| 1 | 12 kV VCB with floor rolling trolley. Isc: 40 kA and Ir: 1250 A |
| 2 | Supply of VCB with floor rolling trolley and all other necessary accessories as per technical specifications. |
| 3 | Installation, testing and commissioning of 12 kV VCB with floor rolling trolley as per item 1.1 & technical specifications. |
| 4 | 12 kV SF6 filled isolating & earthing switch |
| 5 | Supply of 12 kV SF6 filled isolating & earthing switch and all other necessary accessories as per technical specification |
| 6 | Installation, testing and commissioning of 12 kV SF6 filled isolating & earthing switch as per technical specification |
| 7 | End termination kit rated 11 kV forcables at isolator side |
| 8 | Supply of isolator side end termination kit for 11 kV cables as per technical specification |
| 9 | Installation of panel side end termination kit of 11 kV cables. |
| 10 | RCB Motor Control Center (MCC) |
| 11 | Supply of RCB MCC (I/C: 100 A MCCB, O/G: DOL starter 7.5 kW - 5 Nos, 10 kW - 2 Nos,4P, 63 A MCCB - 1 No, 32 Amp MCCB - 2 Nos), as per technical specification |
| 12 | Installation, testing and commissioning of RCB MCC including termination of all existing cables |
| 13 | RCB Power Control Center (PCC) |
| 14 | Supply of RCBPCC(I/C: 250A, O/G: 100 Amp MCCB - 3 Nos, 63Amp MCCB - 2 Nos, 32Amp MCCB - 8 Nos), as per technical specification |
| 15 | Installation, testing and commissioning of RCB PCC including termination of all existing cables |
| 16 | Jetty Chlorination room Motor Control Center (MCC) |
| 17 | Supply of chlorination panel MCC (I/C: 125A MCCB, O/G: DOL starter 30kW - 2 Nos, 63Amp MCCB - 2 Nos, 32Amp MCCB - 4 Nos, Single phase MCB DB), as per technical specification |
| 18 | Installation, testing and commissioning of chlorination panel including termination of all existing cables |
| 19 | WDPH Motor Control Center (MCC) |
| 20 | Supply of WDPH panel MCC (I/C: 250 A MCCB, O/G: DOL starter 1.5kW - 2 Nos, 5.5 kW - 1 Nos, 7.5kW - 2 Nos, 10kW- 2 Nos, 22kW - 1 No, 16 Amp MCCB - 4 Nos), as per technical specification |
| 21 | Installation, testing and commissioning of WDPH panel including termination of all existing cables |
| 22 | WDPH power control box |
| 23 | Supply of WDPH pump control box (2 LLC, 1 Annunciator, 5 multiplication relays, 50 terminals),as per technical specification |
| 24 | Installation of WDPH pump control box |
| 25 | Supply & installation of WDPH pump Push Button station, with provision on 7 pumps start, stop with indication, as per technical specification |
| 26 | Laying and termination of 12/19 core control cable |
| 27 | Supply and installation of Lightning Discharge receiver for lighting protection system at Jetty, as per technical specification |
| 28 | Supply and installation of down strips and horizontal copper strip 25X3 mm lighting protection system at Jetty |
| 29 | Supply and installation of Underwater (sea) earthing electrode for lighting protection system at Jetty alongwith 20 meters of 25X6 mm Cu strip, as per technical specification |
| 30 | Painting of electrical panels, motors, transformers and other electrical equipment, as per technical specification |
| 31 | Fabrication & installation of enclouser for one panel & one designated area and wall mounting MS platform for 5 kg SMPS charger installation, as per technical specification |
| 32 | Scrap removal including dismantelling, removal and shifting of above mentioned eight nos. of panels/isolator, cables, MS items and packing material to TVS, as per technical specification |