| 1 | 17.5.217.5 Demolishing stone rubble masonry including stacking of usable material and disposal of unuseable material within 50 meters lead inclusive of de-watering wherever required. 17.5.2 In cement mortar |
| 2 | 18.28.2.218.28.2.4 Providing, laying and fixing in position RCC spun or hume pipe with collars (ISI 458-2003) in required size packed in gasket for hume or spun yarn and neatly finished with rich grout of cement mortar 1:3 perfectly air tight including testing of joints. (diametre) 200mm ( Excluding Labour Charges ) NP-3 Providing, laying and fixing in position RCC spun or hume pipe with collars (ISI 458-2003) in required size packed in gasket for hume or spun yarn and neatly finished with rich grout of cement mortar 1:3 perfectly air tight including testing of joints.(diametre) 200mm (Labour Charges only) |
| 3 | 18.28.7.218.28.7.4Providing, laying and fixing in position RCC spun or hume pipe with collars (ISI 458-2003) in required size packed in gasket for hume or spun yarn and neatly finished with rich grout of cement mortar 1:3 perfectly air tight including testing of joints. (diametre) 900mm ( Excluding Labour Charges ) NP-3 Providing, laying and fixing in position RCC spun or hume pipe with collars (ISI 458-2003) in required size packed in gasket for hume or spun yarn and neatly finished with rich grout of cement mortar 1:3 perfectly air tight including testing of joints.(diametre) 900mm (Labour Charges only) |
| 4 | 4.21.1.1 Hydraulic excavator/ loader like JCB/ Poclain, Hitachi etc. with all accessories (for actual site working, idle period) having bucket capacity upto 0.40 cum Hire charges without diesel but with operational staff M.oil, spares and lubricants (in Rs) |
| 5 | 4.21.1.4Hydraulic excavator/ loader like JCB/ Poclain, Hitachi etc. with all accessories (for actual site working, idle period) having bucket capacity upto 0.40 cum Idle charges (in Rs.) |
| 6 | 2.27Cost of Diesel |
| 7 | 12.1.1Design, drawing, fabrication, supply, erection, testing and commissioning of Embedded parts consisting of sill beams, vertical tracks, vertical seal tracks, sealing frame, guide tracks/rails, wall plates, seal seats, anchors, anchor girders, yoke girders, tie flats, trunnion supports, rope and pulley supports etc. and any required necessary item, with all accessories as per relevant IS code, for all type radial gates/ Vertical lift fix wheel type sluice and Canal gates/Stop log gates including cost of all materials, machinery, labour, cutting, aligning, anchoring, welding, finishing, cleaning, tools and tackles, applying two coat of zinc rich epoxy primer to give dry film thickness of 70 plus/ minus 5 microns and finish coat (two coats) of solvent less coal tar epoxy paint using airless spray to provide dry film thickness of 150 plus/ minus 5 microns per coat thus total dry film thickness of all coats, including primer coating, should not be less than 350 microns. including packing & forwarding, transportation charges complete item, as per specifications and approved drawings. |
| 8 | 12.37Oiling and greasing of Crest radial gates,Vertical Gates and Intake Service well Gates of Dam including all charges of man and material complete, which include cleaning of wire rope with petrol / diesel and applying Cardium compound to wire ropes, oiling & greasing etc complete as per direction of Engineer-in-Charge. |
| 9 | 5.1.2Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m including dressing of excavated area and dewatering wherever required complete in all respect (b)Hard / dense soil |
| 10 | 9.8.49.8 Providing and Laying in position of Cement concrete Nominal mix (1:3:6) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 9.8.4 20 mm |
| 11 | 9.2.49.2 Providing and Laying in position of Cement concrete Design mix M-20 including leads of all construction materials, plasticizers (if required), curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto; (For mix design Cement content considered 400 kg/ cum of concrete) 9.2.4 20 mm |
| 12 | 10.1.110.1 Side shuttering including propping etc. complete (to achieve finish F 2 for 10.1.1 Block joints of foundation stilling basins buckets, aprons etc. (non -suspended horizontally laid mass concrete) |
| 13 | 9.7.49.7 Providing and Laying in position of Cement concrete Nominal mix (1:2:4) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 9.7.4 20 mm |
| 14 | 7.1.47.8.1Random rubble stone masonry (using R. R. stones where 75 % stones to be not less than 15 cm in size in any direction and weighing not less than 23 kg.) for foundation including curing with all leads of all construction materials including curing etc. complete. (d) In cement sand mortar 1:6 Add extra over item no. 7.1.1 to 7.7.3 for (a) Masonry work in superstructure |
| 15 | 7.1.4Random rubble stone masonry (using R. R. stones where 75 % stones to be not less than 15 cm in size in any direction and weighing not less than 23 kg.) for foundation including curing with all leads of all construction materials including curing etc. complete. (d) In cement sand mortar 1:6 |
| 16 | 8.2.1 Plaster in cement sand mortar 1:4 including racking of joints, smooth finishing & curing etc. complete including all leads of all construction materials of thickness: (a) 20 mm Please Enable Macros to View BoQ information |