| 1 | Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. As per MORT&H Specification. 305 Sr.No.-3.16 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. (Carted Earth) Excluding GST as per direction of E/I. |
| 2 | Excavation for road way in soil by mechanical means including cutting and transporting the earth to site of embankment/dumping area with lead upto 1000 metres, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections. As per MORT&H Specification. 301 Sr.No.-3.3 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 3 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, MORT&H Specification 401 Sr No 4.1 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 4 | Scarifying the existing bituminous surface to a depth of 50 mm and disposal of scarified material with in all lifts and leads upto 1000 metres. As per MORT&H Specification 305.4.3 Sr No. 3.15 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 5 | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. MORT&H Specification 406 Sr No 4.14 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 6 | Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means. As per MORT&H 502 Sr.No 5.1 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 7 | (Dense Graded Bituminous Macadam Grading 2 )Providing and laying dense graded bituminous macadam with higher capacity HMP using crushed aggregates of specified grading, premixed with bituminous binder V-30 @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause 505 B Sr. No. 5.4. complete in all respects. Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 8 | Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. MORT&H Specification 503-II Sr.No.-5.5 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 9 | Providing and laying bituminous concrete with higher capacity hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder V-30 @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause 507 B Sr.No.-5.5 complete in all respects Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 10 | Supply and laying of NP-3 s/s 350mm dia Hume pipe culvert including cost of hume pipe, cartage, fixing of proper alignment.(new const). Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 11 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. As per MORT&H Specification 2100 Sr. No. 12.4 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 12 | RCC Grade M20 using batching plant transit mixer & Concrete pump MORT&H Specification 1500,1700 & 2100 Sr No 13.05 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 13 | Supplying, fitting and placing HYSD bar reinforcement in Foundation complete as per drawing and Technical Specifications MORT&H Specification 1600,2200 Sr No 13.6 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 14 | Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing MORT&H Specification 601Sr No 6.1 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 15 | Construction of un-reinforced, dowel jointed, plain cement concrete pavement (M-30) over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing As per MORT&H specification 602 Sr No. 6.2 Including all taxes, material, T&P, Machinary, royalty, labour cess complete. Excluding GST as per direction of E/I. |
| 16 | 05 years Maintenance Charge @ 2.5% Routine maintenance of road for 05 years after the completion of work vide GO No. - 17/2024 SA-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 & Latter No. 36890C/RMC/Mool-23-24, Date 17.02.2024 of ENC PWD, Lucknow Rate Excluding Cost of G.S.T.Second year Maintenance Charge @ 0.25% |
| 17 | Third year Maintenance Charge @ 0.50% |
| 18 | Fouth year Maintenance Charge @ 0.75% |
| 19 | Fifth year Maintenance Charge @ 1.00% Please Enable Macros to View BoQ information |