| 1 | Removing the Existing AC Sheet Roofing including cost and conveyance of all materials to site and all labour charges etc complete |
| 2 | Roofing with PUF Sheet Roofing L angle 65mmx65mmx 6mm including cost and conveyance of all materials to site and all labour charges etc complete |
| 3 | Roofing with PUF Sheet Roofing Using PUF Panels 50mm thick Either as Single piece thick including cost and conveyance of all materials to site and all labour charges etc complete |
| 4 | Distembering two coats with best approved distember including cost and conveyance of all materials to site and all labour charges etc complete |
| 5 | Exterior Emulsion painting two coats with best approved quality and colour paint over one coat of Base coat including cost and convyance of all materials to work site and labour charges etc., complete. |
| 6 | Painting two coats over Old iron work such as doors, windows, ventilators, windows bars, balustrades etc., with best approved best quality of synthetic enamal paint of approved colour over the existing priming coat etc., complete. |
| 7 | Wiring with 2x1.5 sq.mm PVC Cinsulated Scuns heated FRL Scopper conductor of 1100 V gradeinsuitable PVC rid pipe on wall and celling wit PVC accessories and with TW switch b x and 5h PVC accessories and with TW switch bx and 5 AFT switch with apinting of suitable colour for open PVC light point / fan point (for electronic regulator) (5 points per cell) SD 18 |
| 8 | Supply and fixing 1400 mm (56\\") sweep AC celling fan complete with steppedelectronicregulatorwith 300 mm diwbrid ib the existing clamp SD 110 |
| 9 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B |
| 10 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum. |
| 11 | Cement concrete 1:3:6 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks for 10 cum |
| 12 | Supply and errecting centring including all cost and conveyence and all labour charges for sides.etc compl |
| 13 | Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) . |
| 14 | Paving the flooring with specified type of paver block 60mm thick including laying,compacting with power temper,aligning with approved color and design etc compl Please Enable Macros to View BoQ information |