| 1 | Earthwork in all kinds of soil in excavation of foundation trenches for columns, basement, tie beams, walls and steps in all kinds of soil including moorum, hard stoney earth and earth mixed with boulders except sheet rocks and boulders |
| 2 | Supplying and filling the foundation and plinth with clean coarse river sand of approved quality from approved quarry, laying in layers not exceeding 150mm thick, watering and ramming |
| 3 | Providing & laying cement concrete of prop. (1:3:6) in foundation bed and floors using 40mm nominal size down graded, screened, washed hard black crusher broken granite metal of approved quality |
| 4 | Fly ash bricks of 25cmx12cmx8cm. Size having crushing strength not less than 75 Kg/Sqcm. With dimensional tolerance +2%. percentin cement mortar (1:6) in foundation and plinth |
| 5 | RCC work M20 with 20 mm and down graded size black hard grinite ( crusher broken ) stone chips including hoisting,lowering & laying concrete & compacting by using vibrator watering & curing for 4 weeks including cost & conveyance, royalties & taxes, Centring & Shuttering of all materials & labour required for the work etc complete with all T & P in all respect but excluding cost & conveyance of M.S rods & binding wires & tying the grills & placing in proper position.A) R.C.C. FOUNDATION & COLUMN BASE. |
| 6 | B) R.C.C. PLINTH BEND |
| 7 | C) R.C.C. LINTELS |
| 8 | D) R.C.C. BEAM & COLUMN |
| 9 | E) R.C.C. ROOF SLAB |
| 10 | G) R.C.C. CHAJJA |
| 11 | Straightening, cutting, bending and binding, welding and jointing (if necessary) coiled/bent up M.S. rods/Tor Steel/deformed rods etc. including hoisting, placing in position, tying the grills binding with 18 to 20 guage |
| 12 | Fly ash bricks of 25cmx12cmx8cm. Size having crushing strength not less than 75 Kg/Sqcm. With dimensional tolerance +2%. percentin cement mortar (1:6) brick masonary in super structure |
| 13 | Cement concrete (1:2:4) with 12mm size crusher broken hard granite metal including cost of all labour, materials with all taxes, lead, T & P etc all complete. |
| 14 | 12mm. thick cement plaster (1:6) on brick work racking out the joints finished smooth to proper line and plumb, watering, curing for 7 days with cost, conveyance, royalties taxes of all materials, cost of all labour T&p etc. as per direction of Engineer in charge. (Ground Floor Internal) |
| 15 | 12mm. thick cement plaster (1:3) on brick work with punning |
| 16 | 6 mm thick cement plaster (1:4) to R CC surfaces finished smooth including closed deep chiping and slury treatment |
| 17 | 16 mm. thick cement plaster (1 :6) over brick or stone masonry work racking out the joints finished smooth to proper line and plumb, watering, curing for 7 days with cost, conveyance, royalties taxes of all materials, cost of all labour T&p etc. as per direction of Engineer in charge. (External) |
| 18 | Supplying, fitting and fixing vetrifed tile in floors of size 600mm x 600mm of approved make confirming to IS 13755 laid on 20 mm thick cement mortar 1:4 and filling joints with white cement of approved quality including cost of all materials, labour T&P etc required for the work all complete as per direction of Engineer in charge.( For new work only) |
| 19 | Antiskid Floor Tile - (Make -Johnson / Khajaria/Somali) |
| 20 | Digital Wall Tile - (Size-300mmX450mm) |
| 21 | Dressed seasoned sal wood work framed and fixed (wrought and put up) in trusses, purlines, frames of doors, windows, ventilabours and beams. including cost of all door fittings and fixtures etc. complete. |
| 22 | 32mm piasal wood or local teak wood panelled shutters moulded with all labour ironfitting and wooden hinged cleats etc fitted and fixed complete in all respect. But excluding the cost of iron fitiing. |
| 23 | Supplying, fitting & fixing of two track UPVC Sliding window of approved make with 6mm thick glass of approved quality complete with frame, shutters and all fitting and fixtures.complete as per direction of Engineer in Charge. |
| 24 | Supply, fitting and fixing of Rajashri moulded PVC solid flush door frame with shutter having water and termite proof etc. including cost of hardware fixtures etc. all complete as per direction of Engineer in Charge. |
| 25 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. |
| 26 | Finishing plastered surfaces of walls with Berger Synthetic putty (interior) & marking smooth to receive painting including cost of labour & Material including primer |
| 27 | Providing weather coats two coats with approved quality and shade over a coat of primer over plastered surface with brush including cleaning the surface watering curing cost of cement paint taxes labour charges T&P etc complete as per the direction of Engineer in charge. |
| 28 | Wall painting 2 coats with Plastic Emulsion Paint of approved shade on new work to give an even shade in Ground Floor. |
| 29 | Enamel Painting two coats with any approved paint including cost of all labour, materials T & P with taxes, transportation etc all complete in Ground Floor. |
| 30 | Remove excavate materials from the site by mechanical means with loading and unloading the same within 5 kms lead as per direction of enginner in charge . |
| 31 | PH MaterialCutting Hole in 250mm to 375mm thick wall thick Brick Wall for taking 110mm/160mm dia PVC Pipe and mendig good to damages after completion of Work etc. Complete. |
| 32 | Providing & Fixing of AIWC with integral P trap inclusive of ciestern, seat cover all complete set confirming to IS 2556: Part 8-2004, to the floor with wooden plug and chromium plated screws including jointing the trap with soil pipe in cement mortar ( 1:1 ) etc all complete as per specification. |
| 33 | Providing 100 mm size P or S trap ( with Horn or without Horn ) for water closet squatting pan including jopinting the trap with pan in cement mortar 1:1 as per specification etc. complete. |
| 34 | Providing & fixing to wall, ceiling ands floor the pipe fittings of following nominal bore with clamps including making good the wall ceilling and floor, all complete in ground floor including the cost of material as per the PHE specification and direction of the Engineer in charge ( Sch-80, ASTM-D-1785/2004). 15 mm dia UPVC pipes |
| 35 | 25 mm dia UPVC Pipe |
| 36 | 40 mm UPVC pipe ( considering 10mtr distance of main pipe line) |
| 37 | Providing, fixing, fitting of the following Brass/ Gun metal/ Chromium plated fitting of approved make (Conforming to respective I.S Specification) Including the jointing materials, If any all complete as per the PHE specification and the direction of the Engineer in charge. (Plaza/ciser/Zigma), 50mm X 800 mm long PVC Urinal waste pipe. |
| 38 | 15mm dia C.P Concealed stop cock |
| 39 | 25mm PVC Ball valve |
| 40 | C.P Gratting |
| 41 | 15 mm dia C.P pillar cock |
| 42 | 15 mm CP 2 in 1 Bib cock . |
| 43 | CP Health Foucet with 1.0 mtr PVC Tube |
| 44 | 32 mm C.P Waste |
| 45 | 15 mm X 600 mm PVC Connection Pipe |
| 46 | 40mm UPVC-ASTM Ball Valve |
| 47 | CP Urinal Push Cock 15 mm dia |
| 48 | 10 Ltr PVC low level Cistern with fittings-Colour |
| 49 | EWC Standard Seat Cover (Colour) |
| 50 | 32 mm PVC long Flush bend |
| 51 | C.P. glass self with glass |
| 52 | C.P.revolving shower with arm (overhead) |
| 53 | C.P. towel rail.(600x20)mm |
| 54 | C.P. towel ring. |
| 55 | C.P.soap holder/disc. |
| 56 | C.P. toilet paper holder |
| 57 | Standard Pedestal Wash Basin |
| 58 | Fixing 600 mm x 450 mm Bevelled edge mirror of superior glass mounted on 6 mm thick A.C Sheet or Plywood sheet and fixed to wooden plugs with chromium plated brass screws and washers complete as per Specification. |
| 59 | Providing, Fitting, Fixing of PVC SWR pipe of standard manufactures including all jointing, earthwork in excavation of trenches in all kind of soil up to a depth of 0.90 mtr and refilling the trench in 0.30 mtr layers duly watered and rammed or fixing to walls with supply of nails, bobbings, wall plugs all complete as per the PHD Specification and the direction of the Engineer-in-charge. (110 mm dia PVC SWR Pipe S/S) |
| 60 | 110 mm PVC Door bend |
| 61 | 110 mm PVC plain Bend |
| 62 | 110 mm PVC SWR Cowel |
| 63 | 75 mm PVC SWR Pipe |
| 64 | 75 mm PVC SWR Bend |
| 65 | Supplying of all materials, Labour, T&P and fixing of Rotational moulded polyethylene cylindrical vertical water storage tanks(3 Layer White, 1000ltr) conforming to IS : 12701--1996 as per requirement including conveyance of all materials to work site etc all complete as per specification and direction of the Engineer-in-charge |
| 66 | Making signboard, Photography and other uforseen item i.e. nonplastic in between slabs and road etc labour engaged complete |
| 67 | Supplying of all materials, Labour, T&P and fixing of Acrylic sign board with LED lights (inside) as per specification and direction of the Engineer-in-charge |
| 68 | As per MSBY guideline 3years maintainance @5% Please Enable Macros to View BoQ information |