| 1 | MM154 KOTTUR PRIMARY AGRICULTURE CO-OPERATIVE SOCIETY LTD. NATCHANDUPATTY THIRUMAYAM TALUK PUDUKKOTTAI DISTRICT |
| 2 | Earth work excavation for foundation. |
| 3 | Sand filling for foundation |
| 4 | Back Filling the RCC Column and Basement Filling by the Excavated earth and crushed stone dust etc in the Layer of 200mm thick and water Consolidation and Compaction including cost of all Labour charges .,etc Complete |
| 5 | C.C.1:4:8:using 40mm HBG stone for foundation and basement |
| 6 | RCC 1:11/2:3 mix using 20mm HBG Stone including materials and all Labour charges etc.,complete |
| 7 | RCC 1:2:4 mix using 20mm HBG Stone including materials and all Labour charges etc.,complete |
| 8 | Brick work with cm 1:5 mix using country bricks including and all labour charges etc.,(Foundation & Basement) |
| 9 | Brick work with cm 1:6 mix for Super structure using country bricks including and all labour charges etc. |
| 10 | Supplying fabricating and placing the grills in position of TMT rods reinforcement grills for all RCC works including cost of steel rods and binding wire (The TMT rods along with the binding wire shall be contractors own cost.) |
| 11 | Centering work from foundation to Roof Level of RC Column ,Grade Beam Plinth Beam ,Lintel Beam ,Roof Beam and RCC Roof Slab work in all works etc., using plane surfaces including strutting 3m height using M.S. plate of size 90cm x 60 cm and 10 gauge stiffened with welded mild steel angles of size 25 x 25 x 3mm laid over silver oak (Country wood) joists of size 10cm x 6.5cm, spaced at about 90cm c/c. and supported by casurina props of 10cm c/c. complying with standard specification. |
| 12 | Special Ceiling Plastering in c.m 1:3 mix Using 10mm thick including and all Labour charges etc.,Complete |
| 13 | Wall Plastering cm1:5 mix 12mm thick including all materials and Labour etc., Outer plastering including parapet inner wall Plastering. |
| 14 | Providing granolithic floor finish of the following thickness with plain cement concrete 1:2:4 (One Cement, Two Crushed Stone Sand and Four aggregate) using 6 to12mm gauge hard broken stone 40mm thick jelly including laying, finishing and the top rubbed smooth with power trowel, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers. |
| 15 | White washing two coats with freshly burnt white shell lime in all floors including cost of lime, blue powder, fevicol type gum, brushes,scaffolding charges, etc., completec complying with standard specification and as directed by the departmental officers. |
| 16 | Paining the walls with 2 coats with first class quality Distemper paint of approved color over a priming cost including through scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty, wherever required and neat finishing etc. complete complying with standard speciation (for inner wall) |
| 17 | Painting the wall two coats with approved weather proof Exterior Emulsion paint over one primer coat on cement plastered wall surface ect., complete complying with standard specification and as directed by the departmental officers. For Outer walls |
| 18 | Weathering course using concrete broken brickly 20mm gauge in pure laked lime over RCC Roof Slab in proportion of 32:12 and Finishing the top of roof with one course of machine pressed Tiles of size 23x23x2 cm of approved quality laid in cement mortar 1:3 (one cement, three sand) mixed with water proof compound at 2% by weight of cement used and pointed with the same mortar etc., complete. |
| 19 | Supplying and fixing 18 gauge Steel Rolling shutters for a clear opening of 2.600m x 2.76m and of approved make including supplying and fixing top hood cover and all other accessories locking arrangements. etc., with one coat of red oxide primer. and two coats of Synthetic enamel paint. |
| 20 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \"BB\" for all works in this package} Please Enable Macros to View BoQ information |