| 1 | Filling Foundation and plinth with sand watered and rammed including cost,carriage and royalty etc complete. |
| 2 | RCC M20 work with cement concrete with crushed granite of 20mm and down grade course aggregate of approved quality mixed by concrete mixture including,hoisting,lowering and laying the concrete in position to proper slope and level and compaction by vibrators in layers not exceeding 0.15mtr depth including watering ,curing for required period 28days centering and shuttering and finishing exposed surface smooth providing grooves whereever necessary including cost,conveyance royalty and other taxes of all materials required for this item including Hire amd running charges of Mixture machine.( i)RCC Column up to Lintel level |
| 3 | RCC Column up to roof level |
| 4 | RCC lintel |
| 5 | RCC chajjja |
| 6 | RCC stair case |
| 7 | RCC roof beam |
| 8 | RCC roof slab |
| 9 | in sill bend |
| 10 | Straightenening bent up or coiled MS Rod or HYSD steel (Fe-415) cutting,bending,hooking,welding or joining (if required) the MS rod or HYSD steel and binding,tying the grills hoisting,lowering and placing in proper position as required for RCC work including,cost, conveyance and taxes of MS rod or HYSD steel and binding wires of 18 to 20gauge and labour charges required for the work etc. complete as per the direction of enginner in charge |
| 11 | Brick work with fly ash brick masonry in CM (1:6)in Super structure of size 23cm x11 cmx 8 cm having crushing strength not less than 75 kg/cm2 with dimentional tolerance + 8% with watering and curing after immersing the brick in water at least for six hour before use including cost, conveyance & royalty of materials with labour charges etc. complete in all respect as per the direction of engineer in charge. |
| 12 | Brick work with fly ash brick masonry in CM (1:6)in Super structure of size 23cm x11 cmx 8 cm having crushing strength not less than 75 kg/cm2 with dimentional tolerance + 8% with watering and curing after immersing the brick in water at least for six hour before use including cost, conveyance & royalty of materials with labour charges etc. complete in all respect as per the direction of engineer in charge. |
| 13 | 12mm thick cement plaster (1:6) finishing smooth to outside surface of brick wall after racking out the joint including watering and curing with cost, conveyance and royalty and taxes of all materials and cost of all labour charges required for the work etc. complete. as per the direction of engineer in charge. |
| 14 | 16mm thick cement plaster (1:6) finishing smooth to inside surface of brick wall after racking out the joint including watering and curing with cost, conveyance and royalty and taxes of all materials and cost of all labour charges required for the work etc. complete. as per the direction of engineer in charge. |
| 15 | 6mm thick cement plaster (1:4) finishing smooth to RCC surface with chisilling including watering and curing with cost,conveyance and royalty and taxes of all materials and cost of all labour charges required for the work etc. complete. as per the direction of engineer in charge. |
| 16 | 25 mm thick grading concrete in CC (1:2:2) on roof slab with 4.7mm size HGCB chips including,cost,conveyance and royalty of materials and labour charges complete. |
| 17 | Supplying,fitting and fixing of vitrified tiles of size 600mm x600mm in floor,treads,steps and landing on 25 mm thick bed of cement mortar(1:1) joined with neat cement slurry mixed with pigment to match the shades of the tile including rubbing and polishing with cost conveyance of all materials including cost of tiles etc. complete and as per direction of engineer in charge. |
| 18 | Supplying,fitting and fixing of vitrified tiles in dado,skirting and rises of the steps on 12mm thick cement plaster incement mortar(1:3) with neat cement slurry mixed with pigment to match the shades of the tile including rubbing and polishing with cost conveyance of all materials including cost of tiles etc. complete and as per direction of engineer in charge. |
| 19 | primming one coat to plaster surface with any approved primer including cost of primer ,labour with T &P required for the work etc. complete in all respect and as per the direction of engineer in charge |
| 20 | Finishing wall surface with acrylic wall putty(water based) of approved make and finished smooth and even surface to receive painting includimg cost of materials ,labour with T &P required for the work in all respect and as per the direction of engineer in charge |
| 21 | Wall painting two coat with interior plastic emulsion paint of any approved shade to new work to give an even shade including cost of paints, labour with T &P required for the work in all respect and as per the direction of engineer in charge. |
| 22 | Wall painting two coat with exterior weather paint of any approved shade to new work to give an even shade including cost of paints, labour with T &P required for the work in all respect and as per the direction of engineer in charge. |
| 23 | Supplying,fitting,fixing of MS door and windows including cost,conveyance of material and labour charges all respect complete . |
| 24 | Painting two coat with any approved paint over a coat of primer over MS door and windows with cost of primer,paint and labour in all respect and as per the direction of engineer in charge . |
| 25 | Supplying, fitting, fixing up window ( sliding type ) made up aluminium section 151-154, 151-155, 151-153 and 151-167 as shutter frame with 5mm thick black glass as pannel fitted with rubber beading including locking arrangement including all fitting including cost of materials all taxes labour T & P etc complete as per direction of Engineer in charge. |
| 26 | Providing fitting, fixing of Al. door with OEL anodized Al. door section of 9202 as vertical member, 9201 as top member and 9200 as bottom and middle member and 12mm thick pre-laminated board fixed on door frame by means of tapered clip No. 4660 and the frame to be completed by means of jointing angle No. 1855 including all cost of labour, T&P , hire charges of drilling machine, labour charges etc. complete. Please Enable Macros to View BoQ information |