| 1 | Construction of Medical Treatment Building at New Panchayat office Cambus in Sooriyanarkovil Panchayat |
| 2 | Earthwork excavation for foundation (for narrow excavation) to full depth as per designed in all soils and sub soils except soft disintegrated rock not requiring blasting and hard rock requiring blasting and bailing water wherever necessary. Refilling the sides of foundation with excavated earth other than sand in layers of well rammed and compacted and depositing the surplus earth in places shown by the departmental officers with an initial lead of 10m and initial lift of 2m and clearing and leveling the site etc. complete complying with standard specification. |
| 3 | Supplying and filling in foundations and basement with filling M- sand in layers not exceeding 15 cm.thick,well watered,rammed and consolidated etc. complete complying with standard specifications. |
| 4 | Plain Cement Concrete 1 : 4 :8 ( one part of cement, four parts of sand and eight parts of hard broken stone ) using 40 mm gauge hand broken hard broken granite stone jelly complying with standard specifications in foundations and basement. |
| 5 | Supplying and erecting Centering and Shuttering for soffits including necessary supports and strutting up to 3 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at about 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specification.(Payment for centering shall be given after the concrete is laid). |
| 6 | Footing, Plinth Beam, etc. |
| 7 | Plain surfaces such as roof slab, floor slab, beams, lintels, loft, sill slab, staircase waist, portico slab and other similar works. |
| 8 | Cement Concrete 1:1-1/2:3 (One Cement, One and a half crushed stone M.Sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc. shall be finished smooth with Cement Mortar 1:3 (One Cement and Three M.Sand) and kraft paper laid over it without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers |
| 9 | Steel - Fe 500 D: Supply, fabrication and placing of reinforcement steel of high yield strength ribbed bars of various diameters and grade conforming to IS 1786 for reinforced concrete work. The work includes recoiling, straightening, cutting, bending, fabricating, and placing in position, at all levels including lead and lift, according to drawings, specifications etc. complete and supply & use of 18G black annealed binding wire double fold to tie the bars in position and providing precast cement/ PVC cover blocks for main reinforcement to ensure specified cover and complete., including all labor charges etc as directed by departmental officers. |
| 10 | Brick work in following Cement Mortar 1:5 using best quality II class table moulded bricks 8\\"3/4 x 41/4\\" X23/4\\" for foundation and basement including curing etc.,complete complying with standard specification.including scaffolding curing cost of reinforcement etc.all complete as per specifications and drawings as directed by the Engineer in-charge. |
| 11 | Foundation basement |
| 12 | Ground Floor |
| 13 | Providing granolithic floor finish of the following thickness with plain cement concrete 1:2:4 (One Cement, Two crushed stone M.Sand and Four aggregate) using 10 to 12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trawl, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers) |
| 14 | Paving the floor with best quality Vertified Tiles of size 600 x 600 x 8mm of approved colour, shade and quality laid in cement mortar 1:3 (one cement and three crushed stone M.Sand) 20mm thick in all floors and the top pointed with the white cement mixed same colour pigments etc., complete complying with standard specification. (The make and brand of the tiles should be got approved by Executive Engineer before use on works) |
| 15 | Dadooing walls with following best approved quality, white / colour glazed tiles of following sizes set in Cement Mortar 1:2 (One Cement and Two crushed stone M.Sand) 10mm thick and pointing the joints with white cement mixed with colouring pigments at the rate of 0.40 Kg. / sq.m. neatly in all floors, curing, etc., complying with standard specification and as directed by the departmental officers. |
| 16 | Providing & applying 12 mm thick cement plaster in CM 1:5 (1 part of cement: 5 parts of sand) to walls internally in single coat at all levels to correct line and level including chicken wire mesh at all joints of brick and concrete surfaces with minimum overlap of 150 mm in all directions, scaffolding, rounding off or chambering of corners, offsets, fin/ bands, projections, etc. and cleaning of surface, raking out joints, roughening of surface, chiseling the undulated surface wherever necessary and curing, etc., all materials and labor complete in all respects including all lead, lift and descent and as directed. |
| 17 | Supplying and applying of two coats of putty of3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [ The rates areinclusive of hire charges for grinding machine |
| 18 | Weathering Course Concrete using best quality broken brick jelly of 20 mm uniform gauge in pure slaked lime ( NO Sand to be used ( over the RCC roof slab in the proportion of brick jelly to lime being 32 : 121/2 by volume laid over in single layer and consolidated to the required slope and finished thickness and beating the concrete with wooden beaters of approved pattern, keeping the surface constantly wet by sprinkling lime, jiggery water etc. complete complying with standard specifications and as directed |
| 19 | Finishing the top of roof with one course of machine pressed tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers. |
| 20 | Supplying and Painting new plastered internal wall surface with two coats of distempering one coat of distemper primer |
| 21 | Supplying and painting the walls with one coat of wall primer and two coats of Exterior emulsion (apex or equivalent) as instructed by the departmental officers including preparation of surface curing, etc., complete in all floors complying with standard specifications (The colour and shade of the cement paint shall be got approved by the Executive Engineer before use of work). |
| 22 | Supplying of steel doors, windows, ventilators etc., with best approved best quality etc., complete complying with standard specifications and as directed by the departmental officers. |
| 23 | Painting new iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with two coats of best approved first quality and colour of synthetic enamel paint over the existing red oxide priming coat in all floors excluding cost of priming coat etc., complete complying with standard specification. (The make, quality and colour of paint should be got approved by the Executive Engineer before use on works.) |
| 24 | Labour Charges for Fixing the Doors inculding all Charges etc.. |
| 25 | Labour Charges for Fixing theSteel Window inculding all Charges etc.... |
| 26 | Supplying and fixing PVC Rain water down fall pipes of following dia meter etc., complete. |
| 27 | Electrification |
| 28 | Wiring 2 x 1.5 sq.mm (22/0.30)PVC insulated unsheathed SC.cu.conductor of 1100 V grade in suitable PVC rigid pipe on wall and ceiling with PVC accessories with TW switch box with in flush with wall covered with hylem sheet of 3 mm thick with painting of suitable colour for concealed PVC light/ fan point (SD No.18) |
| 29 | supply and fixing of 1200mm sweep AC ceiling fan complete with stepped electronic regulator with 300mm down rod on the existing clamp (SD 110) |
| 30 | Supply and fixing of 4'-18W LED tube with fitting inclusive of all charges |
| 31 | Wiring 2 x 1.5 sq.mm (22/0.30)PVC insulated unsheathed SC.cu. conductor of 1100 V grade in suitable PVC rigid pipe on wall and ceiling with PVC accessories with TW switch box with in flush with wall covered with hylem sheet of 3 mm thick with painting of suitable colour for concealed PVC plug point (SD No.38) 5 pin plug point |
| 32 | Supply and run of 2 of 4 sq.mm. (56 / 0.3) PVC insulated SC unsheathed copper conductor of 1100V on 7 / 20 GI bearer wire for service connection mains (SD 62) |
| 33 | Supply and fixing of TNEB meter Board suitable for 32A Single Phase service connection with 32A Fuse unit (500V) 32A neutral link and earth link (1\\" x 1/8\\" Copper flat) on TW plank of size 375mm x 300mm x 19mm with supporting TW reepers of 1\\" thick an either side with painting with suitable bolt and nuts for fixing the TW plank on wall with earth connection and inter connection with 7/20 PVC insulated copper wire from EB meter to fuse unit. (SD No. 125) |
| 34 | TNEB Meter Board |
| 35 | Provision for EB Deposit Charges |
| 36 | Provision for 600mm dia RCC Rings with Cover Slab |
| 37 | Sanitary Work |
| 38 | Supplying and fixing in positon Indian Water Closet (Oriya type) of size 580 x 440mm white glazed earthern ware of approved quality and brand with \\"P\\" or \\"S\\" trap conforming to BIS with crushed stone M.Sandcushion and forming flooring alround the closet using 40mm broken brick jelly in lime concrete 1:2:5 (One lime, Two crushed stone M.Sandand Five brick jelly) 100mm thick and finishing the top to the required slope and including giving necessary connection to CI soil pipes (including the cost of 100mm dia CI pipe for a length of 600mm) by dismantling brick masonry wall / reinforced cement concrete roof / floor slab and making good the dismantled portion to the original condition with leakages etc., complete complying with standard specifications and as directed by the departmental officers. (The water closet should be got approved by the Executive Engineer before use on works). |
| 39 | 160mm dia PVC Pipe 6 Ksc/Cm2 (Below G.L) |
| 40 | Water Supply Wokrs |
| 41 | Supplying and fixing in position best quality and approved make Indian made white / colour glazed earthernware wash hand basin of size 550 x 400mm (with pedestal / without pedestal) with a pair of cast iron brackets, including cost 15mm dia brass CP pillar tap, 32mm dia \\"B\\" class GI waste pipe with rubber plug and chain, 15mm dia GM wheel valve, 15mm brass nipple, 15mm dia nylone connection, 32mm dia CP brass waste coupling including fixing of wash basin using CI brackets on to the wall in position with TW plugs and screws, rubber washers, white lead and giving necessary water supply connection and painting the brackets with two coat of painting over a priming coat of anti-corrosive paint including testing for leakages etc., complete complying with standard specification and as directed by the departmental officers. (The wash hand basin and specials should be got approved by the Executive Engineer before use on works). |
| 42 | Supply and Fixing of 1000 Litre Capacity Sintex Water Tank |
| 43 | 25mm GI Pipe |
| 44 | 20mm GI Pipe |
| 45 | 20mm Brass Tap |
| 46 | Provision for SS Hand Rails |
| 47 | Provision for Name Board |
| 48 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \\"BB\\" for all works in this package} Please Enable Macros to View BoQ information |