Name of Work:- Raising Of Shakti Sagar Mst Surpura Tehsil Degana District Nagaur
Sl. No.
Item Description
1
Cutting & clearance of jungle, bushes, shrubs Ankra/Ipomoea, Juliflora typna etc. on canal and bunds in dry/moist/slushy conditions including disposal as per instructions of the Engineer-in-charge. Cost of wood has been deducted from rates and thus will be property of contractor after cutting. Ordinary
2
Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m including dressing of excavated area and dewatering wherever required complete in all respect Hard / dense soil
3
Providing and Laying in position of Cement concrete Nominal mix (1:3:6) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 40 mm
4
Providing and Laying in position of Cement concrete Nominal mix (1:1.5:3) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto; 20 mm
5
Side shuttering including propping etc. complete (to achieve finish F 2 for :Retaining wall, counterfort, abutment, wing walls up stream or down- stream slope facings of dams and open faces of construction joints etc.
6
Supplying of M.S. reionforcement including labour charges for bending binding and placing in position all reinforcement as per drawing including cost of binding wire and all leads and lifts using. Tor or ribbed bars (IS :1786-1985)
7
Add extra over items of cement plaster/ cement concrete/cc.lining/cc flooring or RCC for providing and mixing Polypropylene/polyester fibres as per IS 16481:2022 or latest revision, 6/12 mm long @ 0.25% (125 gram per 50 kg of cement) or in ratio of as specified by manufacturer specification and direction of Engineer in charge with all leads and lifts.
8
Drilling holes of 35 mm diameter for anchor rods.Upto 1.50 m. depth
9
Labour charges for Fixing of anchor bars in neat cement grout including cost of cement and curing etc. complete
10
Supply of Tor steel anchor bars of required diameter, length and shape at site of work complete.
11
Chipping concrete surface, cleaning the exposed surface of steel and concrete with wire brush, washing with water complete as per specifications excluding scaffolding etc. Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.