Excavation in foundation in ordinary soil (Loam, clay or sand) including lift upto 1.50 M, and lead upto 30 M and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in charge upto a distance of 30 M from the foundaiton trenches. (Where machine can not reach/move). For Building work only . (as per PWD shed of rate S.I.NO. 251, 4.1.1)
2
Earth work embankment with ordinary soil in 20 cm layer i/c ramming & dressing with cartage from distence of 3.00km (A.R) (1KM Kacha+2KM Pacca Road)
3
Concrete with 4cm. Guage brick ballast fine sand of 1.25 F:M. and cement in proportion of 8:4:1 in foundation and under floors including supply of all meterials, labour and T&P etc. required for proper completion of work. (as per PWD shed of rate S.I. No. 275)
4
M-150 brick work in 1:3 (one cement and three fine sand of 1.25 F.M. mortar) in foundation and plinth including supply of all meterials, labour and T&P etc. required for proper completion of work. (as per PWD shed of rate S.I. NO. 307, 6.1.5 )
5
R.C.C. Work with cement approved coarse sand and 2cm. gauge approved stone grit in proportion of 1:2:4 in lintels of doors, windows and sunshades excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I Binding wire and including necessary centering and shuttering etc. and supply of all meterials, labour and T&P etc. required for proper completion of work. Binding wire to be supplied by the contractor free of cost. Including making of drip coarse. but in R.C.C. raft foundation and footing with 4cm. Gauge stone ballast. (as per PWD shed of rate S.I. No.287, 5.6.5)
6
Mild steel or TMT Bars(Fe-500D grade or higher) orHYSD Bars or iron in plain work such as reinforced concrete or reinforced brick work (when not included in an over all rates) brought to required shape as necessary including bending for proper completion of the work and including supply of all steel.(as per PWD shed of rate S.I. NO..504)
7
Cement Concrete with 2cm. guage approved stone ballast coarse sand and cement in proportion of 4:2:1 including supply of all materials, labour and T&P etc. required for proper completion of work. (as per PWD shed of rate S.I. No.279A)
8
12mm. Thick plaster with one part of cement and four part of approved coarse sand including supply of all materials labour and completion of work.Including making of groove in plaster surface.(as per PWD shed of rate S.I. No 584, 13.5.5 )
9
Supply & laying of vetrified Tiles 8mm thick size 600mmX600mm of approved make in flooring i/c all comp. (Based on P.W.D. shedule S.I. No. 2 New item of chapter-14 NI-4
10
Supply & fixing yatri shed(size 8'x20') As pe atteched photo ghrap (consist of 6\\".Dia circular hollow S.S. pipe with supporting brackets for supporting of pily carbonated S.S. sheet .(rate as per analysis)
11
Supply and erraction of S.S. sheeting arrengment consist of 16\\" width plateform for sitting.(rate as per analysis)
12
GST @ 18% and Electric Connection Charge Rs. 10508/- Extra Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.