| 1 | Filling foundation and plinth with sand including cost, conveyance & taxes etc. complete. |
| 2 | C.C. (1:3:6) using 4 cm size B.H.G. metal including all cost, conveyance, taxes, royalty watering curing etc. complete. |
| 3 | C.C. (1:2:4) 12 mm size chips with cost, conveyance and taxes etc. complete. |
| 4 | R.C.C. M20 (1:1.5:3) using 12 mm size chips with cost conveyance and taxes of all material etc. complete. |
| 5 | Fly ash Brick masonary in C.M. (1:6) in foundation and plinth with cost, conveyance and taxes etc. complete. |
| 6 | 12 mm thick cement plaster in c.m. (1:6) over brick walls with Cost, Conveyance and taxes etc. complete. |
| 7 | Supplying, fitting and placing uncoated HYSD bar reinforcement complete as per drawing and technical specification. |
| 8 | Finishing walls with water proofing Weather coat paint of approved shade on old work two coats to give an even shade including cost of all materials etc. complete. |
| 9 | Dismantling brick or stone masonary in lime or cement mortar above 3m. Height including stacking the useful materials for reuse and removing the debris within 50 mt. Lead. |
| 10 | Supplying fitting, fixing ,vetrified tiles in floors of size 600mm x 600 mm of approved make with 25mm thick bed of cement mortar (1:1) jointed with neat cement slury mixed with pigment to match the shades of the tiles including rubbing and polishing complete including cost of all materials,Labour T&P etc required for the work . |
| 11 | Supplying and Fixing of M.S. Grills, M.S. DOORS,M.S. Gateetc including cost, conveyance of all materials, priming, and labour for fitting fixing etc.complete as per the instruction of Engineer-in-Charge |
| 12 | Fixing Ceramic Tiles in floors trades or steps and landing on 25 mm thick bed of Cement motar 1:1 Jointed with neat cement slury moxed with pigment to match the shades of the tiles including rubbing and polishing including cost of all meterials etc. complete. |
| 13 | Labour for fitting, fixing M.S door and windows including angle, choukaths in double leaves. |
| 14 | Painting two coats over a cost of primer on new wood/iron work with any approved enamel paint including cost of all materials etc. complete. Please Enable Macros to View BoQ information |