| 1 | Dismantling brick or stone masonry in lime or cement mortar under 3m. height including stacking the useful materials for reuse and removing the debris within 50m. Lead per 1 cum. |
| 2 | Dismentling and removing 2.5cm thick artificial stone flooring including stacking the useful materials for re-use and removing the debries within 50 mts.lead |
| 3 | Dismentling and Removing Rcc Column ,Beam , Slab Srair case Landing and Lintel Including stacking the Use ful materials For re-use and removing the debries with in 50 mt lead. |
| 4 | Earthwork excavation in hard soil with initial lead and initial lift including dressing and levelling the foundation bed and depositing the excavated earth away from worksite etc complete. |
| 5 | Supplying, filling in foundation and plinth with sand, watered and rammed including cost, conveyance & royality and all taxces of materials cost of all labour with T&P etc. complete.RCC foundation, column bases etc. |
| 6 | Cement concrete (1:3:6) with 40 mm size H.G.H.B. metal including cost,conveyance and royalty etc. |
| 7 | RCC M-20 work with 20mm down grade course aggregate including hoisting and laying. a) Ground Floor |
| 8 | b) 1st floor |
| 9 | Straightening bent up or coiled M.S. rod or HYSD steel (Fe- 415), cutting, bending, cracking, hooking, welding or jointing (if required), the M.S rod or HYSD steel and binding, tying the grills, hoisting, lowering and placing in proper position . a) Ground Floor |
| 10 | b) 1st floor |
| 11 | Brick work with 1st class FLY ASS Bricks 23cmx12cmx8cm having crushing strength not less than 75 kg/cm² with dimensional tolerance ± 8% in cm(1:6) in foundation |
| 12 | Brick work with 1st class FLY ASS Bricks 23cmx12cmx8cm having crushing strength not less than 75 kg/cm² with dimensional tolerance ± 8% in cm(1:6) in superstructure. a) Ground Floor |
| 13 | b) 1st floor |
| 14 | 12mm (½\") thick cement plaster (1:6) finshing smooth to outside smooth surface of brick walls after racking out the joint including watering and curing with cost, conveyance, royalties etc complete .a) Ground Floor |
| 15 | b) 1st floor |
| 16 | 16mm (⅝\") thick cement plaster (1:6) finshed smooth to inside rough surface of 9\"/10\" thick brick walls after racking out the joint including watering and curing with cost and conveyance, royalties etc complete. a) Ground Floor |
| 17 | b) 1st floor |
| 18 | Rigid and smooth centering & shuttering for RCC works including false works and dismantling then after casting including cost of materials complete in ground. a)Pedastal(Ground Floor) |
| 19 | b) Plinth Beam(Ground Floor) |
| 20 | c) Column (Ground Floor) |
| 21 | c1) Column (1st floor) |
| 22 | d) Lintel(Ground Floor) |
| 23 | d1) Lintel (1st floor) |
| 24 | e) Beam(Ground Floor) |
| 25 | e1) Beam (1st floor) |
| 26 | f) Slab(Ground Floor) |
| 27 | f1) Slab (1st floor) |
| 28 | Supplying, fitting and fixing vetrifed tile in floors of size 600mm x 600mm of approved make conforming to IS :13755 laid on 20 mm thick cement motar(1:4) filling joints with white cement of approved quality including cost of all material,labour T&P etc requred for the work all complete as per direction of E.I.C. a) Ground Floor |
| 29 | b) 1st floor |
| 30 | Fixing the tiles in dados skirting risers of steps on on 12 mm thick C.P. (1:3) jointed with neat cement Slurry mixed with pigments to match the shade of the tiles including rubbing and polishing complete a) Ground Floor . |
| 31 | b) 1st floor |
| 32 | 6mm thick cement plaster in cement mortar (1:4) to RCC surface finished smooth including deep chipping and slury treatment including punning including cost, conveyance & royality of materials. a) Ground Floor |
| 33 | b) 1st floor |
| 34 | Priming 1coat with wall cement primer (water bound) including cost,conveyance etc complete. a) Ground Floor |
| 35 | b) 1st floor (inside) |
| 36 | b) 1st floor (outer side) |
| 37 | Finishing wall surface of walls with Acrylic wall putty (Water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes, labour T&P etc complete.a) Ground Floor |
| 38 | b) 1st floor |
| 39 | Wall painting with 2 coats with Plastic emulsion paint of approved shade on new work to give an even shade including cost,conveyance etc complete. a) Ground Floor |
| 40 | b) 1st floor |
| 41 | Wall painting with 2 coats with weather coat of approved shade on new work to give an even shade including cost,conveyance etc complete. a) Ground Floor |
| 42 | b) 1st floor |
| 43 | Providing fitting, fixing of Al. door with OEL anodized Al. door section of 9202 as vertical member, 9201 as top member and 9200 as bottom and middle member and 6 mm plain glass in top portion with 12 mm thick pre-laminated board in bottom portion fixed on door frame by means of tapered clip no. 4660 and the frame to be completed by means of jointing angle no. 1855 including all cost of labour, T & P, hire charges of drilling machine, labour charges etc. complete. a) Ground Floor |
| 44 | b) 1st floor |
| 45 | Supplying, fitting, fixing up window (sliding type) made up aluminium section 151-154, 151-155, as window frame section no. 151-155, 151-153, and 151-167 as shutter frame with 5 mm thick black glass as panel fitted with rubber beading including locking arrangement including all fitting including cost of materials all taxes labour, T&P etc. complete a) Ground Floor |
| 46 | b) 1st floor |
| 47 | Supplying,fitting & fixing of stainless steel of 304 grade in hand railing using 50mm. Dia of 2mm. thick circular pipe with Balustrade of size 32mm.x32mm.x2mm.@ 0.90m.C/C and stainless square pipe bracing of size 32mm.x32mm.x2mm. In 3 rows in stair case as per approved design and specification,buffing,polishing etc. with cost, conveyance, taxes of all materials labour T & P etc. required for the completion in all respect. a) Ground Floor |
| 48 | b) 1st floor |
| 49 | 25 mm thick grading concrete in C.C. (1:2:2) on roof slab with 4.7 mm size H.G. chips including cost,conveyance and royalty etc complete. |
| 50 | Provision for Septic Tank & O.H. Tank |
| 51 | Add for unforseen item like chaja, decorative, , iron grill items etc. a) Ground Floor |
| 52 | b) 1st floor Please Enable Macros to View BoQ information |