| 1 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC. 1. Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m. (a) In ground floor including roof. |
| 2 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 2. Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m In ground floor including roof. (a) upto 150 mm. thick |
| 3 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 16. 125 mm. thick brick work with 1st class bricks in cement mortar (1:4) in ground floor. |
| 4 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 7. Brick work with 1st class bricks in cement mortar (1:4) (b) In superstructure, ground floor |
| 5 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (b) 15 mm thick plaster |
| 6 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (a) 20 mm thick plaster |
| 7 | ORDINARY CEMENT CONCRETE ( MIX 1:1.5:3 ) WITH GRADED STONE CHIPS ( 20 MM NOMINAL SIZE) EXCLUDING SHUTTERING AND REINFORCEMENT, IF ANY, IN GROUND FLOOR AS PER RELEVANT IS CODES |
| 8 | BUILDING WORKS (E) ROOFING, SHEET WALLING &WATERPROOF TREATMENT . A. ROOFING & SHEETWALLING 14. Supplying, fitting & fixing Zn-Al alloy (55% Al & 45% Zn) coating of 150 grams per sq. metre (followed by colour coated on both side) steel sheet work having minimum yield strength of 550 Mpa of trapizoidal profile of approved make |
| 9 | BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. A. ORIGINAL WORKS 2A. M.S. structural works with hollow sections (square or rectangular shape) conforming to IS: 806-1968 & IS:1161-1998) connected to one another with bracket, gusset, cleat as per design, drawing & direction of Engineer-in-Charge complete including cutting to requisite shape & size, fabrication including metal arc welding conforming to IS: 816-1969 & IS: 9595 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of all M.S. Hollow section, all consumables such as electrodes, gas and hire charges of all tools and plants and labour reqired for execution and all incidental chages (such as electricity, labour insurance) etc. complete. Payment to be made on the basis of calculated weight of structural memebrs of MS Holow Section as specified in relevent IS code in finished work. Payment for gusset, bracket, cleat may be made by adding the actual weight of such items with weight of finished structural members. The rates are considered for a hight of erection 8 m. / 2nd floor level from the ground. Add 1.5 % extra over the rate for each additional floor or 4m. beyond the initial 8 m. or part thereof. i) For roof truss works a) Span up to 12 Mtr |
| 10 | PLUMBING WORKS (A)-(III) CPVC PIPE WORKS AND FITTINGS (A)-(III) CPVC PIPE WORKS AND FITTINGS Supplying, fitting and fixing CPVC (Chlorinated Polyvinyl Chloride) pipes of approved make conforming to IS-15778: 2007 . with all necessary accessories,specials viz.socket,bend,tee,union,cross,elbo,nipple,longscrew, reducing socket,reducing tee, short piece etc.fitted with holder bats clamps, including cutting pipes,fitting, fixing etc.complete in all respect including cost of all necessary fittings as required,jointing materials in any position above ground. (Payment will be made on the centre line measurements of total pipe line including all specials. No separate payment will be made for accesories, specials. (a) For Exposed Work (i) CPVC Pipes Class-1, SDR-11 (Dia) 15 mm |
| 11 | PLUMBING WORKS (A)-(III) CPVC PIPE WORKS AND FITTINGS (A)-(III) CPVC PIPE WORKS AND FITTINGS Supplying, fitting and fixing CPVC (Chlorinated Polyvinyl Chloride) pipes of approved make conforming to IS-15778: 2007 . with all necessary accessories,specials viz. socket,bend,tee,union,cross,elbo,nipple,longscrew, reducing socket,reducing tee, short piece etc.fitted with holder bats clamps, including cutting pipes,fitting, fixing etc.complete in all respect including cost of all necessary fittings as required,jointing materials in any position above ground. (Payment will be made on the centre line measurements of total pipe line including all specials. No separate payment will be made for accesories, specials. (a) For Exposed Work (i) CPVC Pipes Class-1, SDR-11 (Dia) 20 mm |
| 12 | PLUMBING WORKS (A)-(III) CPVC PIPE WORKS AND FITTINGS (A)-(III) CPVC PIPE WORKS AND FITTINGS Supplying, fitting and fixing CPVC (Chlorinated Polyvinyl Chloride) pipes of approved make conforming to IS-15778: 2007 . with all necessary accessories,specials viz. socket,bend,tee,union,cross,elbo,nipple,longscrew, reducing socket,reducing tee, short piece etc.fitted with holder bats clamps, including cutting pipes,fitting, fixing etc.complete in all respect including cost of all necessary fittings as required,jointing materials in any position above ground. (Payment will be made on the centre line measurements of total pipe line including all specials. No separate payment will be made for accesories, specials. (a) For Exposed Work (i) CPVC Pipes Class-1, SDR-11 (Dia) 25 mm |
| 13 | BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.A) UPVC Pipes:(ii) 110 mm. Dia. |
| 14 | BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.B) UPVC Fittings:a) Plain Tee(ii) 110 mm. Dia. |
| 15 | BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.B) UPVC Fittings:b) Plain Y.(ii) 110 mm. Dia. |
| 16 | BUILDING WORKS(M) DRAIN, DOWN PIPES, CHIMNEY ETC?.(C). ADDITIONAL RATE?(21)Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.B) UPVC Fittings:c) Bend 87.5 degree. (ii) 110 mm. Dia |
| 17 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 3. Making one set of scaffolding only for replacing glass panels, painting, uprooting plant and another repairing works of building and S&P works for external works only with 10 cm. dia bamboo as main posts at the rate of 1 metre centre to centre and 7.5 cm. dia bamboo ties @ 0.75 metre apart fitting and fixing with necessary coir, nails etc. as per direction of the Engineer-incharge. (This item should be executed only after prior approval of the Engineer-incharge). Firstly, one number to be paid and then labour rate for shifting up to further nineteenth (19) times @ 10% each time to be considered. If necessary further after twenty times of total use, another one number new and labour rate for shifting to be considered accordingly a) 3.90 metre height |
| 18 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 3. Making one set of scaffolding only for replacing glass panels, painting, uprooting plant and another repairing works of building and S&P works for external works only with 10 cm. dia bamboo as main posts at the rate of 1 metre centre to centre and 7.5 cm. dia bamboo ties @ 0.75 metre apart fitting and fixing with necessary coir, nails etc. as per direction of the Engineer-incharge. (This item should be executed only after prior approval of the Engineer-incharge). Firstly, one number to be paid and then labour rate for shifting up to further nineteenth (19) times @ 10% each time to be considered. If necessary further after twenty times of total use, another one number new and labour rate for shifting to be considered accordingly b) Extra for additional 3.6 height or part thereof |
| 19 | BUILDING WORKS ( C ) BRICKWORKS, CONCRETE WORKS Etc. A. BRICK WORKS 1. Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. |
| 20 | 35mm thick Cement Concrete Pavement (1:2:4) in floor/footpath etc. with graded stone chips 11.2mm down,properly leveled with 3mm thick screen on top by cement slurry [email protected] cement per Sqm. Rounding off corners, chequering as required including taking necessary protective measure complete in Gr.floor/footpath. |
| 21 | SECTION 1. ------------BUILDING WORKS (K) PAINTING, VERNISHING ETC A. ORIGINAL WORKS 1 (a) Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc (This item is applicable to new work or old work when the original surface has been exposed by removal of old paint.) |
| 22 | BUILDING WORKS (K) PAINTING, VERNISHING ETC?(A) ORIGINAL WORKS.(2)(A) Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary :(b) On steel or other metal surface :With super gloss (hi-gloss) -(iv) Two coats (with any shade except white) |
| 23 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: A. SPECIAL WORKS. III. EVENT MANAGEMENT : 6) Hire and labour charges for 100 mm dia bamboo railing on 150 mm dia Jhau/Eucalyptus or other approved timber posts each 2.0 m in length, tied 2 number post strongly with coir ropes in the fashion of a scissor with a spacing of 1.8 m over pacca road without damaging the surface and tying strongly 3 (three) rows of bamboo railing on each leg and 1 (one) railing connecting all the pivot junctions including cost of loading unloading, stacking & carriage of all materials and labour complete, and maintaining barricading for a period beyond 5 (five) days after the reported & recorded time of completion of the entire work to the satisfaction of Engineer-in-charge. (Note: This work should not be executed without specific permission of Superintending Engineer). (100 mm. dia bamboo railing & 150mm. dia Jhau/Eucalyptus/other approved timber posts @ 1.80m apart). (ii) Railing 3 row on each leg and 1 at pivot point. |
| 24 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 13. Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge |
| 25 | Sub Total |
| 26 | GST 18% |
| 27 | CESS 1% Please Enable Macros to View BoQ information |