| 1 | Based on analysis |
| 2 | Brick work with clay flyash F.P.S. (non modular) brick of class designation 7.5 in superstructure above plinth level up to floor five level in : Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 3 | 12 mm cement plaster finished with a floating coat of neat cement of mix : 1:4 (1 cement: 4 fine sand) |
| 4 | Satna lime wash on walls with one coat. |
| 5 | 12 mm cement plaster of mix : 1:6 (1 cement: 6 fine sand) |
| 6 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 7 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.(Material will be supplied by departmentally.) In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 8 | Recess cutting in stone |
| 9 | Muck & debris cleaning & disposal up to 15.0 M |
| 10 | Brick work withFly ash bricks of class desgn 75 in foundation and plinth in : Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 11 | Half brick Masonery with flyash F.P.S (non modular) brick of class designation 7.5 in foundations and plinth in : Cement morter 1:4 (1 cement : 4 coarse sand) |
| 12 | Half brick Masonery with clay flyash F.P.S (non modular) brick of class designation 7.5 in superstructure above plinth level up to floor V level. |
| 13 | One layer brick flat soling with fly ash bricks,joints filleed with local sand or powdered earth. |
| 14 | Loading material(sand and stone aggregate below 40 mm nominal size) into MUV and unloading at UG |
| 15 | Loading material(bricks) into MUV and unloading at UG |
| 16 | Loading material(cement) into MUV and unloading at UG |
| 17 | Loading material(steel) into MUV and unloading at UG |
| 18 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |