| 1 | Loading, transportation & unloading of complete gear coupling set(from surface), DA-oxygen cylinder from surface to site partly manually and partly with help of haulages, chain pulley block (from 72L/16XD) to site (15XD/58L) partly manually and haulage, mechanical puller(manually) from surface to site. |
| 2 | Pulling out of out of order gear coupling complete from gear box & drive drum shaft after removing of gear box. |
| 3 | Fitting-hammering-grinding-filling of gear coupling complete on gear box. |
| 4 | Fitting-alignment of gear box-drive drum-motor and trial run of the belt conveyor. |
| 5 | Loading, transportation & unloading of 20mtr ISMB-200, 50mtr ISMC-150, 50mtr ISA-65X65X6, DA-oxygen cylinder from surface to 15XD/58L in R-VIIA seam with help of haulages. |
| 6 | Necessary cleaning near loop take up area of 15XD belt. |
| 7 | Necessary Fabrication of worn out loop take up unit of 6 mtr long and Fixed drum unit base frame by-usage of ( ISMB- 200 & 250 joist, ISMC-150 & 125 Channel, IAS-90908 & 65656 angle, Ms plate-20 mm thick) at site |
| 8 | Fittings of loop take-up frame and fixed drum unit at site |
| 9 | Necessary Fabrication of worn out Movable trolley for loop take up unit by using (ISMB- 200 joist & MS plate-20 mm thick) at site |
| 10 | Fitting of loop trolley with 01 no drum at site |
| 11 | Necessary fabrication and fitting of worn out tension arrangement frame by usage of (ISMB- 200 joist, IAS- 65656 angle, Ms plate-20 mm thick) at site |
| 12 | Transporting, Laying, Lapping, Jointing & Tensioning of about 12 mtr. Belting on loop take up and trial run. |
| 13 | Transportation of 60 nos. 1000mm Bottom rollers, 40 nos top roller, 3 nos. decking plate (1.5mX1.5m), 12mm plate (2mX2m), Oxygen and DA cylinder from surface to site at 15XD/58L |
| 14 | Fitting of Bottom rollers after proper alignment of foot stools |
| 15 | Fitting of top rollers after proper alignment of structures |
| 16 | Fitting of decking plates at drive head and tail end |
| 17 | Fitting of striking plate at discharge point after necessary fabrication |
| 18 | Supply of DA cylinder(6.2 CuM/cyl) |
| 19 | Supply of Oxygen cylinder(7.1 CuM/cyl) |
| 20 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |