| 1 | Earth work in all kind of soil for excavation of foundation within initial lead of 50m. and lift of 1.50m including rough dressing, breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3 m in depth As per direction of Engineer in charge . |
| 2 | Sand filling in foundation and plinth with approved river sand well watered and rammed.including cost, conveyance, royalty taxes of all metarials, etc completed as per the direction of the Engineer-in-charge. |
| 3 | Plain Cement Concrete (1:3:6) using 40 mm size H.G. metal ( crusser brocken ) well rammed including cost, conveyance, royalty taxes of all metarials, etc completed as per the direction of the Engineer-in-charge. |
| 4 | Fly Ash Brick masonary of size 25 cm. x 12 cm. x 8 cm. having crushing strength not less than 75 kg. per sqr.cm. in cement mortar (1:6) in foundation & plinth with all cost ,carraige & all taxes etc. complete in all respect as directed by the Engineer-in charge. |
| 5 | Providing and laying Cement Concrete M25 using 20mm size down graded B.H.G. chips for R.C.C. works including cost, carraige, rayality of all materials and machinaries and labours,( including centring & shuttering ) lifts etc complete as per approved drawings & specification & direction of the Engineer-in-charge. (A) Column base footings |
| 6 | (B) Plinth beam |
| 7 | ('C) Lintel |
| 8 | (D) Wall beam |
| 9 | ('E) Roof slab |
| 10 | Supplying, cutting, bending, binding, straightening the reinforcement HYSD steel bar of different diameters including quality control testing charges complete as per specification & direction of Engineer-in-charge. |
| 11 | Fly Ash Brick masonary of size 25 cm. x 12 cm. x 8 cm. having crushing strength not less than 75 kg. per sqr.cm. in cement mortar (1:6) in super structure with all cost ,carraige & all taxes etc. complete in all respect as directed by the Engineer-in charge. |
| 12 | Providing 20 mm thick grading plaster (1:4) |
| 13 | 16 mm thick cement plaster with cement mortar (1:6) over stone/brick masonary |
| 14 | 12 mm thick cement plaster with cement mortar (1:6) over stone/brick masonary |
| 15 | 6 mm thick cement plaster with cement mortar (1:4) to R.C.C. surfaces finished smooth including closed deep chipping & slurry treatment. |
| 16 | 12 mm thick cement plaster with cement mortar (1:4) over brick masonary with cement punning for skirting including all cost, conveyance & royalty etc complete as per direction of the Engineer-in-charge. |
| 17 | Plain Cement Concrete (1:4:8) using 40 mm size H.G. metal ( crusser brocken ) well rammed including cost, conveyance, royalty taxes of all metarials, etc completed as per the direction of the Engineer-in-charge. |
| 18 | M.S.Grill |
| 19 | Enamel paint 2 coats over 1 coat of primer |
| 20 | Finishing walls with weather coat of approved shade on new work 2 coats to to give an shade over 1 coat of wall primer |
| 21 | Labour charges for fitting and fixing M.S window & door (Door-1 & Door-2) |
| 22 | Labour charges for fitting and fixing M.S window & door (V-1 & Windows) |
| 23 | 12 mm thick cement plaster with cement mortar (1:4) over brick masonary with cement punning for skirting including all cost, conveyance & royalty etc complete as per direction of the Engineer-in-charge. Please Enable Macros to View BoQ information |