| 1 | Earth work in hard soil withen 50m. initial lead and 1.5m. Initial lift including rough dressing and breaking the clods to maximum 5cm. To 7cm. Laying the layers not exceeding 0.30m. In depth etc complete. |
| 2 | Providing and filling clean dry sand of approved quality from approved quarry in foundation and plinth in 6\\" thick layer well watered and rammed incl. cost,conveyance, royalties and taxes of all materials etc. |
| 3 | C.C.(1:3:6) using 40mm HG metal of approved quality from approved quarry incl. hoisting, compacting curing,finishing the exposed surface smooth, dewatering, shoring, shuttering if necessary at the time of laying |
| 4 | Filling in foundation and plinth with excavated materials including water and ramming as directed by the Engineer-in -charge. |
| 5 | Flyash brick masonry using Flyash bricks of size 25 cm. x 12 cm. x 8 cm. having crushing strength not less than 75 kg. Per Sqr. Cm. in cement mortar of mix (1:6) with screened & washed sand for mortar after immersing the bricks for 6 (Six) hours in water before use in F & P including splays cutting, circular moulding, corbelling, chamfering and similar such type of works, watering and curing etc. including cost, conveyance, loading, unloading, royalties and taxes of all materials, cost of all labour, scaffolding, sundries, T&P required for the works etc.complete in all respect as per the specification & direction of the Engineer-in-Charge. |
| 6 | Flyash brick masonry using Flyash bricks of size 25 cm. x 12 cm. x 8 cm. having crushing strength not less than 75 kg. Per Sqr. Cm. in cement mortar of mix (1:6) with screened & washed sand for mortar after immersing the bricks for 6 (Six) hours in water before use in Super structure including splays cutting, circular moulding, corbelling, chamfering and similar such type of works, watering and curing etc. including cost, conveyance, loading, unloading, royalties and taxes of all materials, cost of all labour, scaffolding, sundries, T&P required for the works etc. complete in all respect as per the specification & direction of the Engineer-in-Charge.. Ground Floor |
| 7 | First Floor |
| 8 | R.C.C. work of M - 20 having minimum compressive strength (in work test) 200kg./cm2 in 15cm cubes at 28 days after mixing and test conducted in accordance with I.S. 456 and I.S. 516 using 12mm to 20mm size (1/2” to 3/4”) crusher broken hard black granite chips of 20mm size (not to exceed 25%) of approved quality & from approved quarry including hoisting, lowering, laying and compacting concrete with vibrator, watering and curing for 28 days, cost of rigid and smooth centering & shuttering and finishing to exposed surface smooth providing, grooves or beads wherever necessary as per direction of the Engineer-in-charge including cost, conveyance, royalties & taxes of all materials and cost of all labour, T&P etc. as required for the work complete in all respects as per direction of Engineer-in-charge but excluding cost of M.S. rod/Tor steel and binding wires and labour charges for bending, binding and tying the grills etc complete as drawing design and direction of Engineer-in-charge. a) Column base |
| 9 | b) Column & Roof Beam |
| 10 | c) Plinth Bend |
| 11 | d) Lintel |
| 12 | e) Chajja |
| 13 | f) Roof slab |
| 14 | First Floor a) Lintel |
| 15 | b) Column & Roof Beam |
| 16 | c) Roof slab |
| 17 | d) Chajja |
| 18 | e)Stairs |
| 19 | Providing, Cutting, straightening coiled or bent up Fe-500 grade steel (SAIL make) welding or jointing if necessary, bending, binding, tying the grills as required for RCC works, and hoisting, lowering and placing in proper position according to approved designs and drawings including cost, conveyance, loading, unloading, taxes of M.S. rods, Fe-500 or equivalent and binding wires of 18 to 20 gauge required for the work and cost of all labour, sundries, T&P and scaffolding complete in all respect as directed by the Engineer-in-Charge (payment will be made according to the actual weight of M.S. rod, Fe-500 or equivalent consumed in the work and no separate payment will be made towards weight of binding wires which is to be borne by the contractor at his own cost) as per the direction of Engineer-in-charge. Ground Floor |
| 20 | First Floor |
| 21 | 25mm thick grading plaster in cm (1:4) over roof slab including watering & curing with cost & conveyance of all materials & labour with T & P required for the work with all taxes, royalties etc. complete in all respect as per the specification & direction of the Engineer-in-Charge.. First Floor |
| 22 | 12 mm thick C.P in cement mortor (1:6) finished to smooth over brick walls after racking out the joints including watering & curing with cost & conveyance of all materials & labour with T & P required for the work with all taxes, royalties etc. complete in all respect as per the specification & direction of the Engineer-in-Charge. GFloor |
| 23 | First Floor |
| 24 | 16 mm thick cement plaster in cm (1:6) over brick masonary finished smooth after racking out joints to 12 mm deep including watering for curing with cost & with cost & conveyance of all materials & labour with T & P required for the work with all taxes, royalties etc. complete in all respect as per the specification & direction of the Engineer-in-Charge.. Ground Floor |
| 25 | First Floor |
| 26 | 6 mm thick C.P in cement mortor (1:4) including close deep cheeping to the ceiling of the roof including watering & curing with cost & conveyance of all materials & labour with T & P required for the work with all taxes, royalties etc. complete in all respect as per the specification & direction of the Engineer-in-Charge.. Gfloor |
| 27 | First Floor |
| 28 | Supply fitting and fixing vitrified floor tiles in floor 600mmx600mm printed/coloured series trade on steps and landing on 20mm thick bed of cement motar (1:4) joint with neat cement slury mixed with pigment to watched and shade of the tile including rubbing and policing etc complete in all respect as per the specification & direction of the Engineer-in-Charge.. Ground Floor |
| 29 | First Floor |
| 30 | Providing and fixing Vetrified tiles in dados, skirtings and risers of steps on 12 mm thick cement plaster (1:3) jointed with neat cement slury mixed with pigment to match the shades of the tiles complete including cost of tiles, labour, royalty etc complete in all respect as per the specification & direction of the Engineer-in-Charge.. Ground Floor |
| 31 | First Floor |
| 32 | Finishing wall with one coat primer water based of approved make and finished smooth and even surfaceto receiving painting including all labour, T & P, cost of paints complete in all respect as per the specification & direction of the Engineer-in-Charge.. Ground Floor |
| 33 | First Floor |
| 34 | Distempering 2coats with distemper of approved shade on new work to give an even shade with cost of all materials taxs labour t&p etc complete in all respect as per the specification & direction of the Engineer-in-Charge.. Ground Floor |
| 35 | First Floor |
| 36 | Finishing wall with water proofing weather coat paint of approved shade two coats to give an even shade including cost of paints, labour, conveyance etc complete in all respect as per the specification & direction of the Engineer-in-Charge.. Ground Floor |
| 37 | First Floor |
| 38 | Supplying fitting fixing of stainless steel of304 grade in hand railing using 50mmdia 2mmthick circular pipe with Balustrade of size 32mmx32mmx2mm @0.90mtr c/c & stainless steel square pipe bracing of size 32mmx32mmx2mm in 3 rows in staircase as per approved design & specification,buffing,polishing etc with cost, conveyance,taxes of materials,labour,t&p reqd.etc. complete complete in all respect as per the specification & direction of the Engineer-in-Charge.. Ground Floor |
| 39 | Supplying of M.S.Doors, M.S. Gate etc including cost, conveyance of all materials etc.complete as per the instruction of Engineer-in-Charge . |
| 40 | Painting two coats with Enamel paint to doors and windows over a coat of primer incl. cost of all material,T&P and labour etc complete. ( for Iron work ) |
| 41 | First Floor Please Enable Macros to View BoQ information |