| 1 | Special Repairs |
| 2 | 15.28.1:Dismantling roofing including ridges, hips, velleys and gutters etc., and stacking the material within 50 metres lead of :G.S. Sheet |
| 3 | 15.18:Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates,bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead. |
| 4 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil |
| 5 | 50.10.2:Steel work for purlin/single section with G I pipes including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete |
| 6 | 13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand) |
| 7 | 9.48.2:Providing and fixing M.S. Grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete.Fixed to openings/ wooden frames with rawl plugs screws etc |
| 8 | 10.28:Providing and fixing stainless steel (Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in-charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) |
| 9 | 13.43.1:Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer |
| 10 | 13.83.2:Wall painting with premium acrylic emulsion paint of interior grade, having VOC (Volatile including applying additional coats wherever required to achieve even shade and colour.Two coats |
| 11 | 13.111.1:Finishing walls with Acrylic Smooth exterior paint of required shade :Old work (Two or more coat applied @ 1.67 ltr/ 10 sqm) on existing cement paint surface |
| 12 | 13.61.1:Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work |
| 13 | OD179001/2025-2026:Providing &fixing Sandwitch Panel roofing sheet of good quality up to any pitch and fixing with polymer coated J or L hooks bolts & nuts 8mm Dia,GI plain /bitumen washers complete but excluding the cost of purlin ,rafters and trusses etc.the sheet shall be opaque or translucent clear or pigmented textured or smooth as specified. |
| 14 | OD179004/2025-2026:Laterite masonry with neatly dressed laterite stone of size 35x20x20cm or nearest size in CM 1:6for foundation and basement including all cost of materials labour charges etc.complete. |
| 15 | OD179010/2025-2026:Laterate masonry with neatly dressed laterate stone of size 35X20X20 cm or nearest size in cement mortar 1:6 for super structure above plinth level up to floor two level including all cost of materials, labour charges etc. |
| 16 | 14.72:Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven story hight made with 40 mm dia. M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staricase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. Note:- This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done . Please Enable Macros to View BoQ information |