|
| 1 | Creation of Additional Electrical Facilities for Gomia GCS, Bokaro Asset |
| 2 | Lump sum price for complete Scope of Work on turnkey basis, net of scrap value of material, as assessed by the bidder and inclusive of all taxes, duties, levies, insurance, cess etc. Note: Total Lump sum Price shall be inclusive of Design & Detailed Engineering, Materials, Construction, Installation, Testing & Commissioning etc. OIL AND NATURAL GAS CORPORATION LTD. Creation of Additional Electrical Facilities for Gomia GCS, Bokaro Asset APPENDIX A-3, Proforma for Price Schedule Note 1: Only Yellow Coloured Cells to be filled. Note 2: BIDDERS please fill this sheet very carefully and upload as per this price format. Note 3: Please refer general notes below. I Sl. No. Lump sum price for complete Scope of Work on turnkey basis, net of scrap value of material, as assessed by the bidder and inclusive of all taxes, duties, levies, insurance, cess etc. Note: Total Lump sum Price shall be inclusive of Design & Detailed Engineering, Materials, Construction, Installation, Testing & Commissioning etc. Currency INR A Surface Facilities: LUMP SUM PRICE for material & services for the entire scope of work which shall include in general but not limited to Project Management, pre/post engineering site surveys, detailed engineering / process design, procurement, manufacturing, supply, fabrication, inspection, testing, surface preparation and painting, expediting, transportation and delivery of all equipment/materials to the work site, storage, dismantling, removal and handing over of dismantled facilities/ debris, site grading, leveling, civil and structural construction, erection/installation of equipment and packages, piping fabrication and erection, hook up to existing systems, installation of instrumentation, electrical works, painting, insulation, inspection, testing, pre-commissioning, lubricants, chemicals and consumables for testing, liaison works between various agencies, pre- commissioning and the cost of consumables for startup/commissioning, commissioning and 72 hours continuous Performance Guarantee Test Run (PGTR) for the facilities covered under the scope for\\" (Creation of Additional Electrical Facilities for Gomia GCS, CBM Asset Bokaro) \\" on lump sum turnkey basis (The detailed scope of work has been provided in Technical Bid package). B Insurance for LSTK Portion in compliance of clause 7.3 of the GCC (i.e. Sum of B-1 to B-6 below) 0.0 B-1 Contractor’s All Risk Insurance/ Erection all risks/ Storage cum erection Insurance (including Onshore Terrorism cover) B-2 Cargo Transit Insurance B-3 Third Party Liability Insurance B-4 Motor Vehicles Package Policy which included Third Party Liability Insurance B-5 Workmen’s Compensation Insurance / Employer’s Liability Insurance B-6 Contractor's Constructional Plant and Equipment Insurance C IGST/ CGST & SGST/ UTGST as applicable on both A & B (=(A+B)xC1%) 0.0 C1 IGST/ CGST & SGST/ UTGST as applicable on price at A & B above (please quote applicable %) D TOTAL LUMP SUM PRICE FOR THE COMPLETE SCOPE OF WORK OF THE TENDER (i.e. A+B+C) 0.0 E MATERIAL CONTENT / COMPONENT ELIGIBLE FOR PEL/ML BENEFITS (i) Amount included in Item A above (Material Cost) for availing concessional IGST/ SGST & CGST/UTGST as applicable, as per Notification No.3/2017 - Central Tax (Rate) Dated 28.06.2017 and any amendments thereto. (For Domestic Procurement of materials) (ii) Amount included in item A above (Material Cost) for availing Custom Duty Exemptions with Concessional IGST rate for PEL/ML areas as per Notification no. 50/2017-Customs Dated 30.06.2017 and any amendments thereto. ONGC shall issue Recommendatory letter for obtaining EC for above (For Import of materials) Note |
| 3 | Payment shall be made as per Milestone Payment Formula for the respective works. General Notes: |
| 4 | Cost of material shall include cost of the materials/ equipments etc. required to be incorporated in the works, aids for fabrication, transportation and installation, cost of spares and any special tools & tackles required for pre commissioning, lubricants, chemicals and consumables for testing/ pre-commissioning and the cost of consumables for startup/ commissioning as well as for duration of operation as per details given in bidding documents. |
| 5 | Bidders to ascertain themselves all the applicable taxes & duties and include in their offer all such taxes and duties as applicable & quoted, which shall be considered for the purpose of evaluation. Bidders also to indicate ONLY such taxes & duties in relation to this contract, which the bidder is liable to pay directly to Indian Tax authorities separately in the price format at I-C. Reimbursement of IGST, CGST, SGST, UTGST etc. (which bidder is required to pay directly to Indian Tax Authorities) would, however, be made at actuals in Indian Rupees upon submission of documentary proof of duty assessment & payment (through deposit or through credit) thereof and would further be limited to the amount indicated in price schedule, whichever is less. No reimbursement shall be made to the bidder for Custom Duty, IGST, CGST, SGST, UTGST etc., paid by bidders to their Sub Contractor, Vendors, Agents etc. Change in law is not applicable against such taxes & duties (i.e. Custom Duty, IGST,SGST,CGST,UTGST etc.) paid by bidders to their Sub Contractor, Vendors, Agents etc. |
| 6 | The above costs i.e. total lump sum price are all inclusive costs for providing the material & services as per the requirements contained in the Bidding Documents read with subsequent amendments/addendum /corrigendum /clarifications conveyed to the bidder. |
| 7 | TDS as applicable under statute, will be deducted |
| 8 | Deleted |
| 9 | Deleted |
| 10 | Bidders to consider various Custom & GST exemptions/Concessional rate available for eligible PEL/ML areas as well as different facilities covered under the project . |
| 11 | Please refer GCC clause no. 19.0 regarding joint statement which shall be signed by ONGC & contractor at periodic intervals of 06 months. II UNIT RATE : Deleted III Cost Re-Imbursable Additional Items : Cost Plus Percentage |
| 12 | Percentage fee applicable to cost of material used for extra work items. |
| 13 | Percentage fee applicable to equipment subcontracts for extra work. |
| 14 | Percentage fee applicable to labour subcontracts for extra work. |
| 15 | Percentage fee applicable to one year’s spares. Notes: |
| 16 | The above percentage will also be used by the Company to order bought-out items and extra equipment not included in the Bidding Documents. |
| 17 | In respect of item 4 the cost shall be reimbursed as per provision of clause 5.16 of part II, GCC. IV CUSTOMS DUTY : Deleted V Change In Laws and Regulations: Laws, Acts, Rules, Regulations etc. and the tariffs thereof considered by the Bidder while estimating the incidence of taxes, duties, fees, charges, levies etc. included in the bidder’s lump sum prices for the Works (as quoted in the Appendix A-3, I through V) as per relevant provisions of General Conditions of Contract to be used for the purpose of adjustment of Contract Price in the event of change of Law in terms of Clause 7.6 of General Conditions of Contract are as under: Sl. no. ITEM Bidding Documents Clause Reference Laws / Acts / Rules / regulations reference Tarif indicating rate of tax/ duty/ fee/ charge/ levy Tax Amount included in the Lump sum price (Add taxes together for all locations/ works) Remarks 1.0 2.0 3.0 4.0 5.0 |
| 18 | IGST/ CGST & SGST/ UTGST as applicable for the following: i Creation of Additional Electrical Facilities for Gomia GCS, Bokaro Asset as quoted at A of I-Lumpsum of price Schedule. Bidder to ensure that the quoted taxes and duties, against each item, should be w.r.t the corresponding combined value of material, services & value of insurance quoted under various heads of I-Lumpsum of Price Schedu le i.e. Appendix A-3. ii Insurance as quoted at B of I-Lumpsum of price Schedule. a. Total IGST/ CGST & SGST/ UTGST (as applicable) as quoted above b. Total Quoted IGST/ CGST & SGST/ UTGST (as applicable) under item I-C of Price Schedule i.e Appendix A-3 c. Whether item a and b above are equal. Yes Note:- |
| 19 | Bidder to ensure that \\"Total IGST/ CGST & SGST/ UTGST (as applicable)\\" above must be eaual to the value quoted against I-C of Price Schedule i.e Appendix A-3. |
| 20 | Bidders are requested to go through Clause 7.6 of General Conditions of Contract carefully, while furnishing the above table. Strike out the items, which are not applicable or write `not applicable’. |
| 21 | Change in law shall not be applicable to taxes and duties in respect of subcontractors, venders etc. of contractors. |
| 22 | Deleted |
| 23 | Bidders are advised to refer thoroughly scope of work (all disciplines), price impacting activities in the entire terms & conditions mentioned in the tender documents. |
| 24 | For clarity on tax clauses and change in law clauses of GCC, bidder/ contractor may note the following:a. If there is any difference in rate between quoted rate of tax and applicable rate of tax as on bid submission date, then such difference in rate will be maintained for effecting change in law, if any, in future. Without prejudice to any other remedies available to company in the contract or in Law, in case of change in laws during scheduled completion period (included extended period without levy of LD/without reserving right to levy LD), irrespective of amount and rates of taxes quoted by successful bidder/contractor, the total quoted amount (including tax amounts) will be considered as inclusive of all applicable tax amounts which are applicable on the date of bid submission and accordingly, difference between applicable rate of taxes on the date of bid submission and the rates of taxes applicable on the date of change in law, will be reimbursed to successful bidder/contractor by company in case such difference is positive and such difference will be recovered from the successful bidder/contractor by the company in case such difference is negative.b. In case the quoted tax rate/tax amount is less than the applicable tax rate/ tax amount on date of bid submission, it would be considered that the difference in the two rates/amounts is included in the amounts quoted in other quoted line items, other than the quoted tax amount and (i) payment/reimbursement will be limited to considering the quoted tax rate or the quoted tax amount or the amount shown in proof of payment, whichever is lower and (ii) in case there is a change in law, such difference between the quoted tax rate/tax amount and the applicable tax rate/ tax amount on date of bid submission, will be subtracted from the base value (base value is the amount on which taxes are applied which would be derived from the total quoted/contract value inclusive of taxes) to arrive at the net base value on which effect of change in law would be applied.c. In case the quoted tax rate/tax amount is more than the applicable tax rate/ tax amount as on the date of bid submission (i) payment/reimbursement will be restricted to the lower of the two and (ii) in case there is a change inlaw, it will be treated as per Point \\"a\\" above. Please Enable Macros to View BoQ information |