| 1 | Repairs to Panchayat Union Middle School Building @ Karai Panchayat |
| 2 | Chipping the wall plastering and roughening the surface including the cost and conveyance of all materials and cost of all labour charges etc., complete., |
| 3 | Pointing Cement Mortar 1:3 (One Cement and Three Crushed stone M.Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers |
| 4 | Plastering in cm 1:5 mix,12mm thick including the cost of all materials, labour charges etc., complete. |
| 5 | Distempering the inner walls with two coats of best quality oil bounded distemper including the cost of all materials, labour charges etc., complete. |
| 6 | Exterior Emulsion two coats with approved quality of snowcem including the cost of all materials conveyances, labour charges etc., complete. |
| 7 | Painting two coats with approved quality of paint over old steel doors and windows including the cost of all materials, labour charges etc., complete. |
| 8 | Painting the black board and low level black board with approved quality of paint including the cost of all materials, labour charges etc., complete. |
| 9 | Towards the provision of rain water pipe arrangement using 110 mm dia 4Kgf/cm2 P.V.C pipe and P.V.C bend. |
| 10 | Construction of Cup board with shutter |
| 11 | Provision for Chappel Rack with Verandha |
| 12 | Provison for Electric Arrangement |
| 13 | Provision for Bala Painting charges |
| 14 | Repairs to Window charges |
| 15 | Provision for Name board charges |
| 16 | Provision for Photo charges |
| 17 | Repairs to Panchayat Union Middle School Building @ Konai Panchayat |
| 18 | Chipping the Concrete and roughening the surface including the cost and conveyance of all materials and cost of all labour charges etc., complete., |
| 19 | Chipping the wall plastering and roughening the surface including the cost and conveyance of all materials and cost of all labour charges etc., complete., |
| 20 | Weathering Course with Brick Jelly including the cost and conveyance of all materials and cost of all labour charges etc., complete., |
| 21 | Finishing the top of roof with one course of machine pressed tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone M.Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers |
| 22 | Paving the floor with kota stone slab of size 600 x 600 of 18 / 20mm (un-polished) in all floors laid in of cement mortor 1:3 (one cement three M.Sand), 20mm thick and pointed with colour cement neatly including polishing with polishing stone and oxalic acid etc., so as to perfectly smooth and glossy and including hire charges for polishing machine and power consumption charges etc. The kota stone slabs and other materials to be used shall be got approved by the Executive Engineer concerned before use on work, etc., complete as per standard speicification. |
| 23 | Plastering in cm 1:5 mix,12mm thick including the cost of all materials, labour charges etc., complete. |
| 24 | Distempering the inner walls with two coats of best quality oil bounded distemper including the cost of all materials, labour charges etc., complete. |
| 25 | Exterior Emulsion two coats with approved quality of snowcem including the cost of all materials conveyances, labour charges etc., complete. |
| 26 | Painting two coats with approved quality of paint over old steel doors and windows including the cost of all materials, labour charges etc., complete. |
| 27 | Painting the black board and low level black board with approved quality of paint including the cost of all materials, labour charges etc., complete. |
| 28 | Provision for Steel Window all charges |
| 29 | Towards the provision of rain water pipe arrangement using 110 mm dia 4Kgf/cm2 P.V.C pipe and P.V.C bend. |
| 30 | Construction of Cup board with shutter |
| 31 | Provision for Chappel Rack with Verandha |
| 32 | Provison for Electric Arrangement |
| 33 | Provision for Bala Painting charges |
| 34 | Repairs to Window charges |
| 35 | Provision for Name board charges |
| 36 | Provision for Photo charges |
| 37 | Repairs to PUE School Building @ Somasamuthiram in Konai Panchayat |
| 38 | Chipping the wall plastering and roughening the surface including the cost and conveyance of all materials and cost of all labour charges etc., complete., |
| 39 | Plastering in cm 1:5 mix,12mm thick including the cost of all materials, labour charges etc., complete. |
| 40 | Distempering the inner walls with two coats of best quality oil bounded distemper including the cost of all materials, labour charges etc., complete. |
| 41 | Exterior Emulsion two coats with approved quality of snowcem including the cost of all materials conveyances, labour charges etc., complete. |
| 42 | Painting two coats with approved quality of paint over old steel doors and windows including the cost of all materials, labour charges etc., complete. |
| 43 | Painting the black board and low level black board with approved quality of paint including the cost of all materials, labour charges etc., complete. |
| 44 | Construction of Cup board with shutter |
| 45 | Provision for Chappel Rack with Verandha |
| 46 | Provision for Bala Painting charges |
| 47 | Provision for Name board charges |
| 48 | Provision for Photo charges |
| 49 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} Please Enable Macros to View BoQ information |