Name of Work:- Construction of Community Hall at-17 Parivar Panda Park, Sitanath A & B Science Park, Somanath at Ward No.14
Sl. No.
Item Description
1
Earth work in foundation in hard soil or gravelly soil within 50mtr. initial lead and 1.50mtr initial lift including rough dressing and levelling the bed
2
Filling F&P with sand well watered and rammed.
3
C:C: (1:4:8) using 4 cm. size H.G. metal (C.B) including the cost of all materials, labour etc complete.
4
R.C.C. work of M20 grade with 20 mm down grade chips (C.B.) including Hoisting & laying. Cloumn Base
5
Column
6
Plinth Beam
7
Lintel
8
Chajja
9
Roof Beam
10
Roof Slab
11
Labour charges for cutting, bending, binding and tying the grill including the cost of M.S. rod.
12
Fly ash brick masonry in C.M. (1:6) in founadtion & plinth using 25cm x 12cm x 8cm brick having crushing strength not less than 75 Kg / cm2
13
Fly ash brick masonry in C.M. (1:6) in super structure using 25cm x 12cm x 8cm brick having crushing strength not less than 75 Kg / cm2
14
12mm thick C:P (1:6) over brick work
15
16mm thick C:P (1:6) over brick & stone masonry
16
6mm thick C:P (1:4) to R.C.C. surface finished smooth including closed deep chipping and slurry treatment.
17
Fixing tiles in floors, treads or steps and landing over 25mm bed of C:M (1:1) jointed with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing complete excluding the cost of pre-cast tiles
18
Fixing tiles in dados, skirting and risers of steps on 12mm C:P (1:3) jointed with neat cement slurry mixed with pigment to match the shade of the tiles including rubbing and polishing complete excluding cost of precast tiles.
19
Painting two coats with weather seal coat over a coat of water bound wall primer.
20
Wall painting two coats with plastic emulsion paint with cost of paint including primer.
21
Supplying M.S Grill Gate made out of M S Angle, MS Flat, MS Sqr bar and MS Sheet of approved design including cost of materials fabrication cost and delivering at work site.
22
Painting two coats over a coat of priming over new wood work & Iron work with the cost of primer & paint.
23
Electrification Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.