| 1 | Scraping of moss, blisters etc.thoroughly from exterior surface of wallsnecessitating the use of scraper, wire brush etc.(Payment against thisitem will be made only when this has been done on the specific direction of the Engineer-in-charge |
| 2 | Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed. |
| 3 | Plaster (to wall, floor, ceiling etc.) with sand and cement morter including rounding off or chamfering corners as directed and raking out joints or roughening of concrete surfece, including throating, nosing and drip course wherer necessary (grii) With (4:1) cement mortara)20 mm thick plaster.Ground Floor |
| 4 | a)20 mm thick plaster.First floor |
| 5 | a)20 mm thick plaster.Second floor |
| 6 | a)20 mm thick plaster.Third floor |
| 7 | a)20 mm thick plaster.Above Third floor |
| 8 | Plaster (to wall, floor, ceiling etc.) with sand and cement morter including rounding off or chamfering corners as directed and raking out joints or roughening of concrete surfece, including throating, nosing and drip course wherer necessary (grii) With (4:1) cement mortarb)15 mm thick plaster.ground floor |
| 9 | b)15 mm thick plaster.First floor |
| 10 | b)15 mm thick plaster.Second floor |
| 11 | b)15 mm thick plaster.Third floor |
| 12 | Extra rate for using water proofing and plasticising admixture @ 0.2% by weight of cement (or at manufacturer's specified rate) for concrete of various grades |
| 13 | Applying Exterior grade Acrylic primer of approved quality and brandon plastered or cencrete surface old or new surface to receivedecorative textured (matt finish) or smooth finish acrylic exterioremulsion paint including scraping and preparing the surface throughly,complete as per manufacturer's specification and as per direction of theEIC.In Ground Floor: (b) Two Coats ground floor |
| 14 | First floor |
| 15 | Second floor |
| 16 | Third floor |
| 17 | Above Third floor |
| 18 | Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer's specification and as per direction of Engineer-in-Charge to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primer. In Ground floor (Two Coat)a) Normal Acrylic Emulsionground floor |
| 19 | First floor |
| 20 | Second floor |
| 21 | Third floor |
| 22 | Above Third floor |
| 23 | Rendering the Surface of walls and ceiling with White Cement baseWATER PROOF wall putty of approved make & brand.(1.5 mm thick) |
| 24 | Applying Interior grade Acrylic Primer of approved quality and brandon plastered or cencrete surface old or new surface to receiveDistemper/ Acrylic emulsion paint including scraping and preparingthe surface throughly, complete as per manufacturer's specification andas per direction of the EIC. (In Ground Floor)(b) Two Coats ii) Solvent based interior grade Acrylic Primer |
| 25 | (A) Painting with best quality synthetic enamel paint of approved makeand brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : (a) On timber or plastered surface : With other than hi-gloss of approved quality- (iv) Two coats (with any shade except white |
| 26 | Renewing expansion joint with Elastomeric Polysulphide Sealant of gap size 50mm X 25mm Including cleaning of the expansion joint thoroughly, mending of edges & surface, placing 50mm dia Backer rod as back up material with the cost of materials, labours, & all other incidental charges as per manufacturer's specification & direction of Engineer-in charge. |
| 27 | Removing old scales, blisters etc. of interior surface of walls,ceiling byscraping etc. and preparing smooth and even surface with rendering orcement mortar (1:2) (as necessary), to make the surface suitable forreceiving distemper. (Payment against this item will be made only whenthis has been done on the specific direction of the Engineer-in-charge). |
| 28 | Uprooting and removing plants from the surface of walls parapet etc and making good damages. (Repairing of damages to be paid separately).(a) Small plant of girth of exposed stem upto 75 mm. lift upto 6 mtr |
| 29 | Taking out old damaged tarfelt from the roof, parapet etc.preparing the roof surfaces by removing all spoils, blisters, moss etc. from the working site and disposal of the same beyond the compound and cleaning the site in all respect as per direction of Engineer-in-Charge. |
| 30 | Supplying & laying 3mm thick pre-fabricated plastomericwater proofing membrane conforming to EN 12311-1 & ASTMD 5147, manufactured with atactic poly propylene(APP) modified premium grade asphalt , specially reinforced with non-woven polyester core with polyester reinforcement @160 gms per sqm & both faces covered with thermo-fusiblepolyethylene film /MineraL on top face over a coat of primer @ 0.40 lit/sqm of manufacturer's specification on smooth,clean dry surface prepared wherever required.Lap joint shall be provided of 75 mm in longitudinal & 100 mm in transverse direction and fused using LPG/ Propane torch employing extra care ensuring full bondage, complete removal of entrapped air and sealing edges into grooves in appropriate manner as per direction of Engineer -in-chargeall complete including materials,labour and applicable taxes. (Payment shall be made on the basis of finished surface area.). Membrane Property: Softening Point > 150 deg C, ColdFlexibility < -6 deg C, Tensile Strength, N/cm : 600 (longitudinal), 450 (transverse), Tearing Strength, N: 300 (longitudinal), 200 (transverse) |
| 31 | (ii) Door stopper (Anodised aluminium) |
| 32 | i) Hydraulic door closer of approved quality as per I.S.I. standard fitted and fixed complete. a) Heavy type (I.S.I. size 3) |
| 33 | Anodised aluminium barrel / tower / socket bolt (full covered) of approved manufactured from extruded section conforming to I.S. 204/74 fitted and fixed with cadmium plated screws:(vi) 200mm long x 10mm dia. bolt. |
| 34 | Anodised aluminium decorative handle (hexagonal / fluted) of approed quality fitted and fixed complete. (ii) 175mm plate x 12mm dia rod x 60mm hexagonal / fluted. |
| 35 | i) Iron hasp bolt of approved quality fitted and fixed complete (oxidised) with 16mm dia rod with centre bolt and round fitting. (b) 250mm long. |
| 36 | Expansion joint in floor roof etc. formed with V strips madeof 22.5 cm wide strips of 24 gauge aluminium sheets withanchor arm projecting on each side (and end turned )embedded in adjacent cement concrete, including shapingand finishing the edges on either side of the joint (includingthe cost of bituminous filler if any) complete as per directionof Engineer-in-Charge. |
| 37 | Supplying,fitting and fixing 32 mm dia. Flush Pipe of approved make with necessary fixing materials and clamps complete.i) Polythene Flush Pipe |
| 38 | Supplying, fitting and fixing liquid soap container. (d) Polythene |
| 39 | Supplying, fitting and fixing soap holder. (c) Polythene |
| 40 | Supplying, fitting and fixing 10 litre porcelain low-down cistern of approved make with either side or bottom inlet, side overflow, brackets complete with all internnal PVC fittings.White |
| 41 | Supplying, fitting and fixing bib cock or stop cock.(f) (i) Polythene Bib Cock / Stop Cock (HD) with metal inlet (EMCO /ATLAS or equivalent) 15 mm |
| 42 | Supplying,fitting and fixing approved brand P.V.C. CONNECTOR white flexible, with both ends coupling with heavy brass C.P. nut, 15 mm dia.(iii) 600 mm long |
| 43 | Supplying bubble free float glass of approved make and brandconforming to IS: 2835-1987.i) 4mm thick clear glass |
| 44 | Supplying Weather Silicone sealant of approved make and brand for fixing of grove line between the Glasses as per direction of Engineer-in-charge. For Structural Glazing/Curtain wall.Weather Silicone sealant for filling the Grove line between Glasses or any other material for facial work |
| 45 | Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete. A) UPVC Pipes: (i) 75 mm. Dia. |
| 46 | Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, alamoid/Bitumen/M-Seal etc) complete. A) UPVC Pipes: (ii) 110 mm. Dia |
| 47 | Neat cement punning about 1.5mm thick in wall, dado, windowsill, floor etc.NOTE:Cement 0.152 cu.m per100 sq.m |
| 48 | Supplying, fitting and fixing porcelain partition wall of approved make ofsize 618 mm X 310 mm complete in all respect. |
| 49 | (f) Hand Shower(Health Faucet) with 1mtr Fexible Tube with WallHook(Equivalent to Code No.573 & Model -ALLIED of Jaquar orsimilar). Please Enable Macros to View BoQ information |