| 1 | Earth work in hard soil withen 50m. initial lead and 1.5m. Initial lift including rough dressing and breaking the clods to maximum 5cm. To 7cm. Laying the layers not exceeding 0.30m. In depth etc complete. |
| 2 | Sand filling in foundation with well watered & rammed with all cost of carriage & royality etc. comlete. |
| 3 | C.C.(1:3:6) using 40mm HG metal of approved quality from approved quarry incl. hoisting, compacting curing,finishing the exposed surface smooth, dewatering, shoring, shuttering if necessary at the time of laying concrete with cost, conveyance, royalty & taxes of all materials,cost of labour and T&p etc. all complete as per the direction of E.I.C. |
| 4 | Fly ash brick masonry in CM (1:6) for f&p including necessary scaffolding ,raking out joints, curring etc complete as per specfication and direction of the engineer in-charge |
| 5 | Fly ash brick masonry in CM (1:6) for super structure including necessary scaffolding ,raking out joints, curring etc complete as per specfication and direction of the engineer in-charge |
| 6 | R.C.C. work of M - 20 grade with 20 mm and down grade HGCB chips incl. hoisting, laying concrete in layers not exc. 15cm thick, (Column Bases & Pedestal) |
| 7 | Plinth Bend |
| 8 | For beam and column |
| 9 | Lintel |
| 10 | Chajja |
| 11 | Roof Slab |
| 12 | Cutting, straightening, coiled or bent up T. S. rod for R.C.C. work incl. bending, binding & tying the grills and placing in proper position with cost, conveyance,taxes of binding wire 18 to 20 gauge and T.S. rod, cost of all labour & T&P etc complete as per the direction of E.I.C. |
| 13 | 16 MM THICK CP(1:6) over brick masonary work incuding necessary scaffolding,currng ctc complete (inside) |
| 14 | 12 MM THICK CP(1:6) over brick masonary work incuding necessary scaffolding,currng ctc complete |
| 15 | 6 mm Thick Plaster on RCC work |
| 16 | Fixing tile (vitrified ) on floor 20mm thick bed in cm(1:4) jointed with neat cement slury mixed ith pigment to match the shades |
| 17 | Fixing tile (vitrified ) in wall in 12mm thick bed in cm(1:3) jointed with neat cement slury mixed ith pigment to match the shades |
| 18 | Supplying, fitting and fixing steel Angle iron door and windows as per approved design and drawing including all cost of materials and labour etc complete as per direction of Engineer in charge. |
| 19 | 20mm thick grading plaster (1:4),finished smooth over roof slab after cleaning the surface incl.watering, curing etc. complete with cost, conveyance, royalties & taxes of all materials, labour and T&P etc complete |
| 20 | Finishing surface of walls with cement based wall putty (water bsed) of appoved make and finished smooth and even surface to receive painting including cost of all materials taxes labour t&p |
| 21 | Two coats water bound primer with approved shade over cement plaster incl. cost of all material, labour and T&P etc. complete. |
| 22 | Painting two coats with plastic emulsion paint over a coat of water bond cement primer to make an even finished surface in all floors and heights to wall surface of approved make and shade including sand papering, applying putty wherever necessary & cost of scaffolding, staging charges with cost, conveyance, taxes of all materials, cost of all labour, T&P etc. complete as per the direction of the Engineer-in-charge. |
| 23 | Painting two coats with approved paint to doors and windows over a coat of primer incl. cost of all material,T&P and labour etc complete. ( for Iron work ) |
| 24 | Weather coat painting two coats with approved shade over a coat of oil bound primer incl. cost of all material,T&P and labour etc complete. Please Enable Macros to View BoQ information |