| 1 | Earth work in excavation of foundation trenches or drains in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing,spreading or stacking the spoils within a lead of 75m.as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. |
| 2 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150mm including watering and ramming etc. layer by layer complete. With earth obtained from excavation of foundation |
| 3 | Single brick flat soling picked jhama bricks including ramming and dressing bed to proper level and filling joints with powdered earth or local sand. |
| 4 | Cement concrete with 30mm down graded shingles excluding shuttering. |
| 5 | Plum Concrete work with 40 % Cement Concrete with 30 mm down graded stone metal and 60% stone boulder of size 150 mm and above, placed in position as directed excluding shuttering if any. |
| 6 | Ordinary cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttring and reinforcement, if any, in ground floor as per relevant IS codes. |
| 7 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc. including supply of rods initial straightening and removal of loose rust (if necessary), cutting to requisite length hooking and bending to correct shape placing in proper position and binding with16G black annealed wire at every intersection as per drawing and direction. (a) For works in foundation and upto roof of ground floor/upto 4 m |
| 8 | Hire and labour charges for shuttering with centering and necessary staging upto 4m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs,beams,columns,lintels curved or straight including fitting , fixing and striking out after completion of works(upto roof of ground ground floor) (f) 25 mm to 30 mm shuttering without staging in foundation |
| 9 | 125 mm thick brick work with 1st class bricks in cement morter (4:1) in ground floor |
| 10 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (c) 15 mm thick plaster |
| 11 | M.S. structural works with hollow sections (square or rectangular shape) conforming to IS: 806-1968 & IS:1161-1998) connected to one another with bracket, gusset, cleat as per design, drawing & direction of Engineer-in-Charge complete including cutting to requisite shape & size, fabrication including metal arc welding conforming to IS: 816-1969 & IS: 9595 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete.The rate includes the cost of all M.S. Hollow section, all consumables such as electrodes, gas and hire charges of all tools and plants and labour reqired for execution and all incidental chages (such as electricity, labour insurance) etc. complete.i) For roof truss works |
| 12 | Galvanised corrugated iron sheet work (excluding the supporting frame work) fitted and fixed with 10mm dia J or L hook - bolts, limpet and bitumen washers and putty complete with 150mm end lap at one and one corrugation minimum side lap. In roof . a) with 0.80mm thick sheet |
| 13 | Galvanised iron sheet eaves gutter fitted and fixed with necessary 50mm x 6mm MS flat bar clamps bent to design, bolts, nuts, washers etc. complete. Eaves gutter made of 0.63mm sheet(b) 300 mm wide gutter |
| 14 | Galvanised iron sheet ridging fitted with necessary bolts,screws, washers etc. complete. (225mm end lap) 450mm lapping each way . ( c ) With 0.80mm sheet |
| 15 | Double knotted wove wire 2.1 m height (17 bars) vertical 300 mm apart horizontal spacing starting from 88 mm ending 200 mm top and bottom wire 10g and all other intermediate and upright wire 9g with finished border 2 ply twisted fencing complete including tightening and fixing the same to posts with staples at every bar including cost of cutting and of lapping joints in net as necessary including cost of staples and wove wire.450mm lapping each way . ( c ) With 0.80mm sheet Please Enable Macros to View BoQ information |