| 1 | Earth work excavation of foundation in all kind of soil wihin initial lead of 50m and initial lift of 1.5m including dressing the sides leveling the bed and depositing the execued materails away from the work site, shoring etc if required, complete the item of work in all rspect as per direction of the Engineer-in-charge. |
| 2 | Filling foundation and plinth with excavated materials etc. compete |
| 3 | Filling foundation and plinth with filling sand laying in layers including ramming, watering, compacting including cost, conveyance and royality of sand fom approved quarry and other taxes I any with all leads, lift, T7P etc. complete the items of work in all respect as per specification and direction of Engineer-in-charge. |
| 4 | C.C.(1:3:6) using 40 mm size and Downgraded crusher broken HG stone metal free from wathered surface of approved quality from approved Quarry in foundation and plinth including laying concrete in laers with de compaction, watering and curing including cost, conveyance, royality and taxes of all materials with all lead, lift and delifts, T&P etc required for comletion of the work in all respect as per direction of the Engineer-in-charge. |
| 5 | Brick work with Flyash Brick of size 25 cm x 12 cm x 8 cm having crushing strengt between 100kg/cm2 to 149 kg/cm2 in cement mortar (1:6) in Foundation & Plinth including cost, conveyance, royality, taxes of all materials, labour, T&P required for the work complete and as per the direction of the Engineer-in-charge. |
| 6 | SUB-STRUCTURE |
| 7 | RCC work of M-20 grade with 20 mm and downgrade black hard granite chips including cost, conveyance, royality and all taxes of all materials with all leads, lift T&P etc. after the curing of RCC work for 28 days complete the items of work in all respect as per specification and direction of Engineer-in-charge. |
| 8 | Column base & Footing |
| 9 | Plinth Beam |
| 10 | Column (Ground Floor) |
| 11 | Lintel (Ground Floor) |
| 12 | Chajja Ground FLOOR |
| 13 | Beam (Ground Floor) |
| 14 | Roof Slab Ground FLOOR |
| 15 | Providing & Fixing TOR Reinforcement Bar of approed making of RC work of required diameter & of approved quality including strengthening cutting, Bending, Binding, joining tying, the Grills hosting, lowering and placing in position as per the approved design and drawing with provision for fan hooks where required including the cost, conveyance of reinforcement bars of tor steel and bending wires of 18 to 20 gause, cost of all labour, loading, unloading. labour cess T&P, etc required for the work complete for the work in all heights as per specification & excluding GST as per direction of Engineer-in-charge. |
| 16 | GROUND FLOOR |
| 17 | Fly Ash Brick Masonry in cement mortar of mix (1:6) using Fly Ash bricks of size 25c.m x 11 c.m x 8 c.m in superstructure having crushing strength not less than 75 kg per square c.m. with cement and screened & washed sharp sand for mortar after immersing the bricks for 6 (Six) hours in water before use in works with all necessary projections, splays cutting, circular moulding, corbelling, chamfering, watering and curing etc. including cost, coveyance,stacking, loading, unloading, royalties , all taxes ,cost of all labour,Labour cess ,scaffolding, sundries and T&P required for the works etc. complete in all respect as directed by the Engineer-in-charge. |
| 18 | GROUND FLOOR |
| 19 | Plastering Providing 12mm. Thick cement plaster in cement mortar or mix(1:6) in all floors at all height with cement & screened and washed sharp river sand for mortar and finished smooth to the rough surface of the brick masonary walls after racking out the joints (alongwith providing grooves wherever necessary) including watering and curing,rounding of corners etc. complete with cost,conveyance, loading, unloading, royalities and taxes of all materials,cost of all labour,T&P,sundries and scaffolding required for the work etc. as directed by the Engineer-in- charge. |
| 20 | GROUND FLOOR |
| 21 | Providing 16mm. Thick cement plaster in cement mortar or mix(1:6) in all floors at all height with cement & screened and washed sharp river sand for mortar and finished smooth to the rough surface of the brick masonary walls after racking out the joints (alongwith providing grooves wherever necessary)including watering and curing,rounding of corners etc. complete with cost,conveyance,loading, unloading,royalities and taxes of all materials,cost of all labour,T&P,sundries and scaffolding required for the work etc. as directed by the Engineer-in- charge. |
| 22 | GROUND FLOOR |
| 23 | 20 mm Thick Grading Plaster (1:4) over Roof Slab including all cost etc. complete |
| 24 | GROUND FLOOR |
| 25 | Supplying Fiting & Fixing of M.S. Door & Window including all cost etc.complete |
| 26 | GROUND FLOOR |
| 27 | Supplying Fiting & Fixing of Vetrified Tile on Floor including all cost etc.complete |
| 28 | GROUND FLOOR |
| 29 | Supplying Fiting & Fixing of Vetrified Tile on Dados including all cost etc.complete. |
| 30 | GROUND FLOOR |
| 31 | Supplying Fiting & Fixing of Industrial Vetrified Tile on Floor including all cost etc.complete |
| 32 | GROUND FLOOR |
| 33 | Supplying Fiting & Fixing of Industrial Vetrified Tile on Dados including all cost etc.complete |
| 34 | GROUND FLOOR |
| 35 | Supplying, Fitting & Fixing of 32 mm Thick Flush Door Shutter with Approved quality of 30 mm Thick BWR Block board pasted with 1 mm Thick Sunmica on Both side of approed Design and quality icluding cost of all door fittings and fixture etc. complete |
| 36 | GROUND FLOOR |
| 37 | Supplying Fiting & Fixing of Alumunium Window (Sliding Type) including all cost etc.complete |
| 38 | GROUND FLOOR |
| 39 | Supplying Fiting & Fixing of 5mm Thick Black Glass including all cost etc.complete |
| 40 | GROUND FLOOR |
| 41 | Providing Synthetic Enamal Paint (2 coat) over a coat of Pimer including all cost etc.complete |
| 42 | GROUND FLOOR |
| 43 | Providing Acrylic Wall Putty ( Water Based & Cement Based) including all cost etc.complete |
| 44 | GROUND FLOOR |
| 45 | Providing Plastic Emulsion Paint (2 Coat) over a coat of Primer including all cost etc.complete |
| 46 | GROUND FLOOR |
| 47 | Providing Weather Seal Coat (2 Coat) over a coat of Primer including all cost etc.complete |
| 48 | GROUND FLOOR Please Enable Macros to View BoQ information |