| 1 | Earth work in excavation of foundation trenches of drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a load of 75 m, as directed, The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. |
| 2 | (A) Labour for laying 150 mm to 200 mm boulder soling including rough dressing hand packing and ramming down small pieces in the interstics without rolling but including ramming and preparing the bed to proper level and filling up all joints with sandy clay or earth. |
| 3 | Stone Boulder 150 mm of N. Bengal variety |
| 4 | (I) Cement concrete with graded stone ballast (40 mm size excluding shuttering) In ground floor.(B) With N.B. Variety stone metal(a) 1:3:6 proportion |
| 5 | Ordinary Cement Concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any in ground floor as per relevant IS Codes. (ii) River Bazree Ground Floor |
| 6 | Ordinary Cement Concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any in ground floor as per relevant IS Codes. (ii) River Bazree First Floor |
| 7 | Reinforcement for reinforced concrete in all sorts of structures including distribution bars,stirrups, binders etc. initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction (a) For works in foundation and upto roof of ground floor/ upto 4m (i) Tor Steel/ Mild Steel (I) Other than SAIL/TATA/ RINL Ground Floor |
| 8 | Reinforcement for reinforced concrete in all sorts of structures including distribution bars,stirrups, binders etc. initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction (a) For works in foundation and upto roof of ground floor/ upto 4m (i) Tor Steel/ Mild Steel (I) Other than SAIL/TATA/ RINL First Floor |
| 9 | Hire labour charges for Shuttering with hard wood for precast RC Slab curved or straight, and striking out the same including fitting, fixing the precast slab in position with necessary carriage and haulage, hosting etc. complete in all respect. (Only the area in contact to concrete to be measured) Ground Floor |
| 10 | Hire labour charges for Shuttering with hard wood for precast RC Slab curved or straight, and striking out the same including fitting, fixing the precast slab in position with necessary carriage and haulage, hosting etc. complete in all respect. (Only the area in contact to concrete to be measured) First Floor |
| 11 | 125mm thick brick work with 1st class bricks in cement morter(4:1) in ground floor Ground Floor |
| 12 | 125mm thick brick work with 1st class bricks in cement morter(4:1) in ground floor First Floor |
| 13 | Plaster to (wall floor ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and racking out joints including throating, nosing and drip course scaffolding /staging, where necessary (Ground floor). Excluding cost of chipping over concrete surface. (ii) With 1:4 Cement Mortar (a) 20 mm thick plaster |
| 14 | Wood work in door and window frame fitted and fixed in position complete including a protective coat of painting at the contact surface of the frame excluding cost of concrete, Iron Butt Hinges and M S Clamp. (i) Other Local Wood |
| 15 | Panel shutters of door and window, as per design (each panel consisting of single plank without joint), including fitting and fixing the same in position but excluding the cost of hinge and other fittings.In ground floor. (iii) 35 mm thick shutters with 19 mm thick panel of size 30 to 45 cm. (c) Other Local Wood |
| 16 | Glazed shutters of doors, windows, fan light, clerestory windows etc. as per design (with ordinary glass of 7.4kg./sq.m. 3mm. Thick) fitted with putty bed and teak wood bead and nails including fitting and fixing shutter in position but excluding the cost of hinges and other fittings. cost of glass, putty, wooded beads etc.will be paid separately. In ground floor. (ii) 40mm thick shutters |
| 17 | M.S.or W.I. Ornamental grill of approved design jointscontinuously welded with M.S, W.I. Flats and bars of windows, railing etc. fitted and fixed with necessary screws and lugs in ground floor. (i) Grill weighing above 10 Kg./sq.m and up to 16 Kg./sq. M |
| 18 | White Washing including cleaning and smmothening surface thoroughly Three coats on new works only |
| 19 | Applying decorative cement based paint of approved quality after preparing the surface including scraping the same thoroughly (plastered or concrete surface) Two Coats |
| 20 | (b)Priming one coat on timber or plastered surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc |
| 21 | (a)Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc |
| 22 | Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : (a) On timber or plastered surface : |
| 23 | Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : (a) On steel or other metal surface : |
| 24 | M.S. structural works in roof trusses with tubular sections conforming to IS: 806-1957 & IS: 1161- 1958 cnnected to one another with bracket, gusset cleats as per design, direction of Engineer-in-charge complete including cutting to requisite size, fabrication with necessary metal arc welding conforming to IS: 816- 1956 & IS: 9595 using electrodes of approved make and brand conforming to IS:814- 1957, haulage, hoisting and erection all complete.The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour reqired for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural tubular memebrs as specified in relevent IS code in finished work. Payment for gusset, bracket, cleat may be made by adding the actual weight of such items with weight of finished structural members. The rates are considered for a height of erection 8 m. / 2nd floor level from the ground. Add 1.5 % extra over the rate for each additional floor or 4m. beyond the initial 8 m. or part thereof. i) For trusses spanning up to 12.00 m |
| 25 | Galvanised corrugated iron sheet work (excluding the supporting frame work) fitted and fixed with 10 mm. dia J or L hook-bolts, limpet and bitumen washers and putty complete with 150 mm. end lap and one corrugation minimum side lap. (Payment to be made on area of finishedwork)(GCI sheet to be supplied by contractor) (i) In Roof:- a) With 0.60 mm thick sheet |
| 26 | Galvanised iron sheet ridging fitted with necessary bolts, screws, washers etc complete. (225mm end lapping) In roof: with 0.80 mm sheet |
| 27 | Galvanised iron sheets valley gutter with perimeter not less than 750 mm with 225 mm lap each way fitted and fixed with necessary bolts, nuts, screws, etc.complete. Valley gutter made of 0.63 mm. thick sheets. (300mm End lapping) |
| 28 | Supplying Fitting Fixing of iron & net made cage as directed by the department (Double Knotted Wove Wire 1.20 m Ht 17 bars) |
| 29 | Supplying fitting fixing UPVC Pipe with all necessary clamps nails including making holes in walls (110 mm Dia)single socketed 3 metre length. |
| 30 | Supplying and laying chequered tiles of any shade and of approved quality with (1:1.5:3)cement concrete laid in panels or patterns as directed in pavement , footpath etc. including necessary underlay 25 mm thick(avg)cement mortar (1:3) complete in all respect with all labour and materials(Using Cement [email protected]/sqm at back and @2.4kg/sqm for joint filling) 25 mm thick. |
| 31 | Supplying, fitting & fixing 1st quality Ceramic tiles in walls and floors to match with the existing work & 4 nos. of key stones (10mm) fixed with araldite at the back of each tile & finishing the joints with white cement mixed withcolouringoxide if required to match the colour of tiles includingroughening of concrete surface, if necessary or by syntheticadhesive & grout materials etc. With Sand Cement Mortar (1:4)20mm thick @ 2 mm thick cement slurry at back side of tiles using cement @ 2.91kg/sqm and joint filling using white cement slurry @0.20kg/sqm (a) Area of each tile upto 0.09sqm.Other than coloured decorative including white |
| 32 | Supplying, fitting & fixing 1st quality Ceramic tiles in walls and floors to match with the existing work & 4 nos. of key stones (10mm) fixed with araldite at the back of each tile & finishing the joints with white cement mixed withcolouringoxide if required to match the colour of tiles includingroughening of concrete surface, if necessary or by syntheticadhesive & grout materials etc. With Sand Cement Mortar (1:4)20mm thick @ 2 mm thick cement slurry at back side of tiles using cement @ 2.91kg/sqm and joint filling using white cement slurry @0.20kg/sqm (a) Area of each tile upto 0.09sqm.Other than coloured decorative including white |
| 33 | Supplying fitting and fixing EWC(size 7.10x370x810 mm)in white glazed vitreous china ware of approved make supplying fitting and fixing in position complete with necessary nut and bolts) |
| 34 | Supplying fitting fixing Squating plate with integral flushing in white vitreous chinaware of approved make in cement concrete (6:3:1) with jhama chips complete.(450mmx350mm) |
| 35 | Supplying fitting& fixing white vitreous china best quality approved make wash basin with C.I. Brackets on 75 mm x 75mm wooden blocks,C.P. waste fittings of 32 mm dia one approved quality brass C.P. pillar cock of 15 mm dia C.P. chain with rubber plug of 30 mm dia.approved quality P.V.C. waste pipe with C.P. connection (450 mmx 300 mm size) |
| 36 | Supplying ,fitting ,fixing PVC pipes of approved make of Schedule 80 (medium duty)conforming to ASTMD-1785 and threaded to match with GI Pipes as per IS 1239(Part-1)with all necessary accessories,specials,viz,socket,bend,tee,etc. For Exposed Work PVC Pipes 25mm Dia medium quality |
| 37 | Supplying ,fitting ,fixing PVC pipes of approved make of Schedule 80 (medium duty)conforming to ASTMD-1785 and threaded to match with GI Pipes as per IS 1239(Part-1)with all necessary accessories,specials,viz,socket,bend,tee,etc. For Exposed Work PVC Pipes 20mm Dia medium quality |
| 38 | Supplying ,fitting ,fixing PVC pipes of approved make of Schedule 80 (medium duty)conforming to ASTMD-1785 and threaded to match with GI Pipes as per IS 1239(Part-1)with all necessary accessories,specials,viz,socket,bend,tee,etc. For Exposed Work PVC Pipes 15mm Dia medium quality |
| 39 | Supplying P.V.C.water Storage Tank of approved quality with closed top lid (Black) Multilayer (b) 1000 Litre Capacity |
| 40 | Construction of septic tank of different capacities as per approved drawing with 1st class brick work in cement mortar (1:4) including two 560 mm dia R.C.C. manhole cover (heavy Type ) of approved maje supplied ,fitted and fixed in the 10mm thick (R.C.C. (1:1.5:3) top slab with necessary fittings 20 mm with clear water ,removing foreign water from the chamber and including constructing attached inspection pit as per approved drawing For 10 Users (A) with Pakur Variety |
| 41 | Supplying, fitting and fixing 10 litre porcelain low-down cistern conforming to I.S. specification with P.V.C.fittings complete ,C.I.brackets including two coats of painting to brackets |
| 42 | Electrification Works |
| 43 | GST @ 18% |
| 44 | Labour Cess @ 1 % including GST Please Enable Macros to View BoQ information |