| 1 | Civil and Structural works : |
| 2 | 1) Modification of the existing HVAC system as per the existing site condition to maintain design parammeter.This job includes necessary modification of ductwork, piping, electrical connections, and structural supports.All dismantled materials and debris to be removed and disposed as per instruction by the Engineering in-charge. Site preparation work including levelling, excavation, and backfilling as required for new installations. Construction of new foundations and structural supports for HVAC system and other electro-mechanical systems. All civil and structural works to be executed in accordance with the relevant drawing and specification duly approved by concerned Engineering in-charge. Construction of a new shed to house mechanical equipment. The scope includes roofing, cladding, supporting steel structures, and all necessary civil and structural works. Construction of a dedicated electrical room to accommodate the new MCC panel. Includes all required civil works (walls, roofing, flooring), structural framing, electrical provisions, lighting, ventilation etc. as required as per the site requirement2) Upgradation of clean room system to keep provision for dedicated air lock room at the main entry corridor area. Air lock room should have minimum difference 5 Pa positive air pressure compare to the dirty corridor and entry corridor.2.01) Supply, Installation, Testing and Commissioning of Double skin Clean room Wall Cladding, Wall Partition Panel system 80 mm thick , PUF infilled powder coated GI sheet, as per specification complete with concealed conduits for power socket, data, telephone points and necessary factory finished cut-outs for double gazed view panels and doors. Double skin sandwich type GSS/CRCA Powder coated Metallic ceiling panels of 0.6 mm thickness on both sides, PUF in-filled with 40+/-2 Kg/m3 density insulation. Complete with Extruded aluminium powder coated supports and hanging arrangement, with aluminium profiles that create uniform seams. The Partition seams are sealed by RTV silicone with a perfectly flush finishing. PUF insulation material is sandwiched between the two skin layers and sealed from the exterior by the GI frame work including all cut-outs factory fitted, for Air terminals/Diffusers and lighting etc. including necessary utility cut-outs duly concealed, as per specification, including necessary utility factory finished cut-outs duly concealed as per specification3) Supply, Installation, Testing and Commissioning of Clean room compatible Single Leaf Doors 1200 (W)x2100mm (H) as per specification with door closure, SS-'D' handle, Push plate and kick plate along with 480x750 double glazing view panel & Drop-seal4) Supply, Installation, Testing and Commissioning 2-Door Interlock system with Electromagnetic Strike lock unit and Egress Button for air lock for entry gate and dirty corridor gate |
| 3 | AC works :Modular Outdoor TFA Double skin Air Handling Units of 43+/- 2 mm thick PUF injected panels with 24 gauge GI inner skin and pre-coated GI outer skin all as per specification including fan with TEFC motor. AHU shall have Air intake louver combined with pre filter (EU-3), Fine Filter section (EU-9), HEPA filter section (EU-13), coil section with DX 6-Row coil, blower section with DIDW (double inlet double width) centrifugal fan having static pressure of 140 mm/Wg with TWIN MOTOR ARRANGEMENT (1S +1W). The AHU complete in single/double tier construction with Thermal break profile having various sections like Aluminium Fresh air louver section with louver, filter section, fan section, coil section and supply air plenum etc. The AHU having TEFC (totally enclosed Fan Cooled) motor with VFD, Cooling & heating coil, moisture eliminator. AHU should be designed for maximum 2.5m/s face velocity on filters & coils and sections having filters should be provided with necessary port for measuring pressure differential with the help of magnehelic gauge mounted over the AHU itself for regular maintenance of filters. AHU should be provided service windows of suitable width for maintenance of various sections and inspection windows should be provided glass panels for viewing inside the AHU. AHU panel thickness should be 43+/-2mm injected with PUF and sheet thickness should be 22/24. Drain pan of all the AHUs should be dully insulated and material of construction should be 1 mm SS304. Additional safety accessories like Cushy foot mountings, Limits switches for access doors, inspection lamp, Fire proof double canvass connections (Fungal resistant and Lint free) should also be provided along with AHU. |
| 4 | AHU - 1 (New) : Supply, Installation, Testing and Commissioning of TFA type 100% FA Unit with 140 mm WG Static pressure - for following rooms : i) Breeding Room comprising of 3 ventilator suitable for 6 rack ii) Mice Room-1 comprising of 5 ventilator suitable for 8 rack iii) Mice Room - 2 comprising of 3 ventilator suitable for 5 rack. (necessary upgradation of the said rooms air circulation to be considered in this unit))AHU - 2 (New) : Supply, Installation, Testing and Commissioning of TFA type 100% FA Unit with 140 mmWG Static pressure - for following roomsi) Animal Experimentation Room comprising of 2 ventilator suitable for 4 rackii) Office Room to maintain desired room temperature and RHiii) IN-VIVO Room to maintain desired room temperature and RHiii) Necropsy Room to maintain desired room temperature and RH (Necessary upgradation of the said rooms air circulation to be considered in this unit) |
| 5 | Modification, upgradation of the existing AHU-3 ducting system for the Quarantine Room's air circulation as required design parameter considering two (2) ventilator |
| 6 | EAU-1 (New) : Supply, Installation, Testing and Commissioning of Exhaust 100% EA Unit with 125 mmWG Static pressure, TWIN MOTOR arrangement (1S +1W), dedicated exhaust from the 13 nos IVC-Ventilators should be considered in this EAU unit capacity. Rooms are as followsi) Quarantine Room : 2 nosii) Breeding Room : 3 nosiii) Mice Room -2 : 3 nos.iv) Mice Room -1 : 5 nosEAU-2 (New) : Supply, Installation, Testing and Commissioning of Exhaust 100% EA Unit with 125 mm WG Static pressure, TWIN MOTOR arrangement (1S +1W) dedicated exhaust from the 2 nos IVC-Ventilators should be considered in this EAU unit capacity. Rooms are as followsi) Animal Experimentation Room : 2 nos. |
| 7 | Modification and upgradation of all existing 3 numbers AHU (Air Handling Units) and existing 3 numbers EAU (Exhaust Air handling units) as necessary for the desired design parameters to be kept inside the facility zones |
| 8 | Supply, Installation, Testing and Commissioning of Air cooled DX Condensing unit - 5.5 TR X 2 set = 11 TR (2 Working) complete with multiple compressors complete with suitable for operation on R32/R-410A/R-407 Green refrigerant comprising of Scroll type compressor hermetically sealed complete with automatic capacity, safety switches, lubrication system, suitable for operation on 415+10% volts, 50 Hz, necessary support structure including all accessories in all respect. |
| 9 | Supplying, fixing, testing commissioning of Refrigerant Piping system including Refrigerant Gas charging, Drier filters and necessary valves & fittings including thermal Insulation for 4 sets of new Air cooled Condensing units |
| 10 | Air Distribution System :1) Supply, installation, balancing and commissioning of fabricated at site GSS sheet metal / non-ferrous re-inforce spiral flexible ducting rectangular/ round ducting complete with neoprene rubber gaskets, elbows, splitter dampers, vanes, hangers, supports, MS painted flanges, all joints sealed with RTD silicon sealant with MS painted supports as per IS-266 with Zinc deposition 120gms/sqm. etc. as per approved drawings and specifications of following sheet thickness complete as required.1.01) Thickness 0.63 mm sheet / non-ferrous re-inforce spiral flexible ducting1.02) Thickness 0.80 mm sheet / non-ferrous re-inforce spiral flexible ducting2) Supplying, fixing testing commissioning of Aluminium Gear Operated volume control dampers for AHU, ducting and exhaust fans3) Supplying and fixing of following thickness duly laminated aluminium foil of mat finish closed cell Nitrile rubber (Class \\"O\\") insulation on existing duct after applying suitable adhesive for Nitrile rubber. The joints shall be sealed with 50 mm wide and 3 mm thick self adhesive nitrile rubber tape insulation complete as per specifications and as required.19 mm Thickness |
| 11 | Supplying, fixing, testing commissioning of Fuseable link type UL 99 rated fire dampers at AHUs (new) & EAUs (new) at Supply air and Exhaust air system. Modification of existing system's fire damper at existing AHUs, if required. |
| 12 | Supplying, fixing, testing commissioning of extruded aluminium powder coated supply/ exhaust air diffusers with black matt finish VCD (volume control damper) |
| 13 | Supply of following specification motor for existing AHU-1, AHU-2 and AHU-3 |
| 14 | 3.7 KW, 5.0 HP, r/ Min :1435, V : 415 D +/-10%, Hz : 50 +/-5%, A: 7.50 , |
| 15 | 2.2 KW, 3.0 HP, r/ Min :2878, V : 415 D +/-10%, Hz : 50 +/-5%, A: 4.4 , |
| 16 | Providing RTV silicone and sealed with a perfectly flush finishing entire the Animal house facility to protect air leakage. This job included black film application for the corridor-side glass. |
| 17 | Electrical Works:MCC (New) : Supply, Installation, Testing and Commissioning of main electrical LT panel with suitable Amps bus bar and sub panels for HVAC control system. panels shall have aluminium bus bar and required breakers and necessary tripping arrangement. (Free floor/wall mounted, indoor type, front operated, Top/Bottom cable entry. Panels made out of powder coated 2 mm sheet steel, PVC colour coded with humidity control system |
| 18 | Supply, Installation, Testing and Commissioning of electrical power Cabling 1.1 KV grade PVC/ XLPE insulated aluminium/ copper conductor armoured/ unarmoured cables on cable tray(copper / aluminium armoured / flexible cables), control cables (copper), (for plug points and power Sockets) additional power points inside the Quarantine Room, Animal Experimental Room, Breeding Room, Mice Room-1 and Mice Room -2 along with 5 Pin / 15 Amps power sockets and switches. dedicated PDB/LDB unit with MCCB/MCBs. as required as per site condition and standard engg. practice. (1) Power supply and additional power sockets arrangement at the Necropsy Room to cater to the X-ray machine.(2) Implementation of a red light arrangement with a night-day timer modulating sensor.(3) Necessary modifications to the cabling work. including the supply and laying of cables from the main switchyard room to the UPS room. This should include cable management, distribution boards (DB), LDB/PDB, etc. |
| 19 | Supply, Installation, Testing and Commissioning of variable frequency drive (VFD) and enclosure & exhaust air ventilation fan - ABB |
| 20 | Supply, Installation, Testing and Commissioning of duct mounted heating element for TFA units with flow & RH sensor interlocking |
| 21 | Modification, upgradation of CCTV surveillance System with with addition cameras of each room with night vision movement detection auto start IP based Cameras. (16 channel fully HD DVR system with 10 sets high resolution night vision cameras) |
| 22 | Supply, Installation, Testing and Commissioning of Air Curtain suitable for main entrance door space. Material: aluminium body size: 6 Feet (1828 MM) No. of blowers: 4, motors: 2 @ 120W. 1200 x 208 x 235 mm./ 1. impeller Size: 6\\" x 6\\" 5) blower diameter:120mm / suction grill: ABS plastic 6) material of blower: ABS 300, Virgin / 7 tank process powder coating 7) noise level: 63 DB on a AE scale/chassis: Aluminium with powder coated surface |
| 23 | Supply, Installation, Testing and Commissioning of 30 KVA 3-Phase Input / 3-Phase Output online UPS system. Inbuilt static changeover Switch, high input voltage band, DSP control based system, With UNITY Output Power Factor, With 0.99 Input Power Factor, with parallel option, suitable for 30 mins. Back up, including suitable batteries, Rack, Interlink cabling etc.Equipments / items to be connected with UPS are as follows.i) All Air Handling Units (AHUs)ii) 50% of lights and power circuitsii) Exhaust Air Handling Systemiv) All IVC exhaust fansv) Complete Building Management System (BMS)VI) Safety and security systems (e.g., access control, CCTV, door interlock systems, emergency fire alarm systems) |
| 24 | BMS, Automation system works |
| 25 | Up-Gradation of Existing BMS, Automation system: Supply, Installation, Testing and Commissioning of Additional DDC Controller with DDC Panel S55372-C121 - PXC36.1-E.D + DDC Panel, QFM2120 Hum/Tmp.sensor duct 0- 10V/LGNi, QAA2061 Temperature sensor room 0- 10V, QBM2030-1U Diff. pressure sensor, E.D + DDC Panel. Power & Communication cabling including termination and commissioning at site. and integration with existing BMS PC arrangement.(a) Following parameters monitoring in real time basis- i) Temperature reading in each room in real time ii) Humidity reading in each room in real time , iii) Diff. pressure of zone in real time iv) All field equipments (AHUs, EAUs, Pums, Heaters, Pan humidifiers etc.) except chiller units can control by the BMS system(b) Supplying, fixing, testing commissioning of Duct mounted Air-flow sensors(c) Supplying, fixing, testing commissioning of Exhaust duct Temperature sensors(d) Supplying, fixing, testing commissioning of Ceiling mounted mounted temperature sensors in each room(e) Supplying, fixing, testing commissioning of Ceiling mounted mounted Relative Humidity (RH) sensors in each room(f) Supplying, fixing, testing commissioning of portable Temperature and Relative Humidity meter -10 nos to monitor real time Temperature and Relative Humidity (RH) from inside the Animal room facility(g) Upgradation of the PAN humidifiers through humidity thermostat.(h) Upgradation of Access control status monitoring should be managed from two - i) Operator ii) User |
| 26 | Animal lab Testing, Validation |
| 27 | Validation, Testing and Documentation by ISO /IEC 17025 & NABL certified external agency.1) Light test for duct2) Air Balancing and velocity profile test3) Pressure balancing test4) Particle count test5) Temperature and RH test for each room6) Filter Intrigrity test7) Air Flow pattern Test8) Sound level measurement9) Differential pressure checking / Balancing10) Light Intensity Test11) ACPH Test Please Enable Macros to View BoQ information |