| 1 | MECHANICAL WORKS |
| 2 | Providing, laying, jointing, testing and commissioning of C–Class heavy duty GI pipes conforming to IS 1239 (latest revision) with fittings conforming to IS 1239 including all necessary specials such as elbows, tees, reducers, flanges, unions, tapers, bends, nuts, bolts, gaskets etc., including threading and welding wherever required, fixing true to line and level, supporting from wall with suitable MS clamps, hangers or fabricated angle support frames, and providing cement concrete support cubes of size 1’x1’x2’ (approx. 200 Nos.) in M20 grade with embedded MS angle supports duly painted; including surface preparation and painting of above ground pipes with one coat primer and two or more coats of synthetic enamel paint of approved shade; including excavation , sand bedding, laying of underground GI pipe for approximately 60 metres with 2 mm thick anti-corrosive wrapping coating, inserting the same inside suitable diameter RCC Hume pipe for protection, proper jointing and sealing, refilling and compaction; including hydrostatic testing at required pressure and commissioning, complete in all respects as required. |
| 3 | 150 mm diameter |
| 4 | 100 mm diameter |
| 5 | 80 mm diameter |
| 6 | Servicing disel engine pump 50 HP: checking the motor and pump, cleaning the bearing, applying the lubricant etc as required changing the oil, oil filter, air filter, gland packing etc as required |
| 7 | Servicing of 40 HP main pump: The pump, servicing and checking cleaning the bearing, applying the lubricant etc as required |
| 8 | Servicing of 5 HP main pump: The pump, servicing and checking cleaning the bearing, applying the lubricant etc as required |
| 9 | Servicing, cleaning, testing and lubricant of Fire Hydrant Valve |
| 10 | Servicing, cleaning,testing and lubricant of Hose Reel |
| 11 | Servicing, cleaning and arranging of hose box |
| 12 | Servicing, testing and lubricant of 3 way inlet |
| 13 | Servicing, cleaning and lubricant of butterfly valve |
| 14 | Fire NOC renewal, arranging transportation to bring the site station officer, Asst station officer and fire man for inspection etc as required |
| 15 | ELECTRICAL WORKS |
| 16 | Servicing and testing of existing fire alarm panel 4 zone including petty repaires if any required at site. |
| 17 | Servicing and testing of existing manual control point (MCP) . |
| 18 | Servicing, and testing of existing hooter of fire alarm system |
| 19 | Servicing and testing and of existing fire Hydrant Panel including petty repaires if any required at site. Please Enable Macros to View BoQ information |