| 1 | Part 1: Renovation of North faced tiled roof building in PUES at Balasamuthiram Town panchayatEstimate Amount: Rs.4.98 Lakhs |
| 2 | Earthwork excavation in all clauses of soils and depositing on bank with initial lead and lift for foundation as per ss20B |
| 3 | Best Mangalore tiled roofing over country wood reepers with lime morter border including cost and conveyance of all materials and labour charges etc,complete. (85% New Tiles) |
| 4 | Brick work using country bricks of size 83/4\"x41/4\"x23/4\" in cement mortar 1:5 (One cement and five M.Sand) including curing neat finishing, etc., complete complying with standard specifiction. |
| 5 | Removing and scrapping the Plastered surface including cost and conveyance of all materials & all labour charges etc., complete. |
| 6 | Plastering with cement mortar 1:5 mix to 12 mm thick including cost and conveyance of all materials & all labour charges etc., complete. |
| 7 | Plastering with cement mortar 1:3 mix to 10 mm thick including cost and conveyance of all materials & all labour charges etc., complete. |
| 8 | Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification |
| 9 | Providing granolithic floor finish of the following thickness with plain cement concrete 1:2:4 (One Cement, Two crushed stone M.Sand and Four aggregate) using 10 to 12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trawl, thread lining, curing etc. complete |
| 10 | Towards the cost of Removal of Woodern doors and windows including frames, hinges and fastenings and stacking at site etc.,complete |
| 11 | Supply of New Steel Door of size 1.05x2.40m |
| 12 | Supply of New Steel window of size 1.05x1.60m |
| 13 | Distempering the old walls and ceiling one coat with best oil bound distemper of approved quality including preparation of surfaces (the colour and quality should be got approved by the Executive Engineer before use) the rate includes cost of brushes, high scaffolding charges, neat finishing, cost of brushes etc., complete |
| 14 | Re Painting the walls with Two coats with first class quality Plastic Emulsion paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete |
| 15 | Re Painting old wood work with one coat of best synthetic enamel paint of approved quality, colour including ordinary scrapping and preparation of surfaces (the colour and quality should be got approved by the Executive Engineer before use) the rate includes cost of brushes, high scaffolding charges, finishing neatly etc., complete complying with standard specification and as directed by the Departmental Officer. |
| 16 | Painting the old iron works two coats with syntactic enamel paint of approved quality and colour including ordinary scraping using brushes and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) |
| 17 | Supplying and painting two coats new iron work such as steel doors ventilators, window bars etc., (WITHOUT PRIMER). |
| 18 | Painting two coats with approved Black Oxide for Old Black board Black oxide paint (PWD DATA Rate) |
| 19 | Repairs to Steel doors & Windows Class room 1 |
| 20 | Provision for Name board charges |
| 21 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} Please Enable Macros to View BoQ information |