| 1 | Earth work excavation for foundation and depositing on bank for refilling within an initial lead of 10.00 m and an initial lift of 2.00 in hard stiff clay. Stiff black cotton soil, hard red earth, sales, murrams, gravel, stoney earth, earth mixed with small sized boulders and hard gravelly soil and except hard rock requiring blasting including shoring, strutting, bailing water wherever necessary and all other incidental charges etc., complete SS20B |
| 2 | Plain Cement Concrete 1:4:8 (One Part of cement, Four Part of sand, and Eight Part of Aggregate) mix using 40mm ISS HBG metal from approved Quarry including cost and conveyance of all materials and all labour charges for mixing, laying, compacting and curing the concrete to site and other incidental charges etc., complete. as per standard specification 28 V,VI S25 |
| 3 | Supply and erection of steel centering, shuttering for soffits and sides including necessary support strutting for all RCC works using MS sheets of suitable size of BG 10 stiffened with MS angle of size 25x25x3mm for boarding laid over Silver Oak joists of size 10cmx6.5cm space at 10cm c/cand supported by Casurino Prop 10cm-13cm spaced at 75cm c/c etc., complete |
| 4 | Plain Cement Concrete 1:2:4 (One Part of cement, Two Part of sand, Four Part of Aggregate) mix using 20mm ISS HBG metal from approved Quarry including cost and conveyance of all materials and all labour charges for mixing, laying, compacting and curing the concrete to site and other incidental charges etc., complete. as per standard specification 28 V,VI S25 |
| 5 | Supplying, fabricating and placing in position M.S (or) RTS for all RCC Items, including cost of steel and binding wire with all conveyance and labour charges etc.complete complying with standard specifications - TNBP No:30 |
| 6 | Reinforced Cement Concrete 1:1.5:3 (One Cement, One and half crushed stone sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges, centering and shuttering but including Super Plasticiser, mixing charges for machine mix, laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc. shall be finished smooth with Cement Mortar 1:3 (One Cement and Three Sand) and kraft paper laid over it without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers - machine mix |
| 7 | Providing granolithic floor finish of the following thickness with plain cement concrete 1:2:4 (One Cement, Two M.sand and Four aggregate) using 10 to 12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trawl, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers) |
| 8 | Supply and Fixing Bitumen Pad 12 mm thick of approved quality including cost and conveyance of all materials and all labour charges to site and other incidental charges etc., complete. as per standard specification Please Enable Macros to View BoQ information |