excavator) /manualmeans in foundation trenches or drains(not exceeding 1.5 m in width or 10 sqmon plan), including dressing of sides andramming of bottoms, lift upto 1.5 m,including getting out the excavated soiland disposal of surplus excavated soil asdirected, within a lead of 50 m. (UPPWDSOR sl. no. 2.8.1 |
| 3 | Earth work in filling of ordinary soil(including royalty) by mechanicaltransport upto a lead of 5km alsoincluding ramming and watering of theearth in layers not exceeding 20 cm intrenches, plinth, sides of foundation etc.complete as per analysis of rates |
| 4 | Providing and laying cement concrete 1: 6:12 (1 cement: 6 C.sand: 8 graded brickaggregate 40mm nominal size.) includingsupply of all materials, labour and T&Petc required for proper completion of thework as per (UPPWD SOR sl no. 273) |
| 5 | R.C.C. work in slab in 1:2:4 in cementcoarse sand & 20mm grade stone gritexcluding supply of reinforcement butexcluding cost of centering and shutteringetc. all respects as pwd S.I. No. 5.1.3 |
| 6 | Mild steel or iron in plain work such asreinforced concrete or reinforced, brickwork (when not included in an over allrates) wrought to required shape asnecessary including bending for propercompletion of the work and includingsupply of steel its wastage bend hooks(UPPWD SOR sl. no. 504) |
| 7 | First class brick work in 1:4 cement andcoarse sand of 1.25 FM mortar infoundation and plinth including supply ofall materials , labour and T&P etc requiredfor proper completion of work (UPPWDSOR sl. no. 6.1.1) |
| 8 | First class brick work in 1:4 cement andcoarse sand of 1.25 FM mortar in insuperstructure including supply of allmaterials , labour and T&P etc requiredfor proper completion of work (UPPWDSOR sl. no. 6.4.1) |
| 9 | 12mm thick plaster in 1:4 in cement andcoarse sand including including supply ofmaterials, labour, tools, plants etc.required for proper completion of thework.(UPPWD SOR sl. no. 13.4.1) |
| 10 | Providing and fixing 1mm thick M.S.sheet door with frame of 40x40x6 mmangle iron and 3 mm M.S. gusset plates atthe junctions and corners, all necessaryfittings complete, including applying apriming coat of approved steel primers:Using M.S. angels 40x40x6 mm fordiagonal braces (UPPWD SOR sl. no.10.5.1) |
| 11 | Providing and laying cement concrete 1: 2:4 (1 cement: 2 C.sand: 20 graded stoneaggregate 20mm nominal size.) includingsupply of all materials, labour and T&Petc required for proper completion of thework (UPPWD SOR sl. no. 4.1.3) |
| 12 | Providing and laying Ceramic glazed floortiles of size 300x300 mm of 1st qualityconformingto IS : 15622, of approvedmake, in all colours, shades, except White,Ivory, Grey, Fume Red Brown, laid on 20mm thick bed of cement mortar 1:4 (1Cement : 4 Coarse sand), jointing withgrey cement slurry @ 3.3 kg/ sq.mincluding pointing the joints with whitecement and matching pigments etc.,complete (UPPWD SOR sl. no. 11.3.1) |
| 13 | Providing and fixing Ist quality ceramicglazed wall tiles conforming to IS: 15622(thickness to be specified by themanufacturer), of approved make, in allcolours, shades except burgundy, bottlegreen, black of any size as approved byEngineer-in-Charge, in skirting, risers ofsteps and dados, over 12 mm thick bed ofcement mortar 1:3 (1 cement : 3 coarsesand) and jointing with grey cement slurry@ 3.3kg per sqm, including pointing inwhite cement mixed with pigment ofmatching shade complete (UPPWD SORsl. no. 8.31) |
| 14 | Steel work welded in built up sections/framed work, including cutting, hoisting,fixing in position and applying a primingcoat of approved steel primer usingstructural steel etc. as required: Ingratings, frames, guard bar, ladder,railings, brackets, gates and similar works(UPPWD SOR sl. no. 10.25.2) |
| 15 | Providing and applying of white cementbased putty of average thickness of 1 mmof approved brand and manufacture overplastered wall surface.(UPPWD SOR sl.no. 13.80) |
| 16 | Wall painting with plastic emulsion paintof approved brand and manufacture togive even shade: two coat.(UPPWD SORsl. no. 13.60.1) |
| 17 | Painting roof or other iron work ofapproved make and quality on new workwith three coats ti give an even shadeincluding all material labour and T&P etcrequired for proper completion of work. As |
| 18 | (iii) Suspended floors, roofs, landings,balconies and access platform (UPPWDSOR sl. no. 5.9.3) |
| 19 | (iv) Lintels, beams, plinth beams, girders,bressumers and cantilevers (UPPWDSOR sl. no. 5.9.5) |
| 20 | (v) Columns, Pillars, Piers, Abutments,Posts and Struts (UPPWD SOR sl. no.5.9.6) |
| 21 | P/F of display/ inauguration black graniteboard including letter writing etc. All costcomplete |
| 22 | Add 3.75% for electrical external service connections |
| 23 | Add 8% for internal water supply and sanitary installations Please Enable Macros to View BoQ information |