| 1 | Finishing Surface of walls with cement based wall putty (water base)of approved make and finished smooth and even surface to receive painting including cost of scaffolding, staging charges with cost of all materials taxes,labour etc.Complete in all respect as per specification and direction of the engineer-in-charge.(A) Ground Floor |
| 2 | Finishing Surface of walls with cement based wall putty (water base)of approved make and finished smooth and even surface to receive painting including cost of scaffolding, staging charges with cost of all materials taxes,labour etc.Complete in all respect as per specification and direction of the engineer-in-charge.(A) Ground Floor |
| 3 | Distempering two coats with approved shade incl. cost of all material, labour and T&P etc. complete. (A) Ground Floor |
| 4 | Distempering two coats with approved shade incl. cost of all material, labour and T&P etc. complete. (A) First Floor |
| 5 | Weather coat painting two coats with approved shade over a coat of primer incl. cost of all material,T&P and labour etc complete. (A)Ground Floor |
| 6 | Weather coat painting two coats with approved shade over a coat of primer incl. cost of all material,T&P and labour etc complete. (B) First Floor |
| 7 | Painting two coats with approved paint to doors and windows over a coat of primer including cost of all material ,T & P and labour etc complete (For iron work ) (A) Ground Floor |
| 8 | Painting two coats with approved paint to doors and windows over a coat of primer including cost of all material ,T & P and labour etc complete (For iron work ) (B) First Floor |
| 9 | Fixing vetrieied tiles in floors of size 600 mm x 600 mm on 25 mm thick bed of cement morter (1:1) joined with neat cement slurry mixed with pigment to match the shades of the tiles incl. rubbing and polishing complete incl. cost of tile etc all complete.(a)Ground Floor |
| 10 | Fixing vetrieied tiles in floors of size 600 mm x 600 mm on 25 mm thick bed of cement morter (1:1) joined with neat cement slurry mixed with pigment to match the shades of the tiles incl. rubbing and polishing complete incl. cost of tile etc all complete.(B)First Floor |
| 11 | Fixing vetrified tiles in dados, on 12mm th cement plaster (1:3) joined with neat cement slurry mixed with pigment to match the shade of tiles, rubbing, polishing including cost of tiles, conveyance, taxes & labour, T&P and cess etc. complete in all respect as per specification and direction of the Engineer-in-charge(A)Ground Floor |
| 12 | Fixing vetrified tiles in dados, on 12mm th cement plaster (1:3) joined with neat cement slurry mixed with pigment to match the shade of tiles, rubbing, polishing including cost of tiles, conveyance, taxes & labour, T&P and cess etc. complete in all respect as per specification and direction of the Engineer-in-charge(B)First Floor |
| 13 | Cement Concrete (1:3:6) using 4cm size clean H.G. metal of approved quality from approved quarry including hoisting, lowering and laying in layers not exceeding 15cm thick to the required level, ramming watering and curing etc.complete including cost, conveyance, royalty taxes of all the materials required for the work with all labour, T&P and cess etc. complete in all respect as per specification and direction of the Engineer-in-charge.CC for Floor |
| 14 | Fixing chequered tiles in floors on 25 mm thick bed of cement morter (1:1) joined with neat cement slurry mixed with pigment to match the shades of the tiles incl. rubbing and polishing complete incl. cost of tile etc all complete. |
| 15 | 2.5 cm thick grading concrete (1:2:2) on roof slab with 6 mm size hard granite chips .On new work per 1 sqm E.I.C. (A/R P/47 item 17 ) Please Enable Macros to View BoQ information |