| 1 | Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m. a) In ground floor including roof. |
| 2 | Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within alead of 75m as directed. |
| 3 | 125 mm. thick brick work with 1st class bricks in cement mortar (1:4) inground floor. |
| 4 | Cleaning the concrete surface by removing dirt and debris, marking defective locations and removing loose concrete by careful stripping untill hard surface is exposed, cutting the concrete to regular shape, wire brushing the exposed surface and removing debris from site complete as per direction of the Engineer - in - Charge. |
| 5 | Applying epoxy based reactive joining agent for joining the old concrete with fresh concrete to be applied within manufacturer's specified time as per manufacturers specification. (0.4 Kg / m² of concrete surface). |
| 6 | Cement concrete (1:1.5:3) with graded stone chips 5.6 mm size with hexagonal square mesh wire netting, I.R.C. fabric mesh or X.P. M. fitted and fixed after tying the existing reinforcement on concrete without distributing the same and with proper scarping and cleaning the reinforcement and disturbed concrete with wire brush etc. after applying a coat of cement including the cost of wire netting I.R.C or X. P. M. & cost of all handling and scaffolding complete as per direction of Engineer-in -charge. a) 25 mm thick |
| 7 | 1st FLOOR |
| 8 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface] (ii) With 1:4 cement mortar , (b) 15 mm thick plaster. |
| 9 | 1ST FLOOR Area same as Stripping off plaster |
| 10 | 2nd FLOOR, Parapet, Main Building |
| 11 | (a) 10 mm thick plaster, G.F |
| 12 | 1 st floor |
| 13 | Taking out shutter of door and window, dismantling by parts (for repair or replacement of damaged parts) , reassembling and refitting and rehanging same with old fittings but with new screws as necessary. (Where different parts of same shutter are renewed under different item, payment under item 73 will be made once only). |
| 14 | Taking out M.S. or W.I. Grills from wooden frame including cutting lugs from masonry wall and refitting the same and mending good damages after repairs. (Excluding the cost of necessary repair of damages) or doing any other necessary works. |
| 15 | Wood work in door and window frame fitted and fixed in position complete including a protective coat of painting at the contact surface of the frame exluding cost of concrete, Iron Butt Hinges and M.S clamps. (The quantum should be correted upto three decimals). (c) Sal : (e) Sal : Malayasian |
| 16 | Panel shutters of door and window, as per design (each panel consisting of singleplank without joint), including fitting and fixing the same in position butexcluding the cost of hinge and other fittings. In ground floor. (iii) 35mm thick shutters with 19mm thick panel of size 30 to 45 cm. (b) Sishu, Gamar, Champ,Badam,Bhola, Mogra, Hallak. |
| 17 | Glazed shutters of doors, windows, fan light, clerestory windows etc. as per design (with ordinary glass of 7.4kg./sq.m. 3mm. Thick) fitted with putty bed and teak wood bead and nails including fitting and fixing shutter in position but excluding the cost of hinges and other fittings. cost of glass, putty, wooded beads etc.will be paid separately. In ground floor. (ii) 35mm thick shutters. (b) Sishu, Gamar, Champ,Badam,Bhola, Mogra, Hallak. |
| 18 | Styles and rails of wooden shutters fitted and fixed complete. (Payment to be made on area of new work only). In Ground Floor: (ii) 35mm Thick shutter. (b) Sishu, Gamar, hamp,Badam,Bhola, Mogra, Hallak. |
| 19 | Easing door and windows. BSGH-Main Building |
| 20 | i) Iron hasp bolt of approved quality fitted and fixed complete (oxidised) with 16mm dia rod with centre bolt and round fitting. (c) 300mm long. |
| 21 | Iron butt hinges of approved quality fitted and fixed with steel screws, with ISImark.(viii) 100mm. X 75mm. X 3.50mm. |
| 22 | Supplying, fitting and fixing M.S. clamps for door and window frame made of flat bent bar, end bifurcated with necessary screws etc. by cement concrete(1:2:4) as per direction. (Cost of concrete will be paid separately)(a) 40mm X 6mm, 250mm Length |
| 23 | Anodised aluminium barrel / tower / socket bolt (full covered) of approved manufactured from extruded section conforming to I.S. 204/74 fitted and fixed with cadmium plated screws: (v) 150mm long x 12mm dia. bolt. |
| 24 | Labour for taking out steel door and window frame for repairs and re-fixing the same (or replacement by new one) including mending good damages (excluding the cost of repair of damages) and applying a protective coat of paint. Upto one sq.m.area of frame. |
| 25 | Supplying, fitting and fixing windows and ventilators with or without integrated grills conforming to IS 1038-1975 and manufactured from rolled steel sections conforming to IS 7452-1974 with non-friction projecting type, box type hinges, glazing clips, lugs locking bracket, handle plate etc, including hoisting in position, straightening if required, fixing lugs in cement concrete ( 1:2:4) with stone chips 20 mm down cutting holes and mending good damages to match with existing surface complete in all respect excluding glazing.b) Openable steel windows as per IS sizes with side hung shutters and horizotal glazing bars. |
| 26 | Renewing steel plated or oxidised casement stay or peg stay of steel window frames including painting two coats with approved paint complete. |
| 27 | Repairing steel shutter with new rivets including taking out and refixing, adjusting, welding, cleaning cutting holes, mending good damage to match with the existing one. |
| 28 | Easing, oiling and adjusting the steel shutters including scraping all members and fitting so as to make the shutters easily operable (no extra payment will be made for taking out and fixing glass, if necessary). |
| 29 | Easing and oiling, cleaning collapsible gate and repairing to locking arrangements. |
| 30 | Renewing bottom rail or top runners of collapsible gate including mending good all damages. |
| 31 | Reparing collapsible gate by cutting out all rivets as necessary reassambling all members including welding pieces of channels, sraightening bent bars and rivetting with new rivets and fitting in position and painting two coats. |
| 32 | Providing and fixing PVC Door Frame of size 50x47mm with a wall thickness of 5mm (± 0.2 mm) made out of single piece extruded PVC profile, with mitred cut joint sand joint with 2 nos. of PVC bracket of size 190 mm x 100 mm long arms of cross section size 35 mm x 15 mm & self driven self taping screws, the verticaldoor profiles to be reinforced with 40x20mm M.S. rectangular tube of 0.8 mm , including providing EPDM rubber gasket weather seal throughout the frame, including jointing 5 mm PVC frame strip with PVC solvent cement on the back of the profile. The doorframe to be fixed to the wall using 8 x100mm long anchor fasteners complete, all as per manufacturer‟s specification and direction of Engineer -in- charge. |
| 33 | PVC Door Shutter-30 mm thick: Supplying fitting and fixing P.V.C. door shutter of approved quality & shade in position, the style & rail of the P.V.C. door shutter will be made of rigid P.V.C. multicavity hollow chamber of 59 mm x30 mm section with 2.0 mm (+/-0.2 mm) wall thickness.Horizontal & vertical section shall be fixed to each other by self tapping screws and 1 solid polymeric or M.S. galvanised tubular 'L' shaped bracket 100mm x 200mm in each corner of the shutter frame for placing hinges. Polymer based multicavity hollow section of 120 mm x30mm with 2.0 mm (+/- 0.2 mm) wall thickness will be fitted in the middle, reinforced by solid polymer bar of 200 mm long at both ends and screws from both sides as lock rail. The section frame will then be fitted in by PVC panels of size 100 mmx25 mm with wall thickness of 1.2 mm (+/- 0.2 mm) and 2 nos. of 6 mm dia bright rod will be inserted horizontally with both side check and nut system and stretches where fixing of hinges / hasp bolt / tower bolt / door ring are required to be strong enough to with stand wear and tear. The rate is inclusive of cost of all materials, labour, and hire of tools and plants and appliancesi/c carriage of all materials taxes and all other incidental charges complete. |
| 34 | Supplying bubble free float glass of approved make and brand conforming to IS: 2835-1987. ii) 4mm thick coloured / tinted / smoke glass. |
| 35 | Supplying,fitting & fixing of 2-Track / 3-Track Aluminium sliding Window of all Aluminium sections viz. window frame (top,bottom & side frame), shutter (top, bottom, side & interlock member) made of aluminium alloy extrusions conforming to IS 733-1983 & IS 1285-1975, annodised conforming to IS 1868-1983, fitted with all other accessories viz. PVC roller, EPDM gasket, maruti lock, screws etc. including labour charges for fitting & fixing of aluminium 2-track/3-track sliding window with fixing of glass (excluding cost of glass) all complete as per architectural drawings and direction of Engineer-in-charge. 10-12 Micron thickness Annodizing film Natural white. |
| 36 | Supplying, fitting & fixing of partly glazed partly panelled or fully glazed single leaf Aluminium swing door of all aluminium sections viz door frame ( top and side frame), shutter( top rail, bottom rail, lock rail, door vertical) , glazing clip made of Aluminium Alloy Extrusions conforming to iS: 733-1983 and IS: 1285-1975, annodized conforming to IS:1868- 1983, fitted with all other accessories viz. EPDM gusket,cleat, angle screws etc. including labour charges for fitting and fixing of aluminium door with door spring,/aluminium hinges, glass / Panel board all complete as per architectural drawings and direction of Engineer-incharge. ( Excluding cost of glass/ panel board, door spring/ Al hinges, door closer, door stoper, handle, tower bolt and locking arrangment etc) 10-12 Micron thickness Annodizing film . Natural white |
| 37 | Supplying heavy duty hydraulic double action floor spring along with top pin/set of pivots conforming to IS: 6315 or any approved make as per direction of Engineer in charge. |
| 38 | Applying Interior grade Acrylic Primer of approved quality and brand on plastered or cencrete surface old or new surface to receive Distemper/ Acrylic emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer's specification and as per direction of the EIC. (In Ground Floor) (a) One Coat i) Water based interior grade Acrylic Primer. |
| 39 | (a) Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc. |
| 40 | (b) Priming one coat on timber or plastered surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc. |
| 41 | (A) Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : (b) On steel or other metal surface : With super gloss (hi-gloss) -(iv) Two coats (with any shade except white) |
| 42 | (a) On timber or plastered surface : With super gloss (hi-gloss) - (iv) Two coats (with any shade except white) |
| 43 | Making one set of scaffolding only for replacing glass panels, painting, uprooting plant and another repairing works of building and S&P works for external works only with 10 cm. dia bamboo as main posts at the rate of 1 metre centre to centre and 7.5 cm. dia bamboo ties @ 0.75 metre apart fitting and fixing with necessary coir, nails etc. as per direction of the Engineer-incharge(This item should be executed only after prior approval of the Engineer-incharge). Firstly, one number to be paid and then labour rate for shifting up to further nineteenth (19) times @ 10% each time to be considered. If necessary further after twenty times of total use, another one number new and labour rate for shifting to be considered accordingly. |
| 44 | Add: SGST 9 % + CGST 9% = 18 % |
| 45 | Labour Wellfare Cess 1% Please Enable Macros to View BoQ information |