| 1 | Carriage of fallowings from ESC. Modinagar/Ghaziabad to pit site on kachcha pacaa road including loading and unloading chagres at both ends, rcquricd for proper completion of work, distance about to 60Kms. |
| 2 | S.T Pole 13 Mtr long. |
| 3 | P.C.C Pole 11 Mtr long. |
| 4 | S.T Pole 11 Mtr long. |
| 5 | P.C.C POLE 8.5 Mtr long. |
| 6 | Carriage of All Centerlized/De-Centralized Material from store Center Gzb to Pit site as ACSR Weasel conductor, ABC conductor GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator XLPE Cable etc. |
| 7 | Erection of Single Pole support including complete fittings as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work. |
| 8 | S.T Pole 13 Mtr long. |
| 9 | P.C.C Pole 11 Mtr long. |
| 10 | S.T Pole 11 Mtr long. |
| 11 | P.C.C POLE 8.5 Mtr long. |
| 12 | Erection of duble pole/Saction Pole support including complete Lt fittings as per RESPO mannual and as per direction in charge including the cost of Labour, T&P and carrier etc. required for proper completion of work. |
| 13 | S.T Pole 13 Mtr long. |
| 14 | P.C.C Pole 11 Mtr long. |
| 15 | S.T Pole 11 Mtr long. |
| 16 | P.C.C POLE 8.5 Mtr long. |
| 17 | Grouting of Single Pole shall be grouted with cement, sand and birck ballast/stone ballast in ratio 1:4:8 =30x3030 cms. including the cost of cement, sand, birck ballast/stone ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work. |
| 18 | S.T Pole 13 Mtr long. |
| 19 | P.C.C Pole 11 Mtr long. |
| 20 | S.T Pole 11 Mtr long. |
| 21 | P.C.C POLE 8.5 Mtr long. |
| 22 | Grouting of Double Pole shall be grouted with cement, sand and birck ballast/stone ballast in ratio 1:4:8 =30x3030 cms. including the cost of cement, sand, birck ballast/stone ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work. |
| 23 | S.T Pole 13 Mtr long. |
| 24 | P.C.C Pole 11 Mtr long. |
| 25 | S.T Pole 11 Mtr long. |
| 26 | P.C.C POLE 8.5 Mtr long. |
| 27 | Re-Installution of distribution Transformer with carriage kachha pacaa road including loding and unloading charges of both ends, required for proper completion of work distance about to 60 Kms. |
| 28 | 25/63 KVA T.F |
| 29 | 100/160 KVA T.F |
| 30 | 250 KVA T.F |
| 31 | 400/630 KVA T.F |
| 32 | 750/1000 KVA T.F |
| 33 | Laying, sagging. Stringing and binding and jumpering of ACSR 11 K.V XLPE cable, LT ABC Cable etc.newly erected pole as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc. requried for proper completion of work. |
| 34 | ACSR Weasal Conductor |
| 35 | ACSR Rabbit / Dog Conductor |
| 36 | 11 K.V XLPE Cable of various Size |
| 37 | LT ABC Cable of Various Size |
| 38 | Resagging of loose and bad sag of L.T./H.T. line/ACSR Weasel/Rabbit/Dog Conductor |
| 39 | Resagging of loose and bad sag of XLPE Cable Various size |
| 40 | Resagging of loose and bad sag of ABC Cable Various size |
| 41 | Fixing of 11 K.V Stay rod with Stay wire in proper way with Nozelling. |
| 42 | Grouting of Stay rods . |
| 43 | Chopping of Tree branches.. |
| 44 | Tightening of Stay |
| 45 | Grouting of PCC/STP Pole Old |
| 46 | Change of broken/Damaged/Missing following Items :- |
| 47 | Pin Insulator |
| 48 | Disc Insulator |
| 49 | Bended X-Arm/Angle/Channel |
| 50 | T-off Channel |
| 51 | LT Clamp with insulator, nut and bolt. |
| 52 | Site Bracket with fabrication and supply of MS angle and Channel as per site requirement. |
| 53 | Ailment of PCC/STP Pole |
| 54 | F Clamps |
| 55 | Stay Clamps |
| 56 | Stay Insulator |
| 57 | Re-Installution of guarding of GI Wire. |
| 58 | Welding of the Damaged/Broken ST Pole welded Angle Oron piece with Pole |
| 59 | Dismantling of ST/PCc Poles. |
| 60 | Removal of ST/PCc Poles. |
| 61 | Dismantling of 25/63/100KVA Insulator from damaged double pole. |
| 62 | Removal of accessories on double pole PCC/ST Pole. |
| 63 | Fixing of all old/new accessories on new Double pole PCC/STP. |
| 64 | Mounting of 25/63/100 KVA Transfoner or double pole. |
| 65 | Filling/Making of 11 K.V Cable J/Kit of various Size. |
| 66 | The following material is required to be supplied by the contractor. |
| 67 | Providing & Fixing Stay clamp. |
| 68 | Providing & Fixing Stay insulator. |
| 69 | Providing & Fixing of barbe Wire |
| 70 | Providing 11 K.V Cable jointing Kit of various size. |
| 71 | PRC/Dead End/Suspension Clamp/J-Hook |
| 72 | Providing & fizing of F Bracket |
| 73 | LT Clamp with Insulator, Nut & Bolt |
| 74 | Providing & Fizing of X Arm Holding Clamp |
| 75 | Bolt & nut off size. Please Enable Macros to View BoQ information |