| 1 | (E/W in Filling with Cartage Soil) Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 ( For carted earth) |
| 2 | (PCC in 1:3:6) providing concrete for plain concrete in open foundations complete as per drawing and technical specifications shedule item no.281 |
| 3 | Brick masonry work in (1:4) cement mortar in foundation complete excluding pointing and plastering as per drawing and technical specifications shedule item no.301A |
| 4 | Providing and laying (CC in 1:2:4) providing concrete for plain concrete in open foundations complete as per drawing and technical specifications shedule item no.279 |
| 5 | Struck pointing with cement mortar consisting of 1 part cement and 2 part of the fine sand of 1.25 fineness modulus on brick work including supply of all materials labour and completion of work shedule item no.574 |
| 6 | 12 mm thick plaster with one part cement and 4 part of approved coarse sand of all materials labour and completion of work shedule item no.584 |
| 7 | R.C.C. (1:1.5:3) cement , coarse sand & 20mm stone grit all completion of the work shedule item no.584 |
| 8 | M.S. in plain work such as R.C.C. and R.B. work shedule item no.504 |
| 9 | Supply & fixing M.S. fabrication work all l/m complete. shedule item no.517A |
| 10 | Supply & fixing galvanized corrugated iron roofing 24 B.W.G. in position including supply of all materials .labour, tools, & plants etc. required for proper completion of the work and including wastage. shedule item no.536 |
| 11 | dismantling of existing plaster I/C all Material, labour T&P etc Complete as per S.I. No. 706 |
| 12 | One Priming Coat and two coat oil Distemper on New work I/C Supply of all Material, labour T&P etc Complete as per S.I. No. 649-650 |
| 13 | One Priming Coat and two coat of superior synthetic enamel paint I/C Supply of all Material, labour T&P etc Complete as per S.I. No. NEW ITEM-1(a)+2 |
| 14 | (BOE) Laying brick soling layer on prepared sub-grade with brick on edging according to lines, graded and cross-section shown on the drawing filling joints with sand and earth, spreading 25 mm thick layer of earth over brick soling, watering and rolling as per Technical Specification Clause 412 |
| 15 | Supplying and fixing of inverter battery, all Labour , material etc complete. (MR) Please Enable Macros to View BoQ information |