| 1 | Dismantling of old brick laid flat /cc interlocking tiles |
| 2 | Dismentling existing plaster including disposal of refuse as directed by the engineer in charge within a distance of 60 mtr |
| 3 | Dismentling corrugated iron roof walls or partition i/c purlins battens and verticle support and i/c stacking of material as directed by the Engineer in charge within a distance of 60 mtr |
| 4 | Dismentalling cement concrete or brick or granolithic floor including staking of matrial as direct by the engineer in charge within a distance of 60 meter (200 feet) |
| 5 | Disposal of malba |
| 6 | Earth work in excavation |
| 7 | Concrete with 4 cm. gauge Brick Ballast fine sand of 1.25 F.M. and cement in proportion of 12:6:1 in foundation and under floors, including supply of all materials, labour. T & P etc. Required for proper completion the work. |
| 8 | M-150 brick work in 1:4 one cement and four course sand . mortar in foundation and plinth including supply of all materials labour, T & P etc required for proper complition of the work |
| 9 | 12 mm thick plaster with1:4 Cement and four course sand including supply all material and labour, T & P required for proper completion of work |
| 10 | Cement Concrete with 4.0 cm. gauge Approved stone ballast coarse sand & cement in the proportion of 8:4:1 including , supply of all material T&P etc. |
| 11 | Cement Concrete with 2.0 cm. gaug;e Approved stone grid coarse sand & cement in the proportion of 4:2:1 including , T&P etc. |
| 12 | Supply and stacking of hard stone 22.4 -53 mm gauge stone ballast i/c All comp work |
| 13 | Consolidation of hard stone ballast by hand rammer including opening out stacks sorting hard stone ballast into three sizes, repairing patches in existing road suface with hard stone ballast making medhi to retain water and ramming and also including carriage of metal upto 30 meters (100 ft.) carriage of water 200 metre supply and maintenance of barriers and all tools and plants required for proper completion of work, hard stone ballast to be supplied to the contractor free at site.but 12cm (loose) thick coat of stone ballast excluding roller charges +all comp. work |
| 14 | Supplying & fixing 80 mm thick Precast colour cement concrete I shape inter locking paver block ISI mark confirming to IS 15658-2006 with top layer of minimum 5 mm thickness having plan dimention 200x( 160+120mm) of op cement , smooth high gloss finish, skid resistant,manufactured from rubur moulds through vibro -compression mechanism. The compressive strength of concrete pavar block shall not be less than 40MPa and weight 4.5 kg per no. including cost of meterial, with blanket layer of 4.00cm thick fine sand including labour T& P etc required for proper completion of the work as directed by Engineer-in-charge. colour tile |
| 15 | S/FIXING 6 to 8 mm thick ivory or light shades vitrified tiles 600*600 mm size in flooring and skirting with 1:3 approved cement and coarse sand mortar finished with in its cement colour slurry,jointing and polished of approved qwality complete,including supply of all material labour tools and plants etc.required for proper completion of the work as per direction of engineer in charge. |
| 16 | Supply and fixing 6 mm thick china white glazes tiles in flooring or in skirting or dado laid with 1:3 approved cement and coarse sand mortar finished with white cement slurry, jointing and polished of approved quality complete, including supply of all materials, labour, tools and plants etc. required for proper completion of the work as per direction of engineer-in- charge. |
| 17 | Steel work welded in built up section/framed work i/c cutting,hoisting,fixing in position and applying a priming coat of approved steel primer using structural steel steel etc as required in gratings,frames,guard bar,ladder,railings,bracket,gates,and similar work |
| 18 | supply and fixing galvanised coougated iron roofing 24 B.W.G in position incuding supply of materiel,labur tools & plants etc incuding wastage |
| 19 | Providing wall putty on new surface with approved qwality |
| 20 | paniting roofs or other iron work in large areas with one coat priming and one coat of approved (above one Sq Metre) paint (British antesol or equivalent) including supply of all materials labour Tools & plants etc required for proper completion of the work paint to be used ISI Marked. |
| 21 | Finishing wall with weather coat paint of approved make and quality on new work with two coat to give an even shade i/c supply of all material,labour,t and p etc required for proper completion of the work |
| 22 | RCC 1:1.5:3 in cement coarse sand and grit 2 cm. gauge. |
| 23 | Mild steel or iron such as in plane reinforcement concrete. |
| 24 | Deduction for old interlocking tiles all comp of work |
| 25 | Supply/ fixing of black granite stone sign board with cutting of given maters as per direction of engineer in charge in all complete Please Enable Macros to View BoQ information |