| 1 | Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. All kinds of soil. |
| 2 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. (All kinds of soil) |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50 m and lift upto 1.5 m. |
| 4 | Banking excavated earth in layers not exceeding 20cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller, or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and lift upto 1.5 m in All kinds of soil: |
| 5 | Deduct for not rolling with power roller of minimum 8 tonnes for banking excavated Earth in layers not exceeding 20 cm in depth. |
| 6 | Deduct for not watering the excavated earth for banking. |
| 7 | Excavating, supplying and filling of local earth (including royalty)by mechanical transport upto a lead of 5 km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. |
| 8 | Extra for levelling & neatly dressing of disposed soil completely as directed by Engineer-in-charge. |
| 9 | Removal of unhygienic materials (so classified by the site engineer) from designated sites and its disposal as per directions, all inclusive. |
| 10 | Pumping out water caused by springs, tidal or river seepage, broken water mains or drains and the like. |
| 11 | Extra for every additional lift of 1.5 m or part thereof in excavation/banking excavated or stacked material :(All kinds of soil) |
| 12 | Providing and laying in position cement concrete of specified grade including curing, but excluding the cost of centering and shuttering. All work up to plinth level with: |
| 13 | 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 14 | 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 15 | 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) |
| 16 | Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level |
| 17 | 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 18 | 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 19 | Centering and shuttering including strutting, propping etc. and removal of form for: |
| 20 | Foundations, footings, bases of columns etc. for mass concrete. |
| 21 | Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc. |
| 22 | Suspended floors, roofs, landings, balconies and access platforms. / Shelves (cast-in-situ) |
| 23 | Lintel, beams, plinth beams, girders, bressumers and cantilevers. |
| 24 | Columns, pillars, piers, abutments, posts and struts. |
| 25 | Edges of slabs and breaks in floors and wallsa) Under 20 cm wide |
| 26 | b) Above 20 cm wide |
| 27 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level |
| 28 | Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 29 | Mild steel and medium tensile steel bars |
| 30 | Brick work with common burnt clay (non-modular) bricks of class designation 7.5 in foundation and plinth including curing in : |
| 31 | Cement mortar 1:4 ( 1 cement : 4 coarse sand) |
| 32 | Cement mortar 1:6 ( 1 cement : 6 coarse sand) |
| 33 | Extra for brick work with common burnt clay bricks/cement concrete bricks in superstructure above plinth level upto floor five level |
| 34 | RANDOM RUBBLE MASONRY : Random Rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 Cement : 6 coarse sand : 12 graded stone aggregate 20mm nominal size) upto plinth level and curing complete with: a. Cement mortar 1:6 (1 Cement : 6 coarse sand) |
| 35 | Quarry |
| 36 | Nallah |
| 37 | Dry random rubble masonry with hard stone in foundation and plinth: |
| 38 | With bond stone. |
| 39 | Quarry |
| 40 | Nallah |
| 41 | Without bond stone |
| 42 | Nallah |
| 43 | Frames and trusses ; Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in position with hold fast lugs or with dash fasteners of required dia and length (hold fast lugs or with dash fasteners shall be paid for separately) |
| 44 | Second class kail wood |
| 45 | KD imported |
| 46 | Poplar Wood |
| 47 | Providing wood work in frames of false ceiling, partitions etc. sawn and fixed in position or in flumes: |
| 48 | Budloo / Fir wood |
| 49 | Poplar Wood |
| 50 | Providing/Fixing/Fabrication of Sign Board of M.S sheet size (3’x2’) of 2mm thickness to be fixed on angle iron frame of angle size 40x40x5mm thick of height 5’ above ground,fixed in plain cement concrete of mix 1:2:4 including painting, lettering/printing, All complete to the entire satisfaction of the Engineer in Charge. |
| 51 | Capturing and printing HD photographs (of size 4”x6”) on good quality standard photo paper |
| 52 | Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
| 53 | Structural steel work in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
| 54 | Riveted and bolted |
| 55 | Welded |
| 56 | Cement concrete flooring 1:2:4 (1cement: 2 coarse sand: 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry and curing complete, but excluding the cost of nosing of steps etc. Complete. |
| 57 | 25mm thick with 12.5 mm nominal size stone aggregate. |
| 58 | 40mm thick with 20 mm nominal size stone aggregate. |
| 59 | 50 mm thick with 20mm nominal size stone aggregate. |
| 60 | C.G.I. SHEETS ROOFING ; Providing corrugated G. S. Sheet roofing including vertical/curved surface fixed with polymer coated J or L hooks, bolts and nuts 8mm diameter with bitumen and G.I limpet washers or with G.I. limpet washers filled with white lead, including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (upto any pitch in horizontal/vertical or curved surface)excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. |
| 61 | 0.63 mm thick with zinc coating not less than 275 gram/m2 |
| 62 | 0.50 mm thick with zinc coating not less than 275 gram/m2 |
| 63 | Providing ridges or hips of width 60cm overall width plain G.S. sheets fixed with polymer coated J. Or L hooks, bolts and nuts 8mm dia G.I. limpet and bitumen washers complete. |
| 64 | 0.63 mm thick with zinc coating not less than 275 gram/m2 |
| 65 | 0.50 mm thick with zinc coating not less than 275 gram/m2 |
| 66 | CEMENT PLASTER; (IN FINE SAND) : 12mm Cement plaster of mix: |
| 67 | 1 : 4 ( 1 cement : 4 fine sand) |
| 68 | 1 : 6 ( 1 cement : 6 fine sand) |
| 69 | Demolishing cement concrete manually/by mechanical means including disposal of material within 50 meters lead as per direction of Engineer-in charge: |
| 70 | 1:3:6 or richer mix (i/c equivalent design mix) |
| 71 | 1:4:8 or leaner mix (i/c equivalent design mix) |
| 72 | Demolishing R.C.C. work manually/by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 meters lead as per direction of Engineer-in-charge. |
| 73 | Demolishing stone rubble masonry manually/by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 meters lead as per direction of Engineer-in-charge: In cement mortar |
| 74 | Demolishing brick work manually/by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 meters lead as per direction of Engineer-in-charge: In cement mortar |
| 75 | Dismantling old protection work including cutting of crates and stacking of stones |
| 76 | Dismantling barbed wire or flexible wire rope in fencing including making rolls and stacking within 50 meters lead. |
| 77 | Dismantling old plaster or skirting, raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 meters lead. |
| 78 | Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints etc. Complete. |
| 79 | 150 mm dia. R.C.C. pipe-(6”) |
| 80 | 250 mm dia. R.C.C. pipe-(9”) |
| 81 | 300 mm dia. R.C.C. pipe-(12”) |
| 82 | 450 mm dia. R.C.C. pipe-(18”) |
| 83 | 600 mm dia. R.C.C. pipe-(24”) |
| 84 | 900 mm dia. R.C.C. pipe-(36”) |
| 85 | 1000 mm dia. R.C.C. pipe-(40”) |
| 86 | Constructing muthu bunds, comprising boulders and wood bushes in alternate layers; including working in water situations. |
| 87 | Dry stone pitching (any thickness) excluding cost of stones. |
| 88 | On Horizontal |
| 89 | On Top copings of banks |
| 90 | On Slopes |
| 91 | Hand-packing stones in wire-crates; excluding cost of crates and stones |
| 92 | Dumping stone excluding cost of stones. |
| 93 | in Horizontal on level |
| 94 | on Slopes (Behind pitching) |
| 95 | Grouting of stone pitching using M-10 nominal mix concrete (max. Size of aggregates; 20mm nominal) @ 3.65 cum per 100Sqm on horizontal/side slopes; complete including curing. |
| 96 | Opening out old wire crates those and re-binding after filling. |
| 97 | Supply of Stone boulder (nallah) nominal size 225 mm incl. royalty and/or other taxes. (Stack measurements reduced by 15%) |
| 98 | Supply of Stone boulder (quarry) nominal size 225 mm incl. royalty and/or other taxes. (Stack measurements reduced by 15%) |
| 99 | Supply of Stone for masonry work (quarry) incl. royalty and/or other taxes. |
| 100 | Filling empty cement bags with sand/ earth; including cost of sewing and strings; excluding cost of bags and earth / sand. |
| 101 | Unloading sand/earth filled bags from boats |
| 102 | Placing in dry |
| 103 | Placing in Water |
| 104 | Silt clearance from canals. Inclusive of initial lead and lift ( 50m & 1.5m respectively ) |
| 105 | Silt clearance from canals by mechanical means (hydraulic Excavator) Inclusive of initial lead and lift ( 50m & 1.5m respectively ) |
| 106 | Weed clearence |
| 107 | From lakes(using boats) |
| 108 | From canals(including extraction of roots) |
| 109 | Slip Clearance |
| 110 | In ordinary soils disposal lead upto 50 m and lift upto 1.5 m. |
| 111 | Engagement of Labour / Bullock man with single bullock /Chowkidar/Belder/ Coolie/ Mali/sewer man / Helper {unskilled labour} |
| 112 | Engagement of Skilled labour(1st Class) like Mason, Technician, fitter, Blacksmith etc. |
| 113 | Engagement of Skilled labour (2nd Class) like Mason, Painter, Carpenter. |
| 114 | Boatman |
| 115 | Engagement of Boat(Capacity up to 20cum) |
| 116 | Petrol for running of departmental chain saw (wood cutter) inclusive of required admixtures |
| 117 | Hire charges of Pump set of capacity 4000 litres/hour |
| 118 | Vibrator (Needle type 40 mm) |
| 119 | Hire charges for engagement of Chain saw (mechanical wood cutter) incl. Operator, fuel, maintenance, carriage, complete job. |
| 120 | Supplying and stacking of good earth at site including royalty (earth measured in stacks will be reduced by 20% for payment) |
| 121 | Supply of sand |
| 122 | Supply of crusher dust |
| 123 | Supply of EC bags as and where required, incl. all sorts of Carriage, loading, unloading, and stacking etc. Complete job |
| 124 | Hire charges for engagement of mech. Excavator incl. Operator, fuel, maintenance & transportation of excavator to & fro from site to source, complete job ( Tyre type) |
| 125 | Hire charges for engagement of mech. Excavator incl. Operator, fuel, maintenance & transportation of excavator to & fro from site to source, complete job |
| 126 | (Poclain type) Normal Boom |
| 127 | Long Boom |
| 128 | Hire and running charges of light crane |
| 129 | Hire charges of vehicle (SUV Type) during day or night along with licensed commercial driver for site inspection/ emergency situation/ movement of officials indluding all sorts of taxes, parking charges, etc and POL on need basis only. |
| 130 | Upto 30Km Journey |
| 131 | For every km after 30 km |
| 132 | Hire charges of vehicle (Load Carrier) during day or night along with licensed commercial driver for carriage of materials indluding all sorts of taxes, parking charges, loading/unloading/stacking etc and POL on need basis only. |
| 133 | Upto 30Km Journey |
| 134 | For every km after 30 km |
| 135 | Disassembling and reassembling of chain saw wood cutter and making necessary repairs including all accessories required for repair work with all sorts of carriages, complete. |
| 136 | Repairs to shutter by way of removing dents, kinks and setting of iron gate (complete job) |
| 137 | Lubricating, Greasing & oiling of winch machines after cleaning the machine including Disassembling, Realignment and reassembling of hydraulic gate (complete job) |
| 138 | Repairs of worm or gear or screw rod or winch rod incl. Carriage of item involved from site to factory and back to site including Disassembling, Realignment, Greasing and reassembling of hydraulic gate (complete job) |
| 139 | Providing and fixing check nut of required dia and specification.(complete job) |
| 140 | Providing and fixing of threaded winch/sluice rod of required dia and specification including all sorts of carriages. Complete job. |
| 141 | Repairs to side channels by way of removal of bends and kinks incl. Setting and fixing (complete job) |
| 142 | Providing & fixing of grease lids for winch machines (complete job) |
| 143 | Providing & fixing of coupling of required sizes (complete job) |
| 144 | Providing & fixing of rubber seal to Hydraulic gates/Sluices for checking of leakages of PVC quality with 25 x 0.5mm with plate,iron steps including nuts and bolts. (complete job) |
| 145 | Welding by electric plant wherein required incl. Transfer of welding machine/other equipment’s from plant to site and back. |
| 146 | Providing , Installation , commissioning of Single Winch machine complete set of standard quality of 3 tonne capacity with double threaded 50mm dia Winch rod, Gears , Pedestal Rain Cover ,Grease Lids, MS Sleeves, operating Handle with locking arrangement including greasing & oiling complete Job including all carriages & extra carriages upto site of work |
| 147 | Providing , Installation , commissioning of Double Winch machine complete set of standard quality of 5 tonne capacity with coupling rod , coupling set double threaded 50mm dia Winch rod, Gears , Pedestal Rain Cover ,Grease Lids, MS Sleeves, operating Handle with locking arrangement including greasing & oiling complete Job including all carriages & extra carriages upto site of work |
| 148 | Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunk and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material. |
| 149 | Beyond 30 cm girth upto and including 60 cm girth. |
| 150 | Beyond 60 cm girth upto and including 120 cm girth. |
| 151 | Providing/spreading and fixing of LDPE to check/stop the leakages of canals/khuls/minors including fixing/locking arrangements by any means through the entire length /breadth as per the requirement at site of work and desired by ENC complete in all respects |
| 152 | Surface dressing of the ground including removing vegetation and in-equalities, not exceeding 15 cm deep and disposal of rubbish, lead upto 50 m and lift upto 1.5 m in -All kinds of soil. |
| 153 | Providing & laying PVC (type – B) pipes with all the required accessories and carriages, complete job |
| 154 | 150 mm dia |
| 155 | 200 mm dia |
| 156 | 250 mm dia |
| 157 | Providing of 12mm thick marine plywood conforming to IS:710 with nails and screws etc, including all sorts of carriages upto the site of work as per the direction and to the entire satisfaction of the Engineer in Charge (Complete Job) |
| 158 | Providing and serving hygienic pack of Non - veg biryani including sealed mineral water using one litre bottle,tissue paper etc. |
| 159 | Providing and serving high quality hundred gram dry fruit packs in fresh bone china bowls at the site of service complete job |
| 160 | Providing and serving superior quality Kehwa/tea including P/S of superior quality biscuits/cakes etc at the site of service complete job |
| 161 | Providing and serving hygienic pack of veg lunch with one mineral water, tissue papers etc using/serving high quality bone china serving cups/saucers,plates, spoons , trays,etc including maintenance of hygiene at the site of service. Complete Job |
| 162 | Supply of Paper Rims containing 500 Pages, 75 GSM of Spectra/JK Copier at Divisional office including all sorts of carriages |
| 163 | A4 size |
| 164 | Legal size |
| 165 | File Cover |
| 166 | Supply of Cartridges of standard quality at divisional office incl. all sorts of carriages |
| 167 | HP Toner 110 A |
| 168 | Hp Toner 88 A |
| 169 | Toner(Ricoh model MP250ISP) |
| 170 | Refilling of Cartriges of standard quality at divisional office incl. all sorts of carriages |
| 171 | HP Tonner 110 A |
| 172 | Hp Tonner 88 A |
| 173 | Toner(Ricoh model MP250ISP) |
| 174 | Supply of B.A wire knitted crates of Mesh size 100mm x 100mm with Dia of wire 4mm of approved made and make including all sorts of carriage upto the actual site of work complete in all respects to the entire statisfication of Engineer Incharge. |
| 175 | Carriage of material from Source/divisional store up to dumping site of work, including loading, unloading and stacking etc. complete by Mechanical Transport |
| 176 | Cement & steel, G.I/C.I pipe avg. lead upto 01 Kms |
| 177 | Cement & steel, G.I/C.I pipe avg. lead upto 02 Kms |
| 178 | Cement & steel, G.I/C.I pipe avg. lead upto 03 Kms |
| 179 | Cement & steel, G.I/C.I pipe avg. lead upto 04 Kms |
| 180 | Cement & steel, G.I/C.I pipe avg. lead upto 05 Kms |
| 181 | Cement & steel, G.I/C.I pipe avg. lead beyond 5 Kmsupto 10 Kms (per Km) |
| 182 | Cement & steel, G.I/C.I pipe avg. lead beyond 10 Kmsupto 20 Kms (per Km) |
| 183 | Cement & steel, G.I/C.I pipe avg. lead beyond 20 Kms per additional Km |
| 184 | Sand &Agg. 20 mm avg. lead of upto 01 Kms |
| 185 | Sand &Agg. 20 mm avg. lead upto 02 Kms |
| 186 | Sand &Agg. 20 mm avg. lead upto 03 Kms |
| 187 | Sand &Agg. 20 mm avg. lead upto 04 Kms |
| 188 | Sand &Agg. 20 mm avg. lead upto 05 Kms |
| 189 | Sand &Agg. 20 mm avg. lead beyond 5 Kmsupto 10 Kms (per Km) |
| 190 | Sand &Agg. 20 mm avg. lead beyond 10 Kmsupto 20 Kms (per Km) |
| 191 | Sand &Agg. 20 mm avg. lead beyond 20 Kms per additional Km |
| 192 | 40 mm Agg. avg. lead of upto 01 Km |
| 193 | 40 mm Agg. avg. lead upto 2 Kms |
| 194 | 40 mm Agg. avg. lead upto 3 Kms |
| 195 | 40 mm Agg. avg. lead upto 4 Kms |
| 196 | 40 mm Agg. avg. lead upto 5 Kms |
| 197 | 40 mm Agg. avg. lead beyond 05 Kmsupto 10 Kms (per Km) |
| 198 | 40 mm Agg. avg. lead beyond 10 Kmsupto 20 Kms (per Km) |
| 199 | 40 mm Agg. avg. lead beyond 20 Kms per additional Km |
| 200 | Stone soiling avg. lead of upto 1 Km |
| 201 | Stone soiling avg. lead upto 2 Kms |
| 202 | Stone soiling avg. lead upto 3 Kms |
| 203 | Stone soiling avg. lead upto 4 Kms |
| 204 | Stone soiling avg. lead upto 5 Kms |
| 205 | Stone soiling avg. lead beyond 05 Kmsupto 10 Kms (per Km) |
| 206 | Stone soiling avg. lead beyond 10 Kmsupto 20 Kms (per Km) |
| 207 | Stone soiling avg. lead beyond 20 Kms per additional Km |
| 208 | Earth avg. lead of upto 1 Km |
| 209 | Earth avg. lead of upto 02 Km |
| 210 | Earth avg. lead of upto 03 Km |
| 211 | Earth avg. lead of upto 04 Km |
| 212 | Earth avg. lead of upto 05 Km |
| 213 | Earth avg. lead beyond 05 Kmsupto 10 Kms (per Km) |
| 214 | Earth avg. lead beyond 10Kmsupto20Kms (per Km) |
| 215 | Earth avg. lead beyond 20 Kms per additional Km |
| 216 | E.C bags avg. lead of upto 1 Km |
| 217 | E.C bags avg. lead of upto 02 Km |
| 218 | E.C bags avg. lead of upto 03 Km |
| 219 | E.C bags avg. lead of upto 04 Km |
| 220 | E.C bags avg. lead of upto 05 Km |
| 221 | E.C bags avg. lead beyond 05 Kms upto 10 Kms (per Km) |
| 222 | E.C bags avg. lead beyond 10Kms upto20Kms (per Km) |
| 223 | E.C bags avg. lead beyond 20 Kms per additional Km |
| 224 | Crates, avg. lead upto 01 Kms |
| 225 | Crates avg. lead upto 02 Kms |
| 226 | Crates, avg. lead upto 03 Kms |
| 227 | Crates, avg. lead upto 04 Kms |
| 228 | Crates, avg. lead upto 05 Kms |
| 229 | Crates, avg. lead beyond 5 Kms upto 10 Kms (per Km) |
| 230 | Crates, avg. lead beyond 10 Kms upto 20 Kms (per Km) |
| 231 | Crates, avg. lead beyond 20 Kms per additional Km |
| 232 | Carriage of material from dumping site to actual site of work, including loading, unloading and stacking etc. complete by manual labour |
| 233 | Cement for an avg. lead upto 50 mtr. |
| 234 | Cement for an every additional lead of 50 mtrs or part thereof beyond 1st 50 mtrs. |
| 235 | Steel for an average lead upto 50Mtr |
| 236 | Steel for an every additional lead of 50Mtrs or part thereof beyond 1st 50Mtrs |
| 237 | Stone Soling for an avg. lead upto 50 mtr. |
| 238 | Stone Soling for an every additional lead of 50 mtrs or part thereof beyond 1st 50 mtrs. |
| 239 | Sand & 20mm Agg for an average lead upto 50Mtr |
| 240 | Sand & 20mm Agg for an every additional lead of 50 mtrs or part thereof beyond 1st 50 mtrs. |
| 241 | 40mm Agg for an average lead upto 50Mtr |
| 242 | 40mm Agg for an every additional lead of 50 mtrs or part thereof beyond 1st 50 mtrs. |
| 243 | Earth for an average lead upto 50Mtr |
| 244 | Earth for an every additional lead of 50 mtrs or part thereof beyond 1st 50 mtrs. |
| 245 | Crates for an average lead upto 50Mtrs |
| 246 | Crates for an every additional lead of 50 mtrs or part thereof beyond 1st 50 mtrs. |
| 247 | Empty Cement bags for an average lead upto 50Mtrs |
| 248 | Empty Cement bags for an every additional lead of 50 mtrs or part thereof beyond 1st 50 mtrs. Please Enable Macros to View BoQ information |