| 1 | Total amount of the \\"Rate Schedule\\" sheet SCHEDULE OF QUANTITY AND RATE FOR INCREASING CAPACITY FROM 100 KVA TO 250 KVA TRANSFORMERS AT VARIOUS SITE OF SHIVGANGA, POLYTECHNIC, M.V. HOME, VIDHATA, BANSAL ENCLAVE, NEGI MOHALLA AND RAJESHWAR NP5 UNDER IT PARK 2 UNDER EDSD, IT PARK UNDER EDD, RAIPUR AGAINST E-TENDER SPECIFICATION NO. 04/EDCRDDUN/2026-27 1- Est.No.-1(IR.SR2503370)- I/C of 100 KVA to 250 KVA T/F at site Shivganga & Polytechnic under IT Park22- Est.No.-2(IR.SR2503373)- I/C of 100 KVA to 250 KVA T/F at site M.V. Home under IT Park23- Est.No.-3(IR.SR2503377)- I/C of 100 KVA to 250 KVA T/F at site Vidhata & Bansal Enclave under IT Park24- Est.No.-4(IR.SR2503378)- I/C of 100 KVA to 250 KVA T/F at site Negi Mohalla & Rajeshwar NP5 under IT Park2 Name of The Bidder's Firm: 0.0 Sl. No. Description of Work Unit Est.-1 Est.-2 Est.-3 Est.-4 TotalQty Rate Amount Part [A] (Supply Portion) |
| 2 | Holding Clamp for ST Pole SP-55 with N&B |
| 3 | LT Clamp for PCC Pole with N&B |
| 4 | Stay Clamp for ST Pole SP-55 with N&B |
| 5 | LT Clamp for ST Pole SP-23 with N&B |
| 6 | LT Clamp for ST Pole SP-55 with N&B |
| 7 | Dead End Clamp with J Hook |
| 8 | Suspension Clamp with J Hook |
| 9 | MS Clamp with N&B for Distribution Box |
| 10 | Shackle Insulator 100x115 mm with N&B |
| 11 | Distribution Box with N&B AB cable 3 Phase-4Way |
| 12 | Insulation Piercing connector 120 sqmm -50 sqmm |
| 13 | Providing Air Circuit Breaker type complete LT Distribution board for 250/400 KVA DTR fitted with 01 No. 800 Amp CT including microprocessor release IPR-1 Fixed type (4 Pole as per IS: 13947-2 & IEC: 60947-2) with panel and mounting structure as per specification |
| 14 | Bolt & Nuts off size |
| 15 | LT XLPE Cable 1x50 sqmm |
| 16 | 11 KV Fuse Set |
| 17 | LT Fuse set with Fuse Wire |
| 18 | Al. Crimping type lugs 240 sq mm |
| 19 | GI Strip 40x6 mm Total - Part [A] 0.0 Part [B] (Labour Portion) |
| 20 | Carriage of following type of Material from store centre/JE store to site of work distance approximate 0-20 km. With loading & unloading complete: - a) ST Pole SP-55 (Galvanized) Nos 4.0 2.0 2.0 2.0 10.0 0.0 b) 100 KVA T/F Nos 2.0 1.0 2.0 2.0 7.0 0.0 c) 250 KVA T/F Nos 2.0 1.0 2.0 2.0 7.0 0.0 d) Stock Material Qtl 65.24 39.06 60.95 64.52 229.77 0.0 |
| 21 | Head load cartage of following material from road to site (0-1 Km) a) ST Pole SP-55 (Galvanized) Nos 4.0 2.0 2.0 2.0 10.0 0.0 b) 100 KVA T/F Nos 2.0 1.0 2.0 2.0 7.0 0.0 c) 250 KVA T/F Nos 2.0 1.0 2.0 2.0 7.0 0.0 d) Stock Material Qtl 65.24 39.06 60.95 64.52 229.77 0.0 |
| 22 | Excavation of earth for pole pit of size 0.9x0.6x1/6 of full length of pole for erection of pole in all type of soil including proper dressing of sides and ramming of bottom including getting out the excavated soil and disposal of surplus excavated soil as directed complete work |
| 23 | Erection of following Double support pole in proper level and alignment alongwith fixing of all accessories, like top channel, X-bracing & clamps as per RESPO construction Manual. ST Pole SP-55 (Galvanized) Nos 2.0 1.0 1.0 1.0 5.0 0.0 |
| 24 | Grouting of pole in size 0.45x0.45x1/9 of the support in CC ratio 1:4:8 (1 cement : 4 graded stone 20mm nominal size : 8 coarse sand ) block including cost of Cement,sand and stone ballast back filling of soil and boulders in pit and ramming and proper alignment, leveling as per RESPO construction Manual. |
| 25 | Muffing of poles size 0.45 cm x 0.60 cm radious with cc 1:3:6 (1 cement : 3 coarse sand : 6 graded stone 10mm nominal size) block size 45cm height from ground level including cost of cement, stone and sand etc. |
| 26 | Fabrication of M.S. Channel Angle iron after cutting in required sizes with drilling of holes upto good finish for top channel, bracing and special type bracket etc as per RESPO sehedule and local approved drawing. |
| 27 | Erection and Earthing of support with M.S. Earth rod of 2.5 meter long including excavation of pit and digging of M.S. Rod to proper depth and connecting the earth electrode with the help of G.I. wire as per construction manual. |
| 28 | Making of section Pole |
| 29 | Layiing of ACSR Rabbit Conductor in HT Line |
| 30 | Dismantling of LT Line 3 Phase 4 wire (ACSR Weasel conductor) |
| 31 | Installation of 250 KVA T/F on Pole Structure |
| 32 | Laying & Fixing of LT XLPE cable |
| 33 | Earthing of T/F LA & Body |
| 34 | Jumpering of DP TPMO, Fuse Set and T/F |
| 35 | Installation of LT ACB Pannel complete in all respect i.e. disconnection of existing cable from DTR terminal and metering cubucals, fixing of new additional cable in ACB LT Distribution board connecting DTR metering complete, testing and commissioning of ACB connection using all lugs pf proper size lugs will be provided by supplier as per required on site and narrated by engineer in change of work. |
| 36 | Installation of LT distribution Box. |
| 37 | Earthing of ACB |
| 38 | Fixing of Fuse Set |
| 39 | Fixing of LT Fuse Set |
| 40 | Fixing of Accessories |
| 41 | Fixing of Channel, Angle on Pole |
| 42 | Excavation, Erection of stay set complete work. |
| 43 | Providing and fixing of Danger Board and number plate complete by providing clamps of M.S. Flat 50x6 mm and Nuts & Bolts, danger Boards of M.S. Sheet 2 mm Thick 11''x7'' size (Including cost of all material) |
| 44 | T-off connection complete 11 KV line |
| 45 | Back carriagee of scrap material |
| 46 | Dismantling of PCC double Pole |
| 47 | Dismantling of LT XLPE AB cable 3x120+1x95+1x16 sq mm |
| 48 | Dismantling of 100 KVA DTR |
| 49 | Dismantling of accessories from ST Pole Total - Part [B] 0.0 TOTAL [Part-(A) + Part (B)] 0.0 Place Date Superintending Engineer Please Enable Macros to View BoQ information |